Black Friday Special - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

PMP Project Management Professional (2024 Version) Questions and Answers

Questions 4

In a product development project, the project manager is constantly receiving complaints from stakeholders about functionalities being delivered, but not required by the business departments. The project sponsor wants to know if the project resources are being used effectively.

What should the project manager have done to avoid delivering work that is not adding value to the business?

Options:

A.

Document the stakeholders' needs, review them during the retrospective, and create improvement plans.

B.

Encourage the product owner to meet with the stakeholders and create a product backlog based on their needs.

C.

Ask the stakeholders to document their complaints in change requests.

D.

Define a product scope and ask the stakeholders to not deviate from it.

Buy Now
Questions 5

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?

Options:

A.

Create a framework to justify project execution.

B.

Utilize an agile approach for all upcoming projects.

C.

Create a framework to support project success.

D.

Utilize a predictive approach for all upcoming projects.

Buy Now
Questions 6

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of

completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next

milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

Options:

A.

Organize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation.

B.

Ask the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned.

C.

Ask the more experienced team member privately to take the task and inform the other team members that work has been reassigned.

D.

Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation.

Buy Now
Questions 7

A project manager is assigned to a multiyear project. During project execution, the customer delegates a new representative who contacts the project manager directly with a concern about their participation in status meetings. The representative wants to contact team members directly.

What should the project manager do next?

Options:

A.

Send the new representative the approved project management and communications management plans.

B.

Reach out to the customer directly for assistance in incorporating the new representative into the project management plan.

C.

Meet with the project sponsor to discuss how to incorporate the new representative in the project.

D.

Meet with the new representative to determine their understanding of the project and address their concerns.

Buy Now
Questions 8

A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an

approval from the design department will be needed.

What should the project manager do?

Options:

A.

Meet with the design manager to ask for the necessary approval.

B.

Invite a design team member to the next daily meeting.

C.

Update the issue log and escalate it to the project sponsor.

D.

Replace this iteration deliverable for one without any blockers.

Buy Now
Questions 9

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel

confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product

increment with the product owner now.

What should the project manager do to mitigate this risk?

Options:

A.

Extend the sprint end date in anticipation of feedback from the product owner that will require extra work.

B.

Schedule an additional interim demo with the product owner.

C.

Address the issue as part of the retrospective.

D.

Ask the team to work overtime toward the end of the sprint to meet the original sprint end date.

Buy Now
Questions 10

A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact

project implementation.

What should the project manager do next?

Options:

A.

Meet with the team member to understand their concerns and/or issues.

B.

Convene a team meeting to encourage and motivate the entire team.

C.

Assign an additional resource to help the team member with the tasks.

D.

Ask the team member's functional manager if there are any known issues.

Buy Now
Questions 11

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two)

Options:

A.

Discuss the issue with the external supplier's authority.

B.

Review the lessons learned from similar past projects.

C.

Gather additional information and estimate the impact.

D.

Update the risk log and bring this up in the meeting with the client.

E.

Wait for the client to raise a concern and collect more information.

Buy Now
Questions 12

A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client's needs.

Which factor should the project manager have considered when developing the product?

Options:

A.

Stakeholder's location

B.

Responsibility matrix

C.

Stakeholder's needs

D.

Availability of resources

Buy Now
Questions 13

A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?

Options:

A.

Social media

B.

Email

C.

Meetings

D.

Newspapers

Buy Now
Questions 14

A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for

the project. The customer has informed the project manager to disregard the group as they are not in support of the project.

What should the project manager do next?

Options:

A.

Ask the customer to contact the activist group and let them know the project status and completion date.

B.

Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery.

C.

Obey the directive from the customer since they are funding the project and are the most important stakeholder.

D.

Request the project team disregard all communication from the activist group and continue with their project work.

Buy Now
Questions 15

In a frequently changing project, the project manager discovers a customer requirement change during a daily meeting. What should the project manager do?

Options:

A.

Give the change to the scrum master to investigate how much additional effort the change will require.

B.

Tell the customer that the requirement change will be put into the next project phase if management approves.

C.

Validate the requirement change with the product owner and development team before redefining the scope.

D.

Escalate to management for approval since the change was not included in the original requirements.

Buy Now
Questions 16

An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.

What should the team lead do next?

Options:

A.

Create all of the stories just for the next sprint and skip the epics until the next sprint.

B.

Create the epics at a high level for the requirements and begin grooming sessions.

C.

Create the project charter and statement of work (SOW) to estimate the changes and the scope of the change.

D.

Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.

Buy Now
Questions 17

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.

What should the project manager do first?

Options:

A.

Evaluate the cost of the additional requested work.

B.

Evaluate the impact and submit a change request.

C.

Discuss the requested change with the sponsor.

D.

Discuss the requested change with the team.

Buy Now
Questions 18

A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?

Options:

A.

Determine potential threats regarding compliance with the regulations.

B.

Ask human resources (HR) to assign a compliance specialist to the team.

C.

Validate that the software is compliant with standards and regulations.

D.

Measure the extent to which the project complies with the regulations.

Buy Now
Questions 19

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to

evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4

months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the

following resources:

* Two engineers (monthly salary of US$700 each)

* One project manager (monthly salary of US$1,600)

* Additional estimated monthly expenses of US$2,000

The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house

resources.

How much money will the project manager estimate the company can save?

Options:

A.

US$35,000

B.

US$20,000

C.

US$40,000

D.

US$30,000

Buy Now
Questions 20

A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the

original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.

What should the project manager do to resolve this conflict?

Options:

A.

Give the project team time to work through the issues with the new supervisor.

B.

Ensure the new supervisor takes the lead when being challenged.

C.

Immediately remove the resource from the project team.

D.

Communicate with the resource on the roles and responsibilities of this project.

Buy Now
Questions 21

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

Options:

A.

Recurrent team meetings are planned to control the budget against future uncertainties.

B.

Probabilistic analysis was used to develop the budget to address future uncertainties.

C.

The budget was developed by using the lessons learned from previous project data.

D.

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.

Buy Now
Questions 22

A company is launching a new product that has to be ready before the summer season begins. After the discovery process, the team realizes that the requirements are very uncertain.

What should the project manager do?

Options:

A.

Invite stakeholders to discuss project requirements prioritization.

B.

Register a risk and define a contingency plan to finish the project on time.

C.

Ask to include some business subject matter experts (SMEs) in the team.

D.

Assist the team in proposing a minimum viable product (MVP).

Buy Now
Questions 23

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

Options:

A.

Mitigate the risks that are applicable to the current and following iterations.

B.

Focus on the project deliverables rather than the documented risks.

C.

Agree that any issue can be handled when it becomes a problem.

D.

Acknowledge that the risks will be handled in the corresponding iteration.

Buy Now
Questions 24

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.

Ask the team to raise blockers or impediments in daily meetings.

B.

Prioritize deliverables based on business value and define frequent releases.

C.

Ask the team to challenge the project estimations for a faster delivery.

D.

Prioritize the tasks with high risks to reduce the number of iterations required.

Buy Now
Questions 25

A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project.

How should the project manager recognize high performance?

Options:

A.

Thank the team member privately to avoid conflict among the team members.

B.

Acknowledge the high-performing team member in the next team meeting.

C.

Choose a reward for the team member that aligns with their personal goals.

D.

Ask the sponsor to approve a bonus for the high-performing team member.

Buy Now
Questions 26

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

  • Update the issue log and refer to the resource management plan to address the situation.
  • Ask the team for extra work to fulfill the project commitment.
  • Reduce the scope of the project and inform stakeholders.

Options:

A.

Ask the sponsor for an experienced team member in the company to help the project team.

Buy Now
Questions 27

A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.

What should the project manager do?

Options:

A.

Develop different approaches based on team members’ motivation and ability.

B.

Develop a standard approach to provide feedback to all team members.

C.

Provide intensive oversight to the team members who performed poorly.

D.

Create a new standard performance measure based on project requirements.

Buy Now
Questions 28

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team

member's deliverables do not meet the requirements.

What should the project manager do first?

Options:

A.

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables are

submitted.

B.

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

C.

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework the

deliverables.

D.

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

Buy Now
Questions 29

A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.

Which two actions should the project manager leverage to ensure the team is meeting performance expectations?

(Choose two)

Options:

A.

Hold daily virtual meetings to review progress.

B.

Implement time-keeping software for team members.

C.

Task functional managers to drive accountability.

D.

Utilize a web-based kanban board.

E.

Require a monthly individual status report.

Buy Now
Questions 30

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

Options:

A.

Update the lessons learned report and the risk log to reflect that this risk has materialized.

B.

Revise the project management plan and move the task to a time when the technical resource will be available.

C.

Consult the risk register for an appropriate planned risk response and implement.

D.

Review the business requirement with stakeholders and exclude the task assigned to the technical resource.

Buy Now
Questions 31

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

Options:

A.

Assessed feasibility and impacts

B.

Developed benchmarking

C.

Analyzed stakeholders

D.

Detailed the project charter

Buy Now
Questions 32

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?

Options:

A.

Invite the director to attend the daily standup meetings.

B.

Share this with the team and ask them to develop reports for the director.

C.

Introduce the agile aspect to the director and agree on a solution.

D.

Explain to the director that agile projects have live reports.

Buy Now
Questions 33

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

Options:

A.

Reprioritize the backlog based on value and cost of delay divided by duration.

B.

Switch to a predictive approach to prevent any further delays to completion.

C.

Reprioritize the backlog based on story size and competence availability.

D.

Remove low-value items from the backlog to compensate for the higher cost.

Buy Now
Questions 34

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.

Register an issue and escalate it to the project sponsor.

B.

Invite the stakeholders to discuss a new prioritization.

C.

Estimate the management to replace the customer service manager.

D.

Increase the team capacity to finish the project on time.

Buy Now
Questions 35

A project manager has been approached by the project sponsor about adding to the project scope How should the project manager accommodate this request?

Options:

A.

Update the project team about the change request

B.

Disregard the request since the project scope is finalized

C.

Adjust the project schedule to accommodate the new project scope requests

D.

Create a change request lor the change control board (CCB) to review

Buy Now
Questions 36

During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project

kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.

What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?

Options:

A.

Develop a stakeholder-by-stakeholder engagement assessment matrix.

B.

Send a letter to the stakeholders to inform them about the project scope and start date.

C.

Schedule meetings with key stakeholders in advance to gather feedback on the project scope.

D.

Identify stakeholder rejection as a risk in the project risk register.

Buy Now
Questions 37

During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.

What should the project manager do first?

Options:

A.

Request the team member's manager to find a solution.

B.

Discuss with the team and assess the reasons that led to the delay.

C.

Discuss with senior management and seek their guidance.

D.

Assign more resources form other teams on the late work.

Buy Now
Questions 38

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has

been working on this project for 6 months, and the morale of the team is low due to the schedule.

What can the project manager do to motivate the team?

Options:

A.

Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.

B.

Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.

C.

Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.

D.

Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.

Buy Now
Questions 39

A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager's emails are very harsh.

What should the project manager do to solve this situation?

Options:

A.

Adjust the communications management plan to gain stakeholder trust.

B.

Change the communication mode from emails to meetings to reduce stakeholders complaints.

C.

Determine the level of influence of the stakeholders who are complaining.

D.

Explain 1c the sponsor that the communication model being used is from company headquarters.

Buy Now
Questions 40

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

Options:

A.

Organize an online distribution channel from another country.

B.

Ask the sponsor to authorize the launch and then wait for approval.

C.

Ask the board to use their influence and speed up the approval.

D.

Work with the team to find ways to bypass the regulations.

Buy Now
Questions 41

A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has too many items to allow on-time delivery.

What should the project manager do first?

Options:

A.

Increase the capacity of the team to finish the project on time.

B.

Update the risk register and present a contingency plan to meet the deadline.

C.

Ask the team to propose a minimum viable product (MVP) to meet the date.

D.

Suggest to the customer to reduce the backlog to meet the date.

Buy Now
Questions 42

Some of the more experienced members of a project team have complained about the project manager. The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

Options:

A.

Set up a team building event to bring synergy back to the project team.

B.

Adjust the project manager's management style to better fit senior team members.

C.

Ask for advice on how to be a better mentor to these team members.

D.

Meet daily with each senior team member to monitor project status.

Buy Now
Questions 43

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

Options:

A.

Prioritize the projects, giving higher priority to projects that will increase profit.

B.

Make sure the project is fast tracked so that slipped time lines are recovered.

C.

Request that upper management hire additional staff to support the projects.

D.

Ensure that all of the projects are of high quality and are delivered on time.

Buy Now
Questions 44

A team is delivering features to a customer at every iteration. After completing each iteration, the customer is invited for a review. However, the customer is frequently not

available and the review is often delayed, which results in increased rework for the team.

What should the project manager do?

Options:

A.

Ask the customer to review the deliverables in each iteration based on their availability.

B.

Request the customer to clarify all requirements at the start of each iteration.

C.

Plan ahead and define the best way to review the deliverables with the customer.

D.

Include the customer in daily project activities to gain the required guidance.

Buy Now
Questions 45

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

Options:

A.

Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.

B.

Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.

C.

Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.

D.

Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.

Buy Now
Questions 46

A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed

a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other

contracting jobs because they are not part of the project team.

What should the project manager do first in this situation?

Options:

A.

Report the issue to higher management and seek their direct involvement to complete the job from the contract department.

B.

Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project.

C.

Arrange several meetings with the contract department and ask them to contract the project as it is critical for project success.

D.

Communicate with the contract manager to commit a budget for the resources required for project execution.

Buy Now
Questions 47

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change

in project scope.

How should the project manager respond to this requirement?

Options:

A.

Proceed with the existing company governance policy.

B.

Perform an analysis to assess the impact on the project.

C.

Directly comply with the financial regulations.

D.

Escalate the issue to upper management and let them decide.

Buy Now
Questions 48

A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no

longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects,

and there is no capacity for any developer to take on additional work.

What should the project manager do next to fulfill this resource need?

Options:

A.

Determine resource allocation options based on project priority.

B.

Apply changes to the existing resource allocations and inform the development manager.

C.

Meet with the sponsor to determine how to rebaseline the schedule.

D.

Inform the sponsor of the situation and request an extension of the target completion date.

Buy Now
Questions 49

Drag the items on left side to the matching term within the correct project approach on the right side.

PMP Question 49

Options:

Buy Now
Questions 50

By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the project lead use to handle the situation?

Options:

A.

Informal written communication, such as a friendly reminder

B.

Formal written communication, such as an email with a copy sent to the manager

C.

Informal verbal communication, such as a conversation

D.

Formal verbal communication, such as a conversation at the end of the sprint retrospective

Buy Now
Questions 51

A company is going through structural changes. A couple of people will leave the company as their positions were made redundant. The team members are unhappy as they do not understand why the changes are being made when the project is on track.

What should the project manager do?

Options:

A.

Advise the team to continue their work as planned because the schedule cannot be changed.

B.

Organize a team meeting to discuss the changes and their importance for the company.

C.

Advise the team that the changes were decided by the CEO and must be implemented.

D.

Inform the project sponsor about the team's unhappiness and ask for overtime pay.

Buy Now
Questions 52

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in

a couple of months. The licensing cost is significant.

What should the project manager do next?

Options:

A.

Evaluate the impact of nonrenewal of the license.

B.

Escalate the licensing issue to the product owner.

C.

Add a spike to the backlog for an alternative design.

D.

Raise a change request to secure the renewal.

Buy Now
Questions 53

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?

Options:

A.

Work with the procurement team to find alternative options.

B.

Contact the vendor that supplied similar equipment for a previous project.

C.

Use the existing equipment and replace it later with the new equipment

D.

Ask the project sponsor to expedite the vendor selection process.

Buy Now
Questions 54

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?

Options:

A.

Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.

B.

Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.

C.

Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.

D.

Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.

Buy Now
Questions 55

A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be

engaged in how the project will be executed.

How should the project manager proceed?

Options:

A.

Create an environment where the agreement is reached by a majority vote.

B.

Create an environment where the agreement is reached through discussion.

C.

Establish recurring brainstorming sessions to discuss project issues.

D.

Allow team members to contribute ideas in a stream-of-consciousness mode.

Buy Now
Questions 56

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

Options:

A.

Negotiate a contract change with the subcontractor.

B.

Meet with the client to discuss the issue with the subcontractor.

C.

Inform the subcontractor that they must send the schedule.

D.

Tell the subcontractor to submit a draft schedule.

Buy Now
Questions 57

The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,

which gives the impression that the project is out of control. The project manager has been providing the project's status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.

What should the project manager do first to address this situation?

Options:

A.

Evaluate the communication needs to discover the gaps and adjust the original plan if needed.

B.

Use the contingency reserves to implement fast tracking and improve the schedule key performance indicators (KPIs).

C.

Review the resource breakdown structure (RBS) to request the main stakeholder's manager to replace the stakeholder.

D.

Provide evidence to the project sponsor that the project is on track and the communications have been sent.

Buy Now
Questions 58

A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project

team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.

What should the project manager do?

Options:

A.

Discuss with the team, estimate the effort, and raise a change request.

B.

Discuss with the customer the risks identified and team's concerns.

C.

Ask the team to deliver the functionality on the agreed go-live date.

D.

Ask the customer to go live and add the new functionality in the backlog.

Buy Now
Questions 59

A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts

with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high

performer, the project goals may be negatively impacted if they leave the team.

What should the project manager do in this situation?

Options:

A.

Meet with the developer and ask them to be respectful with the other team members and work together as a team.

B.

Meet with the team members and developer individually to understand the situation and build an action plan accordingly.

C.

Collect the team's feedback and send it to human resources (HR) to resolve the conflict.

D.

Arrange a team-building training session and require all of the team members to attend.

Buy Now
Questions 60

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.

What should the project manager do?

Options:

A.

Raise a change request.

B.

Purchase the application.

C.

Create a decision tree.

D.

Analyze assumptions and constraints.

Buy Now
Questions 61

An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance.

However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives

as planned, but also wants to accommodate new information and changes as the project progresses.

Which project management approach should the project manager select for this project?

Options:

A.

Hybrid

B.

Incremental

C.

Agile

D.

Phased

Buy Now
Questions 62

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

Options:

A.

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.

B.

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.

C.

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.

D.

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.

Buy Now
Questions 63

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Buy Now
Questions 64

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.

What should the project manager have done before the beginning of the project?

Options:

A.

Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.

B.

Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.

C.

Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.

D.

Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.

Buy Now
Questions 65

A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.

What should the project manager do?

Options:

A.

Ask senior management to communicate with these departments.

B.

Hire a project management consultant to help resolve the issue

C.

Convince senior management to introduce rewards to resisting departments.

D.

Understand the user concerns and revisit the stakeholder engagement plan

Buy Now
Questions 66

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

Buy Now
Questions 67

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

Options:

A.

Resource breakdown structure

B.

Work breakdown structure (WBS)

C.

Team charter

D.

Project charter

Buy Now
Questions 68

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Buy Now
Questions 69

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every

iteration.

B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential

information.

Buy Now
Questions 70

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

Options:

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Buy Now
Questions 71

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

PMP Question 71

Options:

Buy Now
Questions 72

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

Buy Now
Questions 73

A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project

and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?

Options:

A.

Request help from human resources to keep the key team members on the project.

B.

Work with the project sponsor to determine an appropriate response.

C.

Ask to meet privately with the senior-level executive to discuss the matter further.

D.

Discuss the incident with the key project team members.

Buy Now
Questions 74

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Buy Now
Questions 75

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Encrypted emails

C.

Videoconferencing

D.

Chat conversations

Buy Now
Questions 76

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

Options:

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Buy Now
Questions 77

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

Options:

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

Buy Now
Questions 78

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Buy Now
Questions 79

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

Options:

A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.

B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.

C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).

D.

Ask the client to initiate a change request to make the director accountable for the

decision.

Buy Now
Questions 80

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

Options:

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Buy Now
Questions 81

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

Options:

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Buy Now
Questions 82

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Options:

A.

Rebaseline the project schedule to absorb the delay.

B.

Report the delay with rectifying actions to the project management office (PMO).

C.

Notify the project steering committee about the cause of the delay.

D.

Report the delay with rectifying actions to the change control board (CCB) for review,

Buy Now
Questions 83

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

Options:

A.

Inform the design team to ensure compliance during the product design phase

B.

Inform the quality team that they need to ensure that the product is in compliance

C.

Ensure that compliance is explicitly mentioned in the relevant requirements

D.

Meet with the team and remind them of the compliance requirements

Buy Now
Questions 84

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

Options:

A.

Consult the risk and issue logs.

B.

Initiate a project change request.

C.

Create a baseline impact assessment

D.

Discuss with the project sponsor.

Buy Now
Questions 85

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.

Procure tools that consume less bandwidth for internet calls.

B.

Record the meeting to share with the team members who were unable to join.

C.

Ask the team members to use chat tools as an alternative to calls.

D.

Determine what the problem is and develop an action plan.

Buy Now
Questions 86

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

Options:

A.

Remove the learn member from the team and hue a more skilled one

B.

Ask the technical lead to provide more training to the team member

C.

Ask the technical lead to discuss performance directly with the team member

D.

Meet with the team member to understand the situation and provide feedback.

Buy Now
Questions 87

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

Options:

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project

Buy Now
Questions 88

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

Options:

A.

Explain to the stakeholder that any modifications require additional budget

B.

Review the missed program deliverables with the project team

C.

Review the project charter for the project approval criteria

D.

Speak with the team's manager to get extra hours from the team

Buy Now
Questions 89

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

PMP Question 89

Options:

Buy Now
Questions 90

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

Options:

A.

Established ground rules before the discussion had started.

B.

Asked stakeholders not to voice their opinions during the meeting.

C.

Invited a high-level sponsor to the meeting to reduce the level of disagreement.

D.

Reinforced that higher-level management has the decision power.

Buy Now
Questions 91

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

Options:

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

Buy Now
Questions 92

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.

Ask the team member to send their concerns in writing.

B.

Empathize with the team member and discuss next steps.

C.

Review the organization's human resources (HR) policy.

D.

Schedule a meeting with the team member for the next work day.

Buy Now
Questions 93

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan.

B.

Review the communications management plan.

C.

Send the CEO one executive summary per week instead of five reports per week.

D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.

Buy Now
Questions 94

In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?

Options:

A.

Facilitate a meeting with the stakeholders and product owner to clarify the new need,

B.

Update the acceptance criteria documentation to clearly reflect what was approved.

C.

Review the new requirement and update all the stakeholders accordingly.

D.

Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.

Buy Now
Questions 95

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

Options:

A.

Support the team member by removing the blockers and impediments.

B.

Allocate the blockers and impediments to the product owner to resolve.

C.

Insist that the person who raised the blockers and impediments take ownership.

D.

Add any blockers or impediments to the risk register,

Buy Now
Questions 96

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

Options:

A.

Document the issues and extend the project delivery timeline.

B.

Convene the steering committee and inform them of the impact to the project.

C.

Prioritize the user stories with issues and have the team resolve them

D.

Update the project management plan and risk management plan.

Buy Now
Questions 97

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.

B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.

C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.

D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,

Buy Now
Questions 98

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

Options:

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

Buy Now
Questions 99

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

Options:

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

Buy Now
Questions 100

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

Options:

A.

Assign an experienced resource to support the team member

B.

Escalate the team member's performance to the project sponsor

C.

Ask the team member to learn the new system as on-the-job training

D.

Issue a change request to extend the project schedule

Buy Now
Questions 101

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.

Ask the leadership team for help obtaining the needed staff.

B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.

Check with human resources (HR) regarding the availability of staff.

Buy Now
Questions 102

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

Options:

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Buy Now
Questions 103

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

Options:

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Buy Now
Questions 104

In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?

Options:

A.

Reassign the task to another member of the team

B.

Support the team member by providing one more resource to complete the task immediately

C.

Ask the team member if there is an impediment and help to remove the blockers

D.

Keep the project sponsor informed about the delay

Buy Now
Questions 105

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

Options:

A.

Process a bank loan to pay the payroll of the third-party supplier.

B.

Reassign resources from other projects to pay the third-party supplier.

C.

Explain the third-party supplier situation to the client and request payment.

D.

Inform the client that the project must be delayed until payment is received.

Buy Now
Questions 106

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

Options:

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Buy Now
Questions 107

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Buy Now
Questions 108

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

Options:

A.

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.

Meet with the client and discuss the project deadlines

D.

Seek approval for more time for rework and resolve the issue

Buy Now
Questions 109

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Buy Now
Questions 110

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.

Advise the teams to follow the company’s existing project management approach.

B.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.

Let a senior team member select the approach that is appropriate.

D.

Insist the teams both follow either a predictive or agile approach.

Buy Now
Questions 111

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

Options:

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Buy Now
Questions 112

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

Options:

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Buy Now
Questions 113

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Buy Now
Questions 114

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

Options:

A.

Check the change management plan

B.

Document the issue in the scope management plan.

C.

Conduct a team brainstorming session to resolve the issue

D.

Check the quality management plan

Buy Now
Questions 115

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

Options:

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.

Inform the senior manager that they will need a new project management plan for this feature,

C.

Complete the most current feature and release the resources for the new feature.

D.

Analyze the impact of this change and present the options to the senior manager.

Buy Now
Questions 116

A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

Options:

A.

Inform the stakeholder that they must level their knowledge with other stakeholders.

B.

Update the risk register with the potential impact and apprise the steering committee.

C.

Inform the project management office (PMO) that the team will use a predictive approach for this project.

D.

Allocate time to mentor the stakeholder in the selected project approach.

Buy Now
Questions 117

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

Options:

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Buy Now
Questions 118

A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?

Options:

A.

Assess and evaluate the team member's skills to ensure alignment to the particular requirement and solution

B.

Reassign the requirement to another team member who may have ideas on how to meet the requirement

C.

Assist by connecting the product owner with the team member to discuss what problem is to be solved

D.

Deprioritize the requirement and assign a task tor it to be restated to provide the necessary clarity

Buy Now
Questions 119

A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?

Options:

A.

Share project documentation in a repository with exclusive access.

B.

Schedule weekly knowledge-sharing sessions with key stakeholders.

C.

Send periodic emails to senior management with the latest project updates.

D.

Keep project artifacts up-to-date and accessible to all stakeholders.

Buy Now
Questions 120

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Buy Now
Questions 121

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities

B.

Conduct serial activities on tasks

C.

Increase the number of standup meetings

D.

Perform tasks in parallel

Buy Now
Questions 122

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Buy Now
Questions 123

What should an agile lead do lo ensure their team is set up for success?

Options:

A.

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.

Schedule sprint meetings and coaching sessions to discuss project-related information

C.

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.

Document team tasks and challenges in order to understand when to step in and help a member of the team

Buy Now
Questions 124

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team

What should the project manager do first to ensure the project is compliant?

Options:

A.

Meet with the team to discuss compliance concerns

B.

Review the organizational process assets (OPAs) for compliance topics

C.

Review the compliance strategy and version history

D.

Meet with the project sponsor to discuss their compliance concerns

Buy Now
Questions 125

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

Options:

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Buy Now
Questions 126

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Buy Now
Questions 127

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

Options:

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on the

project variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

Buy Now
Questions 128

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.

Start executing the project as the scope will be defined and redefined throughout the project.

D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Buy Now
Questions 129

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

Options:

A.

Propose using a compliance review board that will be responsible for approving all

product features prior to their release to the public.

B.

Liaison with the compliance group, making them responsible for understanding the

requirements and keeping them prioritized in the backlog.

C.

Meet with the compliance team and make sure that their requirements are covered in the

definition of done (DoD) for each story.

D.

Ensure that the peer review process also covers compliance requirements, creating a

second layer of security for the project.

Buy Now
Questions 130

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.

What should the project manager do next?

Options:

A.

Escalate the issue to the purchasing department for review.

B.

Evaluate the procurement contract to determine the agreed-upon specifications.

C.

Hire a company in country B to perform a quality check before shipment.

D.

Add an additional task to cut the received part according to the specifications,

Buy Now
Questions 131

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''

Options:

A.

Include the local union representative in the high-power, high-impact stakeholder group

B.

Focus on the sideward stakeholders only and let the organization manage the community.

C.

Build channels to extend communication efforts to the local community

D.

Use the city administration to address communication with the community

Buy Now
Questions 132

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

Buy Now
Questions 133

A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution

What should the project manager do?

Options:

A.

Colocate the team members

B.

Perform team-building activities

C.

Review and reassign tasks

D.

Revisit the communications management plan

Buy Now
Questions 134

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.

Evaluate demonstrated task accountability

B.

Determine the appropriate approach

C.

Analyze team member influence

D.

Identify levels of decision-making authority

Buy Now
Questions 135

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Buy Now
Questions 136

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Buy Now
Questions 137

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Buy Now
Questions 138

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

Options:

A.

Explore the minimum requirements of the product and their feasibility.

B.

Explain the resource constraints of the project to management.

C.

Outsource the management of the product to an external team.

D.

Conduct a detailed risk analysis to highlight the risks in the project.

Buy Now
Questions 139

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Options:

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.

B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.

C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.

D.

Perform a gap analysis on renting in each of the locations.

Buy Now
Questions 140

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

Options:

A.

Allow the most senior team members to decide the time that works for the team.

B.

Reassess the team's hours collaboratively so that the team is not impeded by the issue.

C.

Discuss the lack of dedication with the team member and their functional manager.

D.

Remove the team member from the project team to be fair to the other members.

Buy Now
Questions 141

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

Options:

A.

Ask the team to focus on and deliver only the agreed-upon features.

B.

Request additional budget because additional features are being added.

C.

Encourage the team to continue, as this will eventually help the customer.

D.

Ask the product owner to add the additional features to the requirements.

Buy Now
Questions 142

A project team is implementing a new solution that will be distributed worldwide. Due to a new issue that has a global impact, several government agencies are implementing new regulations that will affect the solution. The project manager must assess and prioritize the impact of these changes on the project scope/backlog.

Which analytical tool can be used by the project manager to define this scenario?

Options:

A.

Political, economic social, technological legal, and environmental (PESTLE)

B.

Strengths, weaknesses opportunities, and threats (SWOT)

C.

Valuable rare, inimitable resources, and organization (VRIO)

D.

Net present value (NPV)

Buy Now
Questions 143

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Buy Now
Questions 144

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

Options:

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Buy Now
Questions 145

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

Buy Now
Questions 146

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Buy Now
Questions 147

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

Options:

A.

Create a change request to extend the project's duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.

Buy Now
Questions 148

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

Options:

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

Buy Now
Questions 149

A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in

innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.

What is the most likely reason for the engineer's refusal to work on the project?

Options:

A.

The engineer did not feel welcome or enjoy working with the other project team members.

B.

The project manager did not follow the normal hiring process with the engineer's functional manager.

C.

The engineer has “project burnout" from working long hours and solving difficult problems.

D.

The project manager did not sufficiently support and recognize the engineer's professional growth.

Buy Now
Questions 150

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Options:

A.

Add 4 additional weeks to the schedule and request additional resources.

B.

Ask the sponsor to obtain a special work permit to continue work.

C.

Review the project management plan to see the impact of the possible delay.

D.

Crash the resource management plan to keep the schedule on track.

Buy Now
Questions 151

A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of

sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.

What should the project manager do?

Options:

A.

Introduce a float.

B.

Adjust the budget.

C.

Adjust the project time line.

D.

Fast track the project.

Buy Now
Questions 152

After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW).

These changes would improve the project outcome.

What should the project manager do next?

Options:

A.

Conduct an audit on the procurement process and inform the vendor about the audit's observations.

B.

Assess the situation as an opportunity for improvement and perform a risk analysis.

C.

Consult the list of selected vendors for the bid and evaluate a possible change of vendor.

D.

Revise the procurement control process to avoid undesired changes that might affect the schedule.

Buy Now
Questions 153

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

Options:

A.

Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.

D.

Schedule meetings with all of the stakeholders to make business decisions when needed.

Buy Now
Questions 154

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government

official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include

aspects that the previous project sponsor did not support.

What should the project manager do next?

Options:

A.

Meet with the new project sponsor to review the current project scope and the requested changes.

B.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.

C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.

D.

Inform the new project sponsor that the new aspects will not be included in this project.

Buy Now
Questions 155

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

Options:

A.

Postpone the meeting and invite a subject matter expert (SME) to join the next meeting.

B.

Continue the meeting and ask the project sponsor and product owner to take their discussion offline.

C.

Postpone the meeting and ask the project sponsor and product owner to take their discussion offline.

D.

Continue the meeting and use facilitation techniques to improve communication within the team.

Buy Now
Questions 156

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not

be able to provide assistance for 1 week.

How should the project manager address this situation?

Options:

A.

Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays.

B.

Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer.

C.

Explore options with the IT department to expedite the necessary repairs based on criticality of the project.

D.

Use project reserves to buy new equipment to avoid an impact to the critical path of the project.

Buy Now
Questions 157

A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.

What should the project manager do?

Options:

A.

Discuss this with the project team and select the appropriate tools.

B.

Inform the project team to continue using the current tools.

C.

Implement the communication tools used by other project teams.

D.

Escalate the issue to the sponsor and ask them to decide.

Buy Now
Questions 158

In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project

manager do next?

Options:

A.

Produce a value-added product for the customer as continuously as possible.

B.

Produce a value-added product for the customer in the beginning of the project.

C.

Produce a value-added product along with the supporting documentation.

D.

Produce a value-added product for the customer in each phase of the project.

Buy Now
Questions 159

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

Options:

A.

Assign another senior team member to coach the team member.

B.

Empower the team member to make decisions.

C.

Mentor the team member on a regular basis.

D.

Address the team member's performance accordingly.

Buy Now
Questions 160

A project manager is assigned to a yearlong project. Before the start of the design phase, a competitor announces that they will release a similar deliverable in 8 months, although with fewer features and functionality.

Which two actions should the project manager take next? (Choose 2)

Options:

A.

Modify the project management plan with an incremental approach.

B.

Evaluate the impact of incremental deliverables.

C.

Reduce the scope items of the final deliverable.

D.

Discuss and review this external risk with the project sponsor.

E.

Update the project artifacts to include this issue.

Buy Now
Questions 161

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?

Options:

A.

Reject the changes and stay the original course as initially agreed with the client.

B.

Review the changes and make the decision based on the project team's recommendations.

C.

Discuss the changes with the client and jointly make the decision on how to proceed.

D.

Review the risk register to see if mitigations have already been outlined for this scenario.

Buy Now
Questions 162

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

Options:

A.

Ask key stakeholders to cancel the project due to the difficulty of executing both deliverables at the same time.

B.

Ask the team to start working on the easiest deliverable first so they gain experience to execute the second deliverable.

C.

Meet with the project sponsor and key stakeholders to assess each deliverable's value to the organization and set execution priorities.

D.

Require that the project team execute both deliverables at the same time, since this was requested and approved in the project charter.

Buy Now
Questions 163

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project

manager do to avoid this in the future?

Options:

A.

Schedule weekly project status meetings with all stakeholders including the customer and internal resources.

B.

Include the project stakeholders’ needs while planning the project communications strategy.

C.

Designate a team member to respond to the emails from these stakeholders.

D.

Include the stakeholders’ emails in all of the project status communications.

Buy Now
Questions 164

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

Options:

A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.

B.

Review the terms of reference of the steering committee to include the vendor management head.

C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.

D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.

Buy Now
Questions 165

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

Options:

A.

Ask the Scrum team members to share retrospectives.

B.

Ask the scrum master to attend the workshops.

C.

Invite the Scrum team members as optional participants.

D.

Invite the Scrum team members as mandatory participants.

Buy Now
Questions 166

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for

providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available

in 2 weeks due to some unforeseen problems.

What should the project manager do next?

Options:

A.

Apply the terms and conditions of the contract with penalties.

B.

Issue a change request to reflect the anticipated date for training.

C.

Help the customer find an alternative location to start the training.

D.

Update the project schedule with the new date for training.

Buy Now
Questions 167

A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project

manager is confused since the entire team is located in the same time zone and believes there are other factors at play.

What should the project manager do next?

Options:

A.

Rectify ground rule violations.

B.

Review performance formally.

C.

Examine the team's virtual needs.

D.

Implement new options.

Buy Now
Questions 168

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are

likely to require this knowledge in the future.

What should the agile project manager do?

Options:

A.

Ask the team member to develop more expertise and become a subject matter expert (SME).

B.

Ask the team member to provide a training session for the rest of the team.

C.

Ask the team member to produce a lessons learned document and share it with the team.

D.

Ask the team member to record highlights the team may want to know.

Buy Now
Questions 169

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?

Options:

A.

Identified the vice president as a stakeholder

B.

Recorded the vice president's concerns in the risk register

C.

Escalated any dissent to top management right away

D.

Shared project boundaries so that everyone was aware of the scope

Buy Now
Questions 170

A senior vice president requested the creation of more agile teams to run projects of varying lengths and complexities in parallel with each other.

This will impact the amount of time the project managers will be able to dedicate to each project. The project managers typically dedicate 50% of

their time to projects regardless of their complexity.

What should the project manager do as a servant leader to help achieve this transformation?

Options:

A.

Review the organizational process assets (OPAs) to evaluate mitigation plans for similar risks.

B.

Create a risk entry regarding the project manager's capacity and develop a mitigation plan.

C.

Empower the team to develop the necessary skills to move the project forward independently.

D.

Issue a change request to hire additional project managers based on the increased workload.

Buy Now
Questions 171

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.

Buy Now
Questions 172

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The

project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.

What should the project manager do?

Options:

A.

Ask the experienced members to lead the junior members to facilitate skill transfer.

B.

Encourage team members to focus on delivering results with their specialized skills.

C.

Organize networking sessions to allow the team members to get to know one another.

D.

Ask the team to self-organize and escalate any issues to the project manager.

Buy Now
Questions 173

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

Options:

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.

Create a status reporting template and share it with all team members before the day ends.

E.

Schedule daily meetings with each team to understand their progress and concerns in detail.

Buy Now
Questions 174

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

Options:

A.

The product owner does not have visibility into what the team has done in the product increment.

B.

The product owner trusts the team and is marking the product as complete.

C.

The product owner has evaluated the product against the definition of done (DoD).

D.

The product owner will release the product to customers without showing them a demo.

Buy Now
Questions 175

A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings.

What should the agile project manager do to engage the stakeholder in the project?

Options:

A.

Present the project management plan to the stakeholder and reassure them that they will receive regular project updates.

B.

Introduce the stakeholder to the project team and invite them to the next iteration review meeting with the IT team.

C.

Build trust with the stakeholder by keeping project commitments and use demo sessions to gather feedback and realign goals.

D.

Use stakeholder mapping to document the level of influence and interest for the next iteration planning meeting.

Buy Now
Questions 176

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

Options:

A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.

Instruct the meeting participants to speak only about blockers during the meeting.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Buy Now
Questions 177

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

Options:

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Buy Now
Questions 178

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

Options:

A.

Formalize the product owner assignment.

B.

Review similar projects in the company.

C.

Set the project's purpose, mission, and vision.

D.

Carry out the product backlog creation.

Buy Now
Questions 179

A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.

What should the project manager do?

Options:

A.

Ask the team to outline their expectations and confirm with them the approach to use for knowledge transfer.

B.

Organize knowledge-sharing workshops and ask one of the senior team members to facilitate them.

C.

Ensure that formal email communication is used when more information is needed to understand the work done.

D.

Hire a technical writer to document the work completed to date and develop a handover document.

Buy Now
Questions 180

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

Options:

A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources

B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted

C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline

D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements

Buy Now
Questions 181

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the

company’s competitive advantage. What should the project manager do?

Options:

A.

Reject all requested changes and bypass the company's change control process.

B.

Encourage the project team to add premium features to impress the client.

C.

Start the process to include the new features of the product on the next iteration.

D.

Allow all requested changes and bypass the company's change control process.

Buy Now
Questions 182

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Options:

A.

Design an updated status report.

B.

Request a meeting with the stakeholder.

C.

Escalate this to the project sponsor.

D.

Forward the project status reports.

Buy Now
Questions 183

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?

Options:

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.

B.

Maintain the same task allocation structure to avoid any disruption in the project team.

C.

Move the developer to another team and look for a replacement developer.

D.

Request that all quality assurance tasks be allocated to the new resource.

Buy Now
Questions 184

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.

Buy Now
Questions 185

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

Options:

A.

Use the team's connections with international colleagues to get early warnings on future changes.

B.

Keep the focus on the priority items while the change goes through the change control process.

C.

Reject the change request since it may negatively impact the project's performance.

D.

Implement the change request as soon as possible to avoid accumulating new scope.

Buy Now
Questions 186

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured that communications were sent to all stakeholders when requirements change

B.

Ensured procurement contracts were able be canceled when situations like this arise

C.

Ensured project requirements were validated and communicated with the procurement team

D.

Ensured changing stakeholder needs and requests were properly monitored

Buy Now
Questions 187

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Options:

A.

Finish to start

B.

Start to start

C.

Start to finish

Buy Now
Questions 188

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

Options:

A.

Organize a meeting with the team and update the work breakdown structure (WBS).

B.

Raise this issue, and review and update the progress report for the next monthly project meeting.

C.

Start the organization's change control process via a change request.

D.

Communicate with an officer in the environmental protection department to check if it is necessary.

Buy Now
Questions 189

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

Options:

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Buy Now
Questions 190

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

Options:

A.

Apply a predictive project management approach.

B.

Evaluate and decide on a phased project management approach.

C.

Implement an adaptive project management approach.

D.

Use a hybrid model to combine predictive and adaptive life cycles.

Buy Now
Questions 191

During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager

react to ensure the project remains successful?

Options:

A.

Focus the discussion on recovery and ways to get back on track.

B.

Act in a way to highlight the criticality of the situation.

C.

Punish the team member for providing negative data that will affect the team's morale.

D.

Thank the team member for raising this issue, log it, and move on to the next topic.

Buy Now
Questions 192

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

Options:

A.

Indicate that on the new technology is the functional manager's responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Buy Now
Questions 193

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.

What immediate corrective action should the project manager take?

Options:

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members' supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

Buy Now
Questions 194

During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.

What should the project manager have done to avoid this situation?

Options:

A.

Determined the appropriate type of incentive for key team members

B.

Conducted frequent monitoring on key team members’ performance during project execution

C.

Distributed the monetary incentive according to the team members’ individual performance

D.

identified the underperforming team members and asked the human resources (HR) department to replace them

Buy Now
Questions 195

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

Options:

A.

Plan a training session for the new team members not familiar with the system.

B.

Communicate the rules and criteria to the team members through email.

C.

Work only with the team members familiar with the system

D.

Document which rules and criteria the new team members are not familiar wit

Buy Now
Questions 196

A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

Options:

A.

Use an agile approach and engage a vendor that delivered well in a previous organization.

B.

Consult the product owner and engage a vendor that is recommended by them.

C.

Consult the development team and engage a vendor that is recommended by them.

D.

Use a formal approach using procurement policies, procedures, forms, and work instructions.

Buy Now
Questions 197

An experienced project team member always points out the issues of other team members during meetings. The other team members feel that

the experienced team member is deflecting their own issues in meetings.

What should the project manager do?

Options:

A.

Arrange separated group meetings to allow everyone to express their opinions.

B.

Review the communications management plan with the team and enforce its implementation.

C.

Prepare an agenda for all future team meetings and facilitate the discussion.

D.

Speak with the experienced team member to discuss the issues in a supportive way.

Buy Now
Questions 198

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?

Options:

A.

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.

B.

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.

C.

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.

D.

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Buy Now
Questions 199

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Schedule the meeting at the end of the day to accommodate everyone.

B.

Ignore the situation since the team member is accomplishing their deliverables.

C.

Reinforce the ground rules for standup meetings with the entire team.

D.

Speak with the team member directly to reinforce the ground rules.

Buy Now
Questions 200

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

Options:

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.

B.

Include project stakeholder expectations and needs while creating project acceptance criteria.

C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.

D.

Discuss project acceptance criteria with the project sponsor before the execution phase.

Buy Now
Questions 201

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

Options:

A.

Use the existing budget for executing the fallback plan and update the baseline.

B.

Add additional resources to the project to fast track certain activities and reduce delays.

C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.

D.

Communicate the delay to stakeholders and maintain the existing budget baseline.

Buy Now
Questions 202

After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?

Options:

A.

Ask management to replace the new sponsor with the previous sponsor.

B.

Request the previous sponsor to discuss changes with the project team.

C.

Explore ways to share the project vision and outcome with the new sponsor.

D.

Find ways to bypass the new sponsor and reach management for support.

Buy Now
Questions 203

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

Options:

A.

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.

B.

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other external

stakeholders.

C.

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.

D.

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to the

government.

Buy Now
Questions 204

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

Options:

A.

Meet with the human resources (HR) department to ask for team support.

B.

Follow the process of the most successful team in the organization.

C.

Compare the team's velocity with other teams in the organization.

D.

Focus on the team's engagement during the next retrospective meeting.

Buy Now
Questions 205

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements.

The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

Options:

A.

Update the communications matrix to ensure that client team member is included.

B.

Submit a change request to cover extra hours associated with project meetings.

C.

Increase the project meeting frequency and duration to allow for the extra work required.

D.

Speak with the client team member about the continuous delays during project meetings.

Buy Now
Questions 206

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.

Ask one of the more experienced team members to support the team member with the task.

B.

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.

Ask the experienced team members to produce a manual on how to complete the task.

D.

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Buy Now
Questions 207

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the

documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

Options:

A.

Create a specific sprint to deliver the project documentation.

B.

Assign a dedicated resource to work on the documentation during the project.

C.

Make documentation a standard part of the definition of done (DoD).

D.

Focus on the documentation after the features are delivered.

Buy Now
Questions 208

A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.

What should the project manager do?

Options:

A.

Allow collaboration to smooth out communication between team members.

B.

Add collaboration tools to the communications management plan.

C.

Escalate these communication challenges to the project sponsor.

D.

Organize a team meeting to resolve the communication challenges.

Buy Now
Questions 209

A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.

What should the project manager do to address this problem?

Options:

A.

Increase the contingency reserves to cover unknown-unknowns.

B.

Implement short cycles for inspection and provide feedback.

C.

Increase the management reserves to convert the known-unknowns.

D.

Create a new risk entry to identify the stakeholder as a detractor.

Buy Now
Questions 210

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

Options:

A.

Inform the project sponsor about the problem faced by the team.

B.

Ask the product owner to write the specifications for the related user story.

C.

Organize an early retrospective with the team to analyze the problem.

D.

Facilitate a problem-solving session with the team to analyze the problem.

Buy Now
Questions 211

A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.

What should the project manager do to address this issue?

Options:

A.

Request that the project team change their task deliverables to reflect the project sponsor's requirements.

B.

Set up a daily standup and request that the project sponsor attend to understand the project's tasks and deliverables.

C.

Ask the project team to compile a project scope document and obtain approval from the project sponsor.

D.

Facilitate a stakeholder alignment session so that the team and project sponsor are in agreement with the deliverables.

Buy Now
Questions 212

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

Options:

A.

Meet with the project finance team to measure market variations and product impact.

B.

Direct the project team to estimate user stories in greater detail.

C.

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.

Request that the project team develop a release plan and roadmap for the project.

Buy Now
Questions 213

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

Options:

A.

Ask the team to focus only on the goal, not on ad hoc meetings.

B.

Coach the project owner about the implications of unplanned meetings.

C.

Discuss the issue with the project owner at the retrospective meeting.

D.

Escalate the situation to management because it is affecting the team.

Buy Now
Questions 214

A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide

any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.

What should the project manager do to ease the situation?

Options:

A.

Talk to the customer and project team member separately to assess the issue and decide on the next steps.

B.

Remove the project team member immediately and assign the pending activities to other team members.

C.

Tell the customer that they do not have the authority to remove project team members.

D.

Ask the project team member to call the customer to apologize for their behavior.

Buy Now
Questions 215

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Options:

A.

Allow the agile team to decide what they are able to deliver in each iteration

B.

Ask the team for additional feedback and add tasks to the task board,

C.

Hold a brainstorming session to identify the root cause of the complaints.

D.

Document the customer's complaints and critical issues in the issue log.

Buy Now
Questions 216

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

Options:

A.

scalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Buy Now
Questions 217

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?

Options:

A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.

B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.

C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.

Buy Now
Questions 218

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.

B.

Archive the survey responses with project artifacts for future projects.

C.

Use the information to restart the project.

D.

Evaluate the information collected on areas of improvement.

Buy Now
Questions 219

A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?

Options:

A.

Set up a meeting with the team to discuss and determine the project's challenges.

B.

Propose a revised project schedule to the sponsor as the delays have affected the time lines.

C.

Schedule a meeting with the sponsor to express the team's frustrations about the data.

D.

Meet with the data suppliers to explain the critical timing requirements of the project.

Buy Now
Questions 220

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

Options:

A.

Ask the vendor to communicate via the established channels.

B.

Invite the vendor to a meeting to discuss the concerns.

C.

Escalate the vendor's lack of responsiveness to the project sponsor.

D.

Proceed with other tasks while awaiting a response from the vendor.

Buy Now
Questions 221

An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.

How should the project manager improve team dynamics?

Options:

A.

Require that all team members be physically present for the weekly project review.

B.

Offer the team member an incentive to stay until the end of the project.

C.

Replace the team member with someone who has similar qualifications and is located closer.

D.

Set up a weekly video conference to monitor the progress of the team member's work.

Buy Now
Questions 222

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

Options:

A.

Reschedule the project taking this new information into account.

B.

Refer to the project's resource management plan.

C.

Ask the project sponsor for external resources.

D.

Create a change request to be validated by the project sponsor.

Buy Now
Questions 223

A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the

obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.

What should the project manager have done to avoid this issue?

Options:

A.

Prioritized blockers on the critical path

B.

Distributed the daily standup meeting agenda beforehand

C.

Followed the quality control measurements

D.

Developed the team members’ competences:

Buy Now
Questions 224

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?

Options:

A.

Request approval from the company director to conduct training for the team.

B.

Ask the senior developer to rewrite all the stories.

C.

Engage with the customer and rewrite all the stories.

D.

Rewrite the stories to include the technical vision of the product.

Buy Now
Questions 225

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

Options:

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

Buy Now
Questions 226

A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became

concerned that the product quality will be sacrificed.

What should the project manager do?

Options:

A.

Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.

B.

Invite the customer to join the daily standup meetings to better understand the product design and progress.

C.

Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.

D.

Invite the customer to join the regular sprint planning sessions to better understand the project's progress.

Buy Now
Questions 227

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.

Encourage both team members to meet as soon as possible and resolve the problem

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Report the disruptive team member to the human resource (HR) department.

Buy Now
Questions 228

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

Options:

A.

Understand the customer's perspective and provide mentoring on agile mindsets.

B.

Call for an internal team retrospective and create an improvement action plan.

C.

Ask the customer to work with the product owner to prioritize all requests.

D.

Work with the team to receive customer directions and improve the process.

Buy Now
Questions 229

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

Options:

A.

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.

B.

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reaction

time.

C.

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.

D.

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.

Buy Now
Questions 230

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

Buy Now
Questions 231

A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?

Options:

A.

Utilize a uniform communication structure across all groups.

B.

Define and direct communication to influential stakeholders.

C.

Describe the four groups in the project stakeholder matrix.

D.

Develop and define a communication strategy for stakeholders.

Buy Now
Questions 232

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

Options:

A.

Schedule a one-on-one meeting with the functional manager to prove the project is on time

B.

Listen carefully and show understanding of the growing needs of the functional manager.

C.

Admit that the functional manager is right and promise to rectify the situation immediately.

D.

Show the functional manager that the progress is on time based on the schedule.

Buy Now
Questions 233

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

Options:

A.

Inform the functional manager that self-organization includes task allocation.

B.

Confirm with the team members that the functional manager is responsible for the delivery.

C.

Ask the product owner to clarify the roles and responsibilities of the project team.

D.

Inform the functional manager that task allocation is the responsibility of the product owner.

Buy Now
Questions 234

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

Options:

A.

Foster knowledge sharing and coaching among team members.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Seek an external expert to review the framework.

Buy Now
Questions 235

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

Options:

A.

Performed a stakeholder analysis when the sponsor joined the project

B.

Held a governance meeting to review the project increment

C.

Conducted a product iteration review with the new project sponsor

D.

Escalated the issue to ensure the increment would be approved

Buy Now
Questions 236

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

Options:

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Buy Now
Questions 237

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

Options:

A.

Convene an impact analysis meeting.

B.

Escalate the issue to the product owner.

C.

Consult the communications management plan.

D.

Review the stakeholder register.

Buy Now
Questions 238

A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team

members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?

Options:

A.

Avoid conflict and let the team self-organize on how they want to work on the project tasks.

B.

Ask the project sponsor to provide team members with a project direction regarding outcomes.

C.

Set short-term goals in order to create a winning culture internally and praise team members for achieving them.

D.

Escalate the situation to the steering committee and request that more time be allotted to the project.

Buy Now
Questions 239

A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.

What should the project manager do?

Options:

A.

Invite the sales manager to the next sprint meeting to clarify requirements.

B.

Create a new item in the sprint backlog to determine the appropriate algorithm.

C.

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

D.

Request a meeting with the product owner to help clarify the user story.

Buy Now
Questions 240

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

Options:

A.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver

value incrementally.

B.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the

project.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the end

of the project.

D.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

Buy Now
Questions 241

An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.

What should the servant leader do?

Options:

A.

Escalate this to the project director for a resolution.

B.

Escalate this to the agile lead of the second team.

C.

Review the process and remove the impediment.

D.

Remove the certification need from the project scope.

Buy Now
Questions 242

A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to

reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project

manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide

upon the most effective way to communicate progress.

What should the project manager do?

Options:

A.

Send weekly emails to each stakeholder providing them with the project's progress.

B.

Ask the project sponsor to disseminate project progress across the organization's stakeholders.

C.

Set up an intranet site and allow stakeholders to access the relevant project information.

D.

Divide up the organization among the project team to provide direct project updates.

Buy Now
Questions 243

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

Options:

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Buy Now
Questions 244

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

Options:

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

Buy Now
Questions 245

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

Options:

A.

Use interpersonal skills to expedite the issue.

B.

Send a gentle reminder to the technical service team.

C.

Update the issue log with the status and priority.

D.

Issue a formal warning to the technical service team.

Buy Now
Questions 246

A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?

Options:

A.

Meet with the functional managers to align the expected frequency and results reporting for the team members.

B.

Provide performance feedback to the learn members' functional managers at the end of the year.

C.

Assure team members that this project is a high priority for the company and they will be evaluated accordingly.

D.

Request to be made responsible for the performance plans of those on this project team

Buy Now
Questions 247

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

Options:

A.

Forward the client's request to management as a change request to get formal approval.

B.

Document the information in the meeting minutes and share it with the project stakeholders.

C.

Draft a contract change with the desired scope changes and send it to the client for approval.

D.

Finish the current monthly release as it was planned and replan for the future months.

Buy Now
Questions 248

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.

Study and determine the appropriate leadership style suitable for the team.

B.

Hire a project team leader who can influence the project team members.

C.

Schedule a meeting and communicate the performance concern to the team.

D.

Apply an agile approach to help improve team performance.

Buy Now
Questions 249

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

PMP Question 249

Options:

Buy Now
Questions 250

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

Options:

A.

The organizational process assets (OPAs) have been updated.

B.

The contractual deliverables of the project have been accepted.

C.

It The handover and deliverable acceptance have been completed.

D.

The lessons learned sessions have been conducted.

Buy Now
Questions 251

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Options:

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Buy Now
Questions 252

A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.

What should the project manager do In this scenario?

Options:

A.

Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.

B.

Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.

C.

Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,

D.

Reject the work from this team's backlog and ask the product owner to add It to another team's backlog.

Buy Now
Questions 253

A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.

What should the project manager do to help the team and the customer?

Options:

A.

Manage the risks associated with the proposed approach.

B.

Assist the team with identifying the minimum viable product (MVP) to validate assumptions.

C.

Coordinate with the business unit to get detailed requirements.

D.

Work closely with the marketing team on market research and product segments

Buy Now
Questions 254

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

Options:

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.

B.

Request help from the project sponsor to get support from the sales agents.

C.

Escalate the issue to senior management to gain team buy-in

D.

Explain the change benefits to the sales agents' manager to get their support.

Buy Now
Questions 255

A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.

What should the project manager do?

Options:

A.

Escalate the issue to the project sponsor and seek their immediate intervention.

B.

Assign the unallocated tasks to the functional role and then reallocate when the resources are available.

C.

Assign the unallocated tasks to the project management office (PMO) manager and reallocate when the resources are available.

D.

Ignore the unallocated tasks for now and reallocate when the resources are available.

Buy Now
Questions 256

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Buy Now
Questions 257

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

Options:

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Buy Now
Questions 258

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?

Options:

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

Buy Now
Questions 259

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

Buy Now
Questions 260

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

Options:

A.

Escalate the issue to the project sponsor, as the decision to add the component brings

many benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures that

led to the decision to add a component that was not compatible with the production

line.

C.

Meet with the operations manager to explain the background for the change and

understand the operation manager's concerns about the change.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that the

project may deliver late and over budget due to manufacturing difficulties.

Buy Now
Questions 261

Toward the end of a protect the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan

B.

Review the quality management plan

C.

Review the requirements traceability matrix

D.

Review the work breakdown structure (WBS)

Buy Now
Questions 262

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

Options:

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

Buy Now
Questions 263

Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.

What should the project manager do to resolve this issue and help the team move on to the next iteration?

Options:

A.

Postpone the selection of the technology used until more information is gathered

B.

Suggest their own approach to solve the issue and ask the team to follow it

C.

Call for an open dialogue which the team will arrive at through consensus

D.

Allow the team to decide since the teams should be autonomous

Buy Now
Questions 264

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder's team is unhappy with the results to date.

What should the project manager do?

Options:

A.

Put the new requirements in the backlog with high priority and implement the

requested changes.

B.

Put the new requirements in the backlog and submit a formal change request for

approval.

C.

Put the new requirements in the backlog and let the product owner check their value

and priority.

D.

Put the new requirements in the backlog with low priority and implement the requested

changes.

Buy Now
Questions 265

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

Options:

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

Buy Now
Questions 266

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

Options:

A.

Update the issue log and review the lessons learned register for options

B.

Implement conflict resolution to accommodate the team's needs

C.

Implement decision-making techniques to advance the stones

D.

Empower the team to self-organize and make their own decisions

Buy Now
Questions 267

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp

Options:

A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet

B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine

C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers

D.

Meet with the key stakeholders to identify the proper product concept for the development team

Buy Now
Questions 268

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Buy Now
Questions 269

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

Options:

A.

Evaluate the possibility of managing this project using a predictive approach.

B.

Submit a change request for a new team that has agile experience.

C.

Mentor the team to explain agile principles and create a shared understanding.

D.

Hire a functional manager who is familiar with agile methodologies.

Buy Now
Questions 270

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

Options:

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Buy Now
Questions 271

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

Options:

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Buy Now
Questions 272

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

Options:

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

Buy Now
Questions 273

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

Options:

A.

Define clear guidelines on how decisions should be made under the new

organizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance of

accountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up the

team's velocity.

Buy Now
Questions 274

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

Options:

A.

Perform an impact analysis with subject matter experts (SMEs).

B.

Inform the government representative about the impact of the separate project.

C.

Implement a change request to increase the budget and schedule.

D.

Consult and update the risk register with the project stakeholders.

Buy Now
Questions 275

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

Options:

A.

Escalate the issue from the IT team to management and get the validation prioritized

B.

Work with the IT team to prioritize the validation and release of the new features

C.

Deliver the features when the IT team is able to validate them

D.

Request the IT team to immediately release the product and then validate the features

Buy Now
Questions 276

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Buy Now
Questions 277

On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.

How should the project manager set up communications?

Options:

A.

Inform the client that all communications moving forward will go through the project manager

B.

Ensure that the communications management plan covers contractual obligations

C.

Consult the communications management plan from a recent project that has been closed

D.

Update the communications management plan to allow the subcontractors to communicate directly with the client

Buy Now
Questions 278

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

Options:

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Buy Now
Questions 279

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

Options:

A.

Refer to the stakeholder engagement plan.

B.

Set up a conference call for all stakeholders.

C.

Refer to the communications management plan.

D.

Send an email to all stakeholders.

Buy Now
Questions 280

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

Options:

A.

Request a change in the contract in order to add the deliverable

B.

Add this deliverable to the requirements traceability matrix

C.

Terminate the contract and commence the closeout process

D.

Look to see if the deliverable is described in the statement of work (SOW)

Buy Now
Questions 281

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

Options:

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members' manager and schedule a meeting to discuss the details of this assignment

Buy Now
Questions 282

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

Options:

A.

Document the new stakeholders' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Buy Now
Questions 283

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

Options:

A.

Incremental

B.

Predictive

C.

Hybrid

D.

iterative

Buy Now
Questions 284

A project manager has experience working with a specific provider that has been

requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

Options:

A.

A. Hire resources to obtain knowledge about the provider's specific capabilities.

B.

B. Add penalty clauses to the contract and update the risk register.

C.

C. Encourage the provider to work overtime with no additional costs to the project.

D.

D. Contract another provider with less experience and give them a chance to provide the deliverables.

Buy Now
Questions 285

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.

What should the project manager do?

Options:

A.

Provide a software for instant messaging.

B.

Document all information on the team wiki.

C.

Promote the use of remote site syndication.

D.

Facilitate regular conference calls.

Buy Now
Questions 286

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

Options:

A.

Approach the stakeholder to address the concerns.

B.

Consult the risk management plan.

C.

Escalate the issue to the project management office (PMO).

D.

Refer the stakeholder to the project sponsor.

Buy Now
Questions 287

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?

Options:

A.

Update the risk register and implement the approved risk response plan for quality

deviations.

B.

Identify the resources that were responsible for the deliverable and request a team

development plan.

C.

Update the issue log, identify the involved stakeholders, and assign resources to the

corrective actions.

D.

Submit a change request to update the project quality requirements for the involved

project deliverable.

Buy Now
Questions 288

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

Options:

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Buy Now
Questions 289

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

Options:

A.

Become a servant leader by supporting team collaboration and removing impediments

B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.

introduce new communication tools to the project team members

Buy Now
Questions 290

A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?

Options:

A.

Inform the project steering committee of this constraint.

B.

Inform the project team and create a spike for the next Iteration.

C.

Inform the legal department that the project scope will be updated.

D.

Inform the product owner that the project will continue as planned.

Buy Now
Questions 291

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

Options:

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

Buy Now
Questions 292

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

Options:

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

Buy Now
Questions 293

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

Options:

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

Buy Now
Questions 294

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

Options:

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working as

expected.

Buy Now
Questions 295

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

Options:

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Buy Now
Questions 296

A project manager is assigned to a new water treatment plant project that has been

delayed for many years. It is revealed in the project charter that the sponsors of this project

are from three different business units. This is the first time the sponsors have ever

implemented such a project.

What should the project manager do?

Options:

A.

Establish mentoring and coaching sessions.

B.

Review the knowledge repository for similar projects.

C.

Schedule the project kick-off meeting immediately.

D.

Meet with the project sponsors to align expectations

Buy Now
Questions 297

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

Options:

A.

Ask human resources (HR) to coordinate another activity.

B.

Reassess the team situation and provide a proper solution.

C.

Inform HR about the situation and ask for support.

D.

Meet with the team to explain that conflicts must be addressed and solved.

Buy Now
Questions 298

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

Options:

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

Buy Now
Questions 299

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

Options:

A.

Assign this member to facilitate the next meeting to ensure project team collaboration.

B.

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.

C.

Review and update the project ground rules to make meeting attendance mandatory.

D.

Understand the reason for the team member's absence and encourage them to attend future meetings.

Buy Now
Questions 300

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

Options:

A.

Escalate the situation to the engineer's manager

B.

Request external training for the engineer

C.

Request external training for the engineer and designer

D.

Allow the engineer and designer to cross-train with each other

Buy Now
Questions 301

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

Options:

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives

B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders

C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project

D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable

Buy Now
Questions 302

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

Options:

A.

Ask the team to assess whether the product specification can be expressed in user

stories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities to

deliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for the

project due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for the

project in order to participate in iterative planning and reviews.

Buy Now
Questions 303

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

Options:

A.

Company's historical organizational project artifacts

B.

Company's project responsibility assignment matrix (RAM)

C.

Company's resource management plan

D.

Company's resource calendars

Buy Now
Questions 304

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

Options:

A.

Develop project onboarding guidelines for the team members assigned to the project.

B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders to

participate.

C.

Ensure that lessons learned are considered as part of the project schedule

decomposition.

D.

Confirm that no conflicts exist in resource calendars with assigned activities on other

projects.

Buy Now
Questions 305

A project manager is assigned to deliver an innovative solution that is part of a

brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.

How should the project manager bridge the gap and ensure the project delivers the expected

business value?

Options:

A.

Determine the critical requirements.

B.

Document the risks and mitigations.

C.

Define the project schedule.

D.

Create a project scope statement.

Buy Now
Questions 306

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal and

external resource requirements.

B.

Commit each team member's time and deliverables and aim for overall project

completion.

C.

Continue the project implementation without the site engineers to ensure the schedule

is maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Buy Now
Questions 307

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?

Options:

A.

Projects with the least duration

B.

Projects that maximize the business value

C.

Projects with maximum revenue generation

D.

Projects with the least associated risks

Buy Now
Questions 308

A project team delivered a critical deliverable to the customer. The customer

complained that the maintenance manual was not included.

What should the project manager do next?

Options:

A.

Submit a change request to include the manual.

B.

Add the needed manual and update the risk log.

C.

Review the stakeholder engagement plan.

D.

Review the terms and conditions of the contract.

Buy Now
Questions 309

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Buy Now
Questions 310

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

Options:

A.

Explain to the management team that reporting and management dashboards are not effective agile practices

B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant

C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)

D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting

Buy Now
Questions 311

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

Options:

A.

Review the backlog to reschedule the deliverable for a later iteration.

B.

Engage with stakeholders directly to review the iteration process.

C.

Determine whether other cross-functional team members are able to take over the

work.

D.

Go to management and ask to hire a new external developer.

Buy Now
Questions 312

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

Options:

A.

Send an email update to existing team members about the addition of the new team

members.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Buy Now
Questions 313

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

Options:

A.

Document the issue in the issue log and escalate to the project sponsor

B.

Inform the project sponsor and suggest canceling the project

C.

Review the project goals and eat criteria m the project charter

D.

Ask the leader of research and development to decide on next steps

Buy Now
Questions 314

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

Options:

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.

Buy Now
Questions 315

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

Options:

A.

Share unsuccessful results from previous projects with a similar scope

B.

Provide the failed test results along with the agreed-upon acceptance criteria

C.

Show that the acceptance criteria were changed by the vendor without approval.

D.

Document in the risk log that the issues in the system were already identified

Buy Now
Questions 316

During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?

Options:

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Force/direct

D.

Collaborate/problem solve

Buy Now
Questions 317

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

Options:

A.

Issue log

B.

Lessons learned register

C.

Stakeholder engagement plan

D.

Risk register

Buy Now
Questions 318

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

Options:

A.

Replace the team member immediately to maintain a good relationship with the

functional manager.

B.

Discuss the issue with the functional manager to understand the reason for the

complaint.

C.

Support the team member and provide documentation to the functional manager

proving their performance.

D.

Protect the team member and ask the project sponsor to minimize any external

interruptions.

Buy Now
Questions 319

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

Options:

A.

Contract negotiation

B.

Team assessment

C.

Mentoring and coaching

D.

On-the-job training

Buy Now
Questions 320

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

Buy Now
Questions 321

A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.

How should the project manager address this?

Options:

A.

Consult the previous project manager to discuss how they managed these questions.

B.

Ensure all engineers are aware that questions should only be submitted in their weekly reports.

C.

Email the company vision to the engineers and tell them they need to meet deadlines

D.

Reinforce to all engineers the company vision of a safety-first approach to project activities.

Buy Now
Questions 322

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

Options:

A.

Asking and listening

B.

Being collaborative

C.

Managing expectations

D.

Building trust

Buy Now
Questions 323

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

Options:

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Buy Now
Questions 324

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

Options:

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

Buy Now
Questions 325

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

Options:

A.

Review the communications management plan with the team members.

B.

Remind the team members to follow the team charter.

C.

Motivate the team members to speak freely in the meeting.

D.

Arrange a team-building activity to involve all team members.

Buy Now
Questions 326

A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?

Options:

A.

Continue production processes and plan to discuss changes at the next annual target review meeting.

B.

Begin a marketing campaign to sell alternative packaging after the 12-month period ends.

C.

Inform management of the new law as an opportunity to expand market share and share the proposed products

D.

Organize a meeting with all stakeholders and review the stakeholder engagement plan

Buy Now
Questions 327

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

Options:

A.

Speak with the team member about their engagement and contributions

B.

Perform an assessment of each member of the project team

C.

Assign the team member to a team where they can contribute more

D.

Conduct a team building event to involve the team member

Buy Now
Questions 328

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

Buy Now
Questions 329

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?

Options:

A.

Change the project scope and seek approval to exclude this town from the overall

project.

B.

Engage with the town's authorities to discuss the reason for the change in commitment

and agree on a solution.

C.

Instruct the team to move to the next town and continue the project to avoid further delays.

D.

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.

Buy Now
Questions 330

In the planning phase, a project manager receives identified risks from the sponsors

and subject matter experts (SMEs) and wants to develop a risk response strategy for them.

What should the project manager do first?

Options:

A.

Perform a risk reserve analysis.

B.

Assign allocated budget to cover key risks.

C.

Agree on the criteria to prioritize risks.

D.

Assign a risk responsibility to each team member.

Buy Now
Questions 331

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

Options:

A.

Ask the issue reporter to close the issues, because there are no project team members

who have the required domain knowledge.

B.

Review the open issues with the issue reporter and issue a change request to hire an

external domain expert.

C.

Request that the project team members learn the required domain knowledge and

resolve the open issues in a short time.

D.

Reduce the project scope to ensure that the project team has the knowledge to deliver

the system on schedule.

Buy Now
Questions 332

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?

Options:

A.

Recommend agile training programs that best suit the client project manager's schedule.

B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.

C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

D.

Provide the client project manager with agile best practice documents and web resources.

Buy Now
Questions 333

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

Options:

A.

Ensure all three teams deliver independently without interactions so that they remain

focused and meet customer requirements.

B.

Implement communication techniques and ensure the teams follow a relay pattern of

handing off work from one team to the other.

C.

Use a fishbone analysis to resolve problems and iron out communication issues

between the teams.

D.

Maintain localized teams to circumvent the challenges of delay or any other

unforeseen risks that might prevent progress.

Buy Now
Questions 334

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.

Request the project team include the stakeholder's details and make sure the project

status reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register for

incorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Buy Now
Questions 335

A hybrid project team is working on an upgraded version of software for their

product owner. The team is also responsible for supporting the existing product and

customers. For the last three sprints, the team had to stop their project work and focus on

major support items for the product owner. The testers are struggling to cope with the

constant changes to the plan, which has resulted in a number of emotional outbursts.

How should the project manager proceed?

Options:

A.

Request a replacement for those team members who are unhappy with this way of

working.

B.

Schedule a session with the product owner to explain that no support items can be

taken into the sprints going forward.

C.

Ask human resources (HR) to send the team members to a change management

workshop.

D.

Schedule a session with the team to discuss the issues and work with them to define a

plan to manage the sprints going forward.

Buy Now
Questions 336

Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?

Options:

A.

Remove one of the team members

B.

Identify the issues between the team members and guide them toward a resolution

C.

Warn the team members about their behavior

D.

Train the team members on communication techniques and interpersonal behavior

Buy Now
Questions 337

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

Options:

A.

Regression analysis

B.

Stakeholder analysis

C.

Qualitative risk analysis

D.

Decision tree analysis

Buy Now
Questions 338

A project has been running for 2 months and now requires approval for a supplier to

begin some execution tasks. The project team has evaluated several suppliers and selected

their top two preferred suppliers. The project sponsor requested that another supplier who has

lower costs be added to the list. However, the project manager is aware that this supplier

does not always fulfill the project requirements.

What should the project manager do?

Options:

A.

Set up a requirements review session and obtain agreement for selection criteria.

B.

Recommend to the team to add the sponsor's preferred supplier to the list.

C.

Choose the sponsor's preferred supplier for the project to avoid conflict between the

team and sponsor.

D.

Recommend to the sponsor to review the results of the team's supplier evaluation.

Buy Now
Questions 339

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

Options:

A.

Updated the stakeholder engagement plan to reflect a change in the product owner

B.

Communicated the status of the project more frequently with the product owner

C.

Updated the communications management plan to reflect a change in the communication needs

D.

Reevaluated the new product owner's needs for better engagement

Buy Now
Questions 340

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

Options:

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Buy Now
Questions 341

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

Options:

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

Buy Now
Questions 342

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

Options:

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager's usual methods as all projects are unique.

Buy Now
Questions 343

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

Options:

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

Buy Now
Questions 344

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

Buy Now
Questions 345

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Buy Now
Questions 346

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then share

it with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agile

approach in the upcoming project.

C.

Make a request to human resources for new team members who have agile

experience.

D.

Ask the project sponsor to change the approach back to predictive as that is the

team’s strength.

Buy Now
Questions 347

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

Options:

A.

Report the violation to the change control board (CCB) and seek comprehensive

approval for these modifications.

B.

Update the change management plan to define the level of control required for

these types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no action

because the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

Buy Now
Questions 348

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

Options:

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

Buy Now
Questions 349

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

Buy Now
Questions 350

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

Options:

A.

Provide feedback to the team and conduct a meeting to review the team rules.

B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.

Provide feedback to the team and request agile training for the new member.

D.

Provide feedback to the team and coach the new team member in agile methodology.

Buy Now
Questions 351

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Options:

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Buy Now
Questions 352

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

Options:

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst's concerns and reassign the task to another team member

Buy Now
Questions 353

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

Buy Now
Questions 354

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.

How should the project manager address this situation?

Options:

A.

Negotiate payment after all project migration is completed

B.

Sign a single agreement for the whole project

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective

Buy Now
Questions 355

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?

Options:

A.

Send a detailed status report highlighting the issue with funding to all of the stakeholders.

B.

Submit a change request to the financial manager to increase the funding and continue as is.

C.

Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.

D.

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.

Buy Now
Questions 356

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?

Options:

A.

Consult the project sponsor and request their feedback

B.

Consult the product owner and request a complete prioritization session

C.

Consult a senior project manager within the organization and request their expert judgement

D.

Consult a senior developer within the organization and request their input.

Buy Now
Questions 357

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

Options:

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

Buy Now
Questions 358

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

Options:

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

Buy Now
Questions 359

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

Options:

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Buy Now
Questions 360

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

Options:

A.

Stop the meeting and reschedule for another time with a more concise presentation.

B.

Set up information review sessions before reconvening another approval session.

C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.

D.

Obtain approval as fast as possible and close the meeting.

Buy Now
Questions 361

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

Options:

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Buy Now
Questions 362

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

Options:

A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.

Implement the role of an agile risk manager to take care of the risk management process.

D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

Buy Now
Questions 363

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

Options:

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Buy Now
Questions 364

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

Options:

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

Buy Now
Questions 365

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Buy Now
Questions 366

A project sponsor receives project information and updates in a timely manner, but

the sponsor is concerned because key information is missing in the reports. What should the

project manager do?

Options:

A.

Review the communication needs of key stakeholders.

B.

Confirm that the project information is understood and feedback is received.

C.

Determine communication methods, frequency, and level of detail.

D.

Provide all project information to the stakeholder.

Buy Now
Questions 367

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

Options:

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.

Review team capacity and reassign the functionality to additional iterations as required

C.

Determine if the team member can work from home to complete the functionality.

D.

Review the work in progress with the product owner to determine the next step

Buy Now
Questions 368

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

Options:

A.

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.

Update the stakeholder register and risk management plan.

C.

Update the stakeholder register and revise the stakeholder engagement plan.

D.

Explain to the community members why they were not included as stakeholders for the project.

Buy Now
Questions 369

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

Options:

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Buy Now
Questions 370

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

Options:

A.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred

B.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays

C.

Met with the team, allowed team members to make decisions about what to do and established performance goals

D.

Conducted routine meetings and identified team members who are under performing

Buy Now
Questions 371

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

Options:

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

Buy Now
Questions 372

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

Options:

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Request that new team members familiar with iterative approaches be assigned to this project.

C.

Update the project schedule to consider a daily standup as part of the project design phase.

D.

Define the ground rules, responsibilities, and conflict management strategies.

Buy Now
Questions 373

A project manager is leading a virtual team that is geographically dispersed. What

should the project manager do to avoid uncertainty in the project due to different cultures?

Options:

A.

Start the project and add any uncertainty that arises to the risk register.

B.

Dissolve the virtual team and build a colocated team.

C.

Gather relevant cultural data and engage members in discussions covering their work ethics.

D.

Build a culturally neutral team that will not be affected by cultural differences.

Buy Now
Questions 374

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

Options:

A.

Risk log

B.

Change log

C.

Backlog

D.

Issue log

Buy Now
Questions 375

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

Options:

A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.

Perform a detailed analysis of the release content for each component of the solution.

C.

Propose a new design of the solution to replace the external component with an internal one.

D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

Buy Now
Questions 376

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

Options:

A.

Escalate to the project steering committee.

B.

Invite the finance department to the next project demo.

C.

Review the project requirements.

D.

Use the currently available resources.

Buy Now
Questions 377

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

Options:

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

Buy Now
Questions 378

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor.

B.

Review the resources required for the tasks on the critical path.

C.

Review and update the risk management plan.

D.

Allocate resources to develop the competencies of the other team members

Buy Now
Questions 379

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Buy Now
Questions 380

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

Buy Now
Questions 381

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

Buy Now
Questions 382

In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager's next step?

Options:

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team's plans.

Buy Now
Questions 383

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Buy Now
Questions 384

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

Options:

A.

Provided copies of the stakeholder engagement plan to all team members.

B.

Defined the roles and responsibilities of the team members.

C.

Updated the communications management plan.

D.

Established ground rules for the team

Buy Now
Questions 385

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

PMP Question 385

Options:

Buy Now
Questions 386

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

Options:

A.

Communicate this issue to the human resources department.

B.

Provide additional training to the new hire.

C.

Increase team cohesiveness by sharing information and experiences openly.

D.

Update the issue log and define the mitigation strategy.

Buy Now
Questions 387

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

Options:

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

Buy Now
Questions 388

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Options:

A.

Convinced the critical resource to remain on the project.

B.

Requested an experienced resource as a replacement

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Buy Now
Questions 389

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

Options:

A.

Ask for additional team members to maintain the velocity

B.

Implement a checkpoint in the iteration to verify if the team is on track

C.

Conduct a focused retrospective to help the team to discover the root cause

D.

Ask the team to have a lower commitment for the next iteration

Buy Now
Questions 390

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

Options:

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

Buy Now
Questions 391

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

Options:

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Buy Now
Questions 392

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

Options:

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Buy Now
Questions 393

During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?

Options:

A.

Benchmark other similar exhibitions' deliverable lists and final outcomes

B.

Initiate a survey to solicit end-customer opinions and prioritize exhibition contents

C.

Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.

D.

Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract

Buy Now
Questions 394

A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)

Options:

A.

High-level product backlog

B.

Key performance indicators (KPls)

C.

Product vision

D.

Schedule performance indexes (SPIs)

E.

Product roadmap

Buy Now
Questions 395

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

Options:

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Buy Now
Questions 396

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Buy Now
Questions 397

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.

D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Buy Now
Questions 398

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team.to accelerate the iterations and avoid interruptions.

B.

Discuss the problem with the team and decide how to do the work together.

C.

Verify team performance and ask for improvement during daily standup meetings.

D.

Recommend that the project sponsor increases the budget to bring new resources.

Buy Now
Questions 399

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

Options:

A.

Be clear with directions and assignments so people stay focused and engaged with their work.

B.

Promote an environment where everybody knows what their contribution means to the project as a whole.

C.

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint

D.

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Buy Now
Questions 400

During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.

What should the project manager do first?

Options:

A.

Negotiate with the key team members to send a daily report and let the sponsor know that the project cost will increase. ty

B.

Recommend to the sponsor that performance of the project be reviewed once per week.

C.

Review the communications management plan and submit a change request if required.

D.

Evaluate the capacity of each team member to attend daily meetings in person or virtually and reduce the time of each meeting.

Buy Now
Questions 401

A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

Options:

A.

Incorporated the change within the scope of the project

B.

Reviewed the quality inspections

C.

Complied with the customer specifications

D.

Documented the technical reviews with the new change

Buy Now
Questions 402

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

Options:

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team's communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

Buy Now
Questions 403

A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.

How should the project manager handle this situation?

Options:

A.

Discuss the company culture with the supervisor to clarify expectations.

B.

Review the overall organizational culture of the company again.

C.

Request that the new supervisor be assigned to another project.

D.

Explain to the workers that they need to listen to the supervisor.

Buy Now
Questions 404

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

Options:

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

Buy Now
Questions 405

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

Options:

A.

Early value cannot be achieved until the product is fully released.

B.

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.

Early value will be gained only if beta products can be released to the market.

D.

Early value will be gained only if the speed can be increased to release the product to the market.

Buy Now
Questions 406

A product owner has an idea for a new product but is struggling to define the

features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?

Options:

A.

Assess the product roadmap to see if there is another product that is more suitable for the build.

B.

Develop a minimum viable product (MVP) for assessment from a select customer group.

C.

Commission a business analyst to research similar competitor products.

D.

Complete a work breakdown structure (WBS) to assess the cost of each feature

Buy Now
Questions 407

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

Options:

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

Buy Now
Questions 408

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Buy Now
Questions 409

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

Options:

A.

Project stakeholders and the team

B.

External subject matter experts (SMEs) and the team

C.

Project sponsor and the team

D.

Project sponsor and the external SMEs

Buy Now
Questions 410

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

Options:

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

Buy Now
Questions 411

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

PMP Question 411

Options:

Buy Now
Questions 412

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

Options:

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

Buy Now
Questions 413

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

Options:

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project's quality control measurements

D.

Develop a mitigation based on the solution design

Buy Now
Questions 414

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

Options:

A.

Monitor the interactions between the vendor and infrastructure manager going forward.

B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.

Escalate the issue to the sponsor so appropriate action can be taken.

D.

Instruct the vendor to correct the problem without additional arguments.

Buy Now
Questions 415

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?

Options:

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Buy Now
Questions 416

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Buy Now
Questions 417

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.

Review the work allocation and reassign some tasks to shorten the critical path.

B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.

Keep the task assignments unchanged since the project management plan has been approved.

Buy Now
Questions 418

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?

Options:

A.

Update the issue log.

B.

Perform a qualitative risk analysis.

C.

Perform a root cause analysis.

D.

Implement a risk response plan.

Buy Now
Questions 419

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

Options:

A.

How the quality was managed

B.

How the acceptance criteria were met

C.

How the scope was managed

D.

How the stakeholders were managed

Buy Now
Questions 420

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

Options:

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

Buy Now
Questions 421

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

Options:

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

Buy Now
Questions 422

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

Options:

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Buy Now
Questions 423

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor's request because it is out of scope

D.

Validate the proposed change's impact on the project.

Buy Now
Questions 424

Match the project situation on the left to the meeting on the right where the situation could occur.

PMP Question 424

Options:

Buy Now
Questions 425

A project manager is assigned to oversee the deployment of a new product that

will be used by the entire organization. A key success factor for the project is the timely

and successful adoption of the new solution by all entities.

What should the project manager do to ensure the success of this critical project?

Options:

A.

Considering the project scope and the multiple entities impacted by the solution,

communicate with the stakeholders and ask them to adhere to the date.

B.

Ask the project sponsor to issue a directive requesting all business entities to

accept the date set for the new solution launch.

C.

Given the size of the organization and the multiple parties involved, discuss the

launch date with the CEO and then communicate it to all entities.

D.

Engage in creative and iterative negotiations with the leaders of each entity to

agree on the launch date.

Buy Now
Questions 426

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

Buy Now
Questions 427

A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project

What should the project manager do?

Options:

A.

Use the management reserves to fund some team-building activities

B.

Inflate project estimates to provide a financial buffer for team activities.

C.

Find another method to increase the team's performance

D.

Implement a reward system aimed to keep the team engaged and motivated

Buy Now
Questions 428

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily

B.

Decrease the sprint cycle to the average repriontization request by calculating it in days

C.

Set up a meeting with the project team and ask for their opinion on what to do

D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle

Buy Now
Questions 429

A junior staff member was recently assigned to the team. The new team member tells the project manager that they are confused because they are not familiar with what is expected of them on the project

What should the project manager do to assist the new team member?

Options:

A.

Advise the new team member to enroll in project management training.

B.

Instruct the new team member to review the responsible, accountable consult, and inform (RACI) matrix before asking for help

C.

Advise the new team member to review the project charter and stakeholder engagement plan.

D.

Review the resource management plan and provide mentoring to the new team member if necessary

Buy Now
Questions 430

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

Options:

A.

Introduce a recognition program to motivate and reward resource performance

B.

Enhance the competencies of the project team through training, mentoring and coaching.

C.

Increase the trained staff to create back-up for resources

D.

Meet with management to discuss dividing the project into smaller projects

E.

Convince senior management to hire third-party staff

Buy Now
Questions 431

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?

Options:

A.

Review the milestone list to determine which tasks can be fast-tracked

B.

Review the risk management plan to identify the response strategy

C.

Escalate the issue to the sponsor and debrief them about the situation

D.

Organize a team meeting to discuss the next course of action

Buy Now
Questions 432

After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features

What should the project manager do to avoid this in the future?

Options:

A.

Set up requirements-gathering sessions with all key stakeholders to evaluate the scope once again and reprioritize the backlog based on the sessions.

B.

Schedule adequate sprint demos to gather early feedback from the stakeholders and adapt the plan accordingly

C.

Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.

D.

Evaluate the team's skills to look for someone with experience in product design and assign that person the task of rebuilding the product interface

Buy Now
Questions 433

A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials

What should the project manager do next?

Options:

A.

Ask the project sponsor to allocate more budget to cover the costs

B.

Update the procurement management plan and negotiate with the contractor.

C.

Ask the contractor to review the offer and reduce the costs.

D.

Update the procurement strategy and negotiate with the contractor

Buy Now
Questions 434

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

Options:

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them

B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.

C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report

D.

Research which templates of reports were used the most for this framework and incorporate them into the project

Buy Now
Questions 435

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

Buy Now
Questions 436

A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects

What should the project manager do?

Options:

A.

Schedule a steering committee meeting and obtain their approval on the request

B.

Support the decisions of the team and transfer the decision making responsibility to them.

C.

Inform the team that although this is a hybrid environment, the project manager

must still be responsible for making decisions

D.

Consult the product owner about letting the resources make decisions

Buy Now
Questions 437

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?

Options:

A.

Schedule meetings with the customer to determine their ability to support multiple incremental deliveries

B.

Work with the agile team to schedule the incremental deliveries to enable delivery

of business value sooner to the customer.

C.

Work with the stakeholder to understand what the concerns are while at the same time conveying the benefits of incremental deliveries

D.

Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder's request.

Buy Now
Questions 438

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

Options:

A.

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.

B.

Speak with individual team members to determine what they would like to do to improve the situation in the team

C.

Have the team inform senior management of the situation and ask for recommendations.

D.

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct

Buy Now
Questions 439

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.

Create a prioritized backlog and define iteration review sessions with stakeholders

B.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders

C.

Schedule a daily meeting to review team performance and impediments

D.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders

Buy Now
Questions 440

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond'?

Options:

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance

D.

Explain to the stakeholder that the stakeholder engagement plan requires their

attendance at all reviews

Buy Now
Questions 441

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)

Options:

A.

Discuss with the construction team alternatives on moving the new train station to another location.

B.

Publish information on the city’s website about the benefits that the new tram station will bring

C.

Have a meeting with the mayor and explain the importance of the new train station to the city.

D.

Conduct regular meetings with the neighbors to get their buy-in for the project

E.

Register this situation as a risk and develop a mitigation plan

Buy Now
Questions 442

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

Options:

A.

Set up a meeting with key stakeholders to clarify requirements

B.

Escalate to the project steering committee and request additional time

C.

Travel to the development team's office to push the schedule

D.

Create prototypes with the development team to confirm requirements

Buy Now
Questions 443

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.

Raise the issues in the retrospective and propose solutions

B.

Inform management that commitments will not be met.

C.

Involve management to help resolve the conflicts

D.

Coach the team both as a whole and individually

Buy Now
Questions 444

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

Options:

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Buy Now
Questions 445

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

Options:

A.

Raise a change request to immediately implement the printing module component.

B.

Escalate this issue to the project sponsor immediately

C.

Ask the project team to conduct a quality audit of the printing module components.

D.

Meet with the project team to understand the issue and define actions.

Buy Now
Questions 446

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

Options:

A.

Sort conflicts into two groups: positive and negative

B.

Place conflicts into categories: structural and interpersonal.

C.

Place conflicts on a shared conflict list and ensure it is visible

D.

Review conflicts during daily Scrum so they are handled in a timely manner

Buy Now
Questions 447

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

Options:

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Buy Now
Questions 448

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all defects identified during testing were resolved before implementation

B.

Ensured that all of the required tasks identified in the scope were completed successfully

C.

Ensured that all documentation was completed post implementation before closing the project

D.

Ensured that all the required approvals were received per the organizational procedures

Buy Now
Questions 449

Drag the communication event on the left to the mam subject discussed during the event on the right.

PMP Question 449

Options:

Buy Now
Questions 450

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

Options:

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

Buy Now
Questions 451

Drag the to the correct scenario on the right

PMP Question 451

Options:

Buy Now
Questions 452

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

Options:

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

Buy Now
Questions 453

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Buy Now
Questions 454

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

Options:

A.

Schedule a meeting for the project team to review the communications management plan.

B.

Tell the rest of the project team to continue discussions with the new team member

C.

Send an email to the project team outlining the communications strategy.

D.

Mentor the new team member on the methodology the project team is using

Buy Now
Questions 455

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

PMP Question 455

Options:

Buy Now
Questions 456

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

Options:

A.

Updated the risk management plan and registered lessons learned for the project

B.

Reorganized the team for the project based on the work breakdown structure (WBS)

C.

Maintained constant communication with the stakeholders of the other projects

D.

Used the resource management plan to identify the impacts of the other projects

Buy Now
Questions 457

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

Options:

A.

Remove the changes to match the original requirements.

B.

Add team members to the project to avoid more schedule delays.

C.

Evaluate the impacts of the changes that were made to the project

D.

Update project documentation with the new scope

Buy Now
Questions 458

A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)

Options:

A.

Five whys

B.

Communications management plan

C.

Ishikawa diagrams

D.

Issue log

E.

Open-space meetings

Buy Now
Questions 459

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.

Use soft skills to convince the project sponsor to approve the new budget estimate

Buy Now
Questions 460

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

Options:

A.

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B.

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C.

Reinforce with the key stakeholder that the project is performing on schedule\

D.

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

Buy Now
Questions 461

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

Options:

A.

Request budget to reward the team member so others will be motivated to obtain the same certification

B.

Promote the team member to product owner to leverage the new knowledge with the clients

C.

Provide an incentive to team members who begin using the new tool on this project.

D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team

Buy Now
Questions 462

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

Options:

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project's scope.

D.

Submit a change request to increase the budget and buy new equipment

Buy Now
Questions 463

A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.

PMP Question 463

Options:

Buy Now
Questions 464

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?

Options:

A.

Start developing a business case.

B.

Start a strengths, weaknesses, opportunities and threats (SWOT).

C.

Engage stakeholders and allocate resources

D.

Gather requirements from stakeholders

Buy Now
Questions 465

A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished

How should the project manager approach this situation?

Options:

A.

Request that the customer reviews and clarifies feature definitions for the current sprint

B.

Send a burndown chart of the current sprint to the customer and seek clarifications.

C.

Educate the customer and have them participate in daily standup meetings.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements

Buy Now
Questions 466

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting

What should the project manager have done to avoid this situation?

Options:

A.

Reviewed the communications management plan before inviting an external client representative to the meeting

B.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting

C.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register

D.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting

Buy Now
Questions 467

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

Options:

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team's needs

D.

A risk management plan to incorporate known risks

Buy Now
Questions 468

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

Options:

A.

Ensured the team charter was developed by the team members

B.

Ensured the team members are fully supportive of all decisions.

C.

Distributed the project charter to all team members.

D.

Used a charismatic leadership style

Buy Now
Questions 469

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

Options:

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Buy Now
Questions 470

During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?

Options:

A.

Have the project team work on other activities

B.

Implement plans to remove the obstacles

C.

Escalate to the project steering committee

D.

Prioritize the obstacles for resolution

Buy Now
Questions 471

A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated

What should the project manager do to address this issue?

Options:

A.

Create a change request and update the scope management plan

B.

Conduct stakeholder identification and a project objectives review session

C.

Update the stakeholder list and fix the deliverables

D.

Update the project management plan and lessons learned

Buy Now
Questions 472

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

Options:

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Buy Now
Questions 473

A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?

Options:

A.

Analyze the quality requirements.

B.

Plan quality management

C.

Continually survey the quality of the deliverable

D.

Set up quality policies and procedures

Buy Now
Questions 474

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

Options:

A.

The contract has not been appropriately reviewed by the project team

B.

The stakeholder engagement plan has not been correctly implemented

C.

The legal department has not disseminated the law correctly to all staff.

D.

The project manager does not have enough knowledge on this legal matter

Buy Now
Questions 475

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

Options:

A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.

Update the communications management plan and implement the change

C.

Meet with the project sponsor to discuss how to address the situation.

D.

Meet with the stakeholder prior to the meeting to obtain their opinion

Buy Now
Questions 476

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

Options:

A.

Share the project documents and invite the key stakeholder to discuss any concerns

B.

Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline

C.

Proceed with a working session for teams that do not belong to that key stakeholder

D.

Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy

Buy Now
Questions 477

A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company

What should the project manager do first?

Options:

A.

Organize individual sessions with the stakeholders to build awareness and trust in the new framework

B.

Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.

C.

Send documentation to the senior manager about the advantages of the new framework

D.

Escalate the senior manager's concern to the project sponsor and distribute the status to the team

Buy Now
Questions 478

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

Options:

A.

Award certificates of appreciation to encourage the team

B.

Inform the team about the delivery pressure from the project sponsor

C.

Send a formal notice to team members instructing them to maintain performance

D.

Hire a few temporary team members to help with the additional work.

Buy Now
Questions 479

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

Options:

A.

The project is an information technology project and has minimal impact to the organization

B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.

The project scope is well defined and the requirements are prioritized

D.

The project team has a colocated space and is capable of working together

Buy Now
Questions 480

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Buy Now
Questions 481

A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?

Options:

A.

Plan a working session focusing on the scope, vision, and mission of the initiative

B.

Start developing the project management plan based on a previous project template from the project management office (PMO).

C.

Conduct benchmarking to determine the business viability of the initiative

D.

Conduct an impact analysis of the new initiative to determine how the project should be rolled out

Buy Now
Questions 482

A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information

How should the project manager handle this situation?

Options:

A.

Apply lean manufacturing to limit the team’s work

B.

Increase retrospectives to deliver results fast

C.

Make work visible using kanban boards.

D.

Incorporate small batches of work into the project

Buy Now
Questions 483

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

Options:

A.

Allocate and use part of the project's contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory's hazards, providing employment to the local community

Buy Now
Questions 484

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.

Request more funding from the project sponsor to hire additional skilled resources

and to incorporate additional quality in the project delivery approach and outcome

C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

Buy Now
Questions 485

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

Options:

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.

B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly

C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties

D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer

Buy Now
Questions 486

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

Options:

A.

Review the project goal diagram with the team.

B.

Perform a stakeholder evaluation

C.

Confirm which templates the team should be using

D.

Review the risk management plan

Buy Now
Questions 487

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task

What should the project manager do to obtain the information required by the developer?

Options:

A.

Request direction from the project sponsor

B.

Write an email to the client requesting clarification

C.

Seek support from the development manager.

D.

Work with the product owner to clarify the requirement

Buy Now
Questions 488

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

PMP Question 488

Options:

Buy Now
Questions 489

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

PMP Question 489

Options:

Buy Now
Questions 490

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

Options:

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

Buy Now
Questions 491

A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?

Options:

A.

Referred to the communications management plan

B.

Validated the issue log

C.

Validated the project artifacts

D.

Performed expert judgment

Buy Now
Questions 492

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

Options:

A.

Review lessons learned from previous projects that used the same team

B.

Review the organizational culture, structure, and governance

C.

Coordinate a meeting to understand the situation and resolve any conflicts.

D.

Coordinate a meeting with regional managers to ask for support

Buy Now
Questions 493

A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint

What should the project manager have done to avoid this situation?

Options:

A.

Involved the key stakeholders in the decision-making process

B.

Customized stakeholder communications based on the stakeholders’ needs

C.

Analyzed the changes in stakeholder attributes

D.

Documented the project vision and objectives

Buy Now
Questions 494

A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?

Options:

A.

Increase the details of the work breakdown structure (WBS) to minimize errors and delays.

B.

Split the backlog into phases to ensure that the key features are delivered first

C.

Ask the sponsor to prioritize some functionalities of the product.

D.

Identify the minimum functionality required for the product

Buy Now
Questions 495

The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members

What two actions should project manager take? (Choose two)

Options:

A.

Ask the team members to work it out themselves

B.

Discuss this situation with other project managers and ask for advice

C.

Reiterate ground rules at the next meeting and ensure that all team members are clear about these rules.

D.

Address the behavioral issue with each team member

E.

Discuss the behavior directly with their managers and request them to correct the behavior.

Buy Now
Questions 496

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives'?

Options:

A.

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.

Submit a change request to the CCB and update the schedule

C.

Update the scope and add more resources to the project

D.

Update the scope and move on to the next project milestone

Buy Now
Questions 497

An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.

What should the project manager do to resolve this issue?

Options:

A.

Hire the resource in order to achieve the project objectives.

B.

Ask the client for a meeting and explain that the task will not be performed

C.

Evaluate the consequences and meet with the client to explain the possible scenarios.

D.

Try to accomplish the task internally by leveling resources from other projects

Buy Now
Questions 498

Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right

PMP Question 498

Options:

Buy Now
Questions 499

A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization

How should the project manager handle the different stakeholders?

Options:

A.

All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders

B.

Because there are different perspectives perform a stakeholder analysis and act based on the outcome.

C.

The project manager is working on the client's premises, so follow the directions of all the key stakeholders

D.

This is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization

Buy Now
Questions 500

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?

Options:

A.

Speak with peers about the need for a project charter

B.

Develop the project charter and send it for approval

C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities

D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan

Buy Now
Questions 501

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Buy Now
Questions 502

The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.

What should the project manager do?

Options:

A.

Determine the risks and identify a resolution during the retrospective meeting

B.

Inform stakeholders about the delay during project updates

C.

Determine cross-dependencies and plan a spike in the next spont

D.

Discover the gaps in the communications management plan and address them accordingly

Buy Now
Questions 503

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

Options:

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Buy Now
Questions 504

According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

PMP Question 504

Options:

Buy Now
Questions 505

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

Options:

A.

Ask the marketing director to participate in daily meetings

B.

Mentor the marketing director on hybrid approaches

C.

Ask the marketing team members to coach the director

D.

Tram the marketing team and keep the director informed

Buy Now
Questions 506

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

Options:

A.

Reviewing and updating the requirements management plan

B.

Carrying out quality audits and failure analyses

C.

Monitoring the work breakdown structure (WBS)

D.

Monitoring and updating the benefits realization plan

Buy Now
Questions 507

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

Options:

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

Buy Now
Questions 508

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

Options:

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Buy Now
Questions 509

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Buy Now
Questions 510

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

Options:

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2024 Version)
Last Update: Nov 16, 2024
Questions: 1702

PDF + Testing Engine

$179.7  $599

Testing Engine

$134.7  $449
buy now PMP testing engine

PDF (Q&A)

$119.7  $399
buy now PMP pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 24 Nov 2024