Winter Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpm65

Hot Vendors
Note! The SDM_2002001050 Exam is no longer available.

SDM_2002001050 SDM Certification - NI Questions and Answers

Questions 4

Which are the five competence levels used in NSN?

Options:

A.

- beginner

- basic

- intermediate

- advanced

- world-class

B.

- initial

- basic

- intermediate

- advanced

- world-class

C.

- initial

- basic

- intermediate

- professional

- world-class

D.

- initial

- basic

- medium

- advanced

- world-class

Buy Now
Questions 5

Who is responsible to prepare the initial Project Plan for Gate 4 approval?

Options:

A.

Project Manager.

B.

Bid Manager.

C.

Tender Project Manager or PM PDM.

D.

Execution Project Team.

Buy Now
Questions 6

What is the first step a PM needs to do if a KPI, compared to the previous periods, is below the average?

Options:

A.

Organize asap a meeting with project stakeholders.

B.

Analyze if the variation compared to the average is within the same range as previous periods.

C.

Have a serious discussion with the project F&C and give him a final warning to improve the KPI.

D.

Initiate a recovery plan to improve the KPI

Buy Now
Questions 7

Which main steps are required to set up an effective Change Management Process in a project?

Options:

A.

- The change mgmt process is discussed and approved by customer/subcontractor/NSN NI PjM team.

- The change management process is documented and communicated to customer/subcontractor/internally in NSN.

- Follow-up mechanisms defined and agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.

B.

- The change mgmt process is discussed and approved by NSN NI PjM team.

- The change mgmt process is documented and communicated internally in NSN.

- Follow-up mechanisms defined and agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.

C.

- The change mgmt process is discussed and approved by customer/subcontractor/NSN NI PjM team.

- The PM talks about the change management process with all relevant stakeholders internally in NSN and on the customer/subcontractor side.

- Follow-up mechanisms agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.

D.

- The change mgmt process is discussed and approved by NSN NI PjM team.

- The PM talks about the change management process with all relevant stakeholders internally in NSN.

- Follow-up mechanisms agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.

Buy Now
Questions 8

Which of the following is included in the scope statement?

Options:

A.

Cost baseline.

B.

Project quality plan.

C.

Project plan.

D.

Project deliverables.

Buy Now
Questions 9

Customer is responsible for Network Planning but the quality of the Datafill is poor and requires NSN to use own resources to make revisions. What is the best way to manage this additional scope for the project?

Options:

A.

Use the information that comes from the Customer as it is, even if the quality is bad, because the Customer has full responsibility on that.

B.

Recommend to the customer how the quality of the Datafill could be improved and agree with customer how to proceed with Implementation. Inform CT of a potential up selling opportunity for Network Planning Services.

C.

Stop integrations until Customer provides a correct Datafill that can be used.

D.

If the corrections to the Datafill are not too many, make the changes and move on with the Rollout.

Buy Now
Questions 10

What is never included in the cost estimate during the bid phase?

Options:

A.

3rd party software support fees.

B.

Cost for project management.

C.

Standard production costs.

D.

Risk mitigation costs.

Buy Now
Questions 11

Who is responsible to present the project results in the Project Review Meetings?

Options:

A.

Project Manager with support of the CPM.

B.

CPM and F&C.

C.

CPM with support of the Project Manager.

D.

Project Controller.

Buy Now
Questions 12

Which tool must be used to control the Change Management process?

Options:

A.

A Change Management template agreed with the Customer and the IPM Change Management Module.

B.

IPM Change Management Module only.

C.

Any tool, to be defined in the Customer contract.

D.

NELLE.

Buy Now
Questions 13

What are the main responsibilities of the Cost & Progress Manager (EVM)?

Options:

A.

To issue the Purchase Orders in atimely manner to subcontractors.

B.

to prepare the Baseline independently and present to PM for approval prior to project start.

C.

That invoices aretimely processed andto avoid delays to subcontractor payments.

D.

Cost control and monitoring, doing regular reviews with the Project Manager.

Buy Now
Questions 14

In today's project status meeting with the customer, the customer PM stated the following: " The supplier of the transmission network has a huge delay, you can't start with your activities at the moment". How does the PM react?

Options:

A.

Make a re-planning of the project and immediately release the resources.

B.

Start discussions about possible claims immediately in the meeting in order to have them on the table already.

C.

Initiate a meeting with the relevant stakeholders in NSN (CT, SSM's, project members) in order to align the way forward and up sell strategy.

D.

No reaction needed as the resources can be utilised for other projects.

Buy Now
Questions 15

What is NOT a task provided by EVM?

Options:

A.

To highlight a possible need for corrective action.

B.

To forecast project cost and schedule at completion.

C.

To provide cost and schedule variances along the way.

D.

To highlight delays in the invoicing process.

Buy Now
Questions 16

Which of the following is an NI deliverable during sales phase?

Options:

A.

Logistics plan

B.

Project Target Agreement

C.

Care plan

D.

Acceptance procedure

Buy Now
Questions 17

Why are PARD (Project Asset Rotation Days) and TILT (Telecom Implementation Lead-Time) KPI's closely related to each other?

Options:

A.

Because both KPI's are NI project related.

B.

Because PARD is influenced by the TILT KPI (influenced = if one is decreasing the other is also decreasing).

C.

Because both KPI's are CT cash flow related.

D.

Because TILT is influenced by the PARD KPI (influenced = if one is decreasing the other is also decreasing).

Buy Now
Questions 18

Internal acceptance is a milestone that will trigger:

Options:

A.

SAP Billing block released.

B.

SAP Goods Receipt.

C.

Customer invoicing.

D.

Cost Estimation To Completion (ETC).

Buy Now
Questions 19

What is the right timing to review the costs in a subcontractor contract?

Options:

A.

Only when the Customer pushes NSN to reduce costs.

B.

When there is a change in the scope.

C.

Periodically or when Customer asks for price revisions.

D.

When the contractor shows a bad performance.

Buy Now
Questions 20

A Quality Plan must be developed…

Options:

A.

…in complex Projects when NSN needs to work with different service providers.

B.

… during Project Planning as part of the Project Management Plan.

C.

… when performance of subcontractors is affecting the Acceptance.

D.

… when the project is a Turn Key project.

Buy Now
Questions 21

What milestones are used to calculate SILT?

Options:

A.

IS13.1 Main Equipment on site and Last Customer Invoice Trigger.

B.

IS13.1 Main Equipment on site and Provisional Acceptance.

C.

Date of equipment shipped to the site and Date of Invoice Received by the Customer.

D.

IS13.1 Main Equipment on site and Internal Acceptance.

Buy Now
Questions 22

What is the basic source of information for the development of the Quality Plan?

Options:

A.

Project quality and acceptance requirements stated in the current customer contract.

B.

Equipment installation manuals.

C.

Templates from NSN PM Compass.

D.

Experience from previous projects executed with the same Customer.

Buy Now
Questions 23

One of the outputs of scope definition is:

Options:

A.

Work Breakdown Structure (WBS).

B.

Change Management Plan.

C.

Scope management plan.

D.

Formal acceptance.

Buy Now
Questions 24

When does the PM need to update ROLLO with customer/project data?

Options:

A.

After the customer forecast is received.

B.

At year end.

C.

At least once a month, before period cut-off.

D.

Per STP.

Buy Now
Exam Code: SDM_2002001050
Exam Name: SDM Certification - NI
Last Update: Nov 27, 2023
Questions: 160
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 21 Nov 2024