Special Summer Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Questions 4

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Buy Now
Questions 5

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Buy Now
Questions 6

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented.

 

Buy Now
Questions 7

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

Options:

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment

 

Buy Now
Questions 8

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.

Risk burndown chart

B.

Ishikawa diagram

C.

Risk breakdown structure (RBS)

D.

Affinity diagram

Buy Now
Questions 9

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Options:

A.

Industry's standard procedures

B.

Current request for proposal (RFP)

C.

Company's historical financial reports

D.

IT infrastructure, networks, and data information

E.

Government laws and regulations

 

Buy Now
Questions 10

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register.

 

Buy Now
Questions 11

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

What should the project manager do next?

Options:

A.

Request a budget relief using the management reserve.

B.

Conduct a risk reassessment and reserve analysis.

C.

Review the consequences of potential changes.

D.

Coach stakeholders on risk identification practices.

Buy Now
Questions 12

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.

Perform a qualitative risk analysis and update the results.

B.

Update the assumptions/exclusions register with the new information.

C.

Update the risk register and prepare for the Monte Carlo analysis.

D.

Perform a quantitative risk analysis and update the results.

Buy Now
Questions 13

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Options:

A.

Engaging the key stakeholders during the prioritization process

B.

Prioritizing the risks based on the project sponsor's risk appetite

C.

Engaging with the project sponsor before presenting to the board

D.

Working with an established industry standard prioritization method

Buy Now
Questions 14

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Buy Now
Questions 15

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Options:

A.

Develop and employ an Ishikawa diagram

B.

Analyze the assumptions and constraints

C.

Perform a review of project documents

D.

Create prompt lists for expert interviews

Buy Now
Questions 16

A project manager has requested the risk manager's support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.

What should the risk manager recommend?

Options:

A.

The new component should be purchased.

B.

Both options are losses to the project.

C.

Cost to expedite the execution is not worth the added risk.

D.

Perform a Monte Carlo simulation to quantify the impacts.

Buy Now
Questions 17

A Scrum team has recently lost its product owner to another team. A new product owner has been hired for the Scrum team. This product owner is currently new to the project, unfamiliar with the team's practices, and does not have a full grasp of the product users. After a few sprints, the product owner is receiving constructive feedback from both internal and external stakeholders related to the direction of the product and its current challenges.

What can the product owner do to improve the product's perception among stakeholders and ensure the team understands the product vision?(Choose 2)

Options:

A.

Re-assess the product goal, place it on the product backlog, and explain it to the team.

B.

Invite more stakeholders to the daily scrum meetings to voice their opinion of the product.

C.

Create sprint goals and communicate them at the sprint planning event.

D.

Invite product teams to more frequent reviews to observe the team's work and encourage feedback.

E.

Invite stakeholders to the sprint retrospective to brainstorm with the team improvements.

Buy Now
Questions 18

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.

B.

The organization's professional engineers having reservations about possible information tampering.

C.

A growing number of competitors with digital signatures.

D.

An elimination of manual steps associated with recording wet signatures

E.

The growing adoption of mobile communications in the industry.

Buy Now
Questions 19

A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Options:

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

Buy Now
Questions 20

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

Options:

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.

Buy Now
Questions 21

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

Buy Now
Questions 22

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.

B.

Use the Wideband Delphi method.

C.

Use the brainstorming technique.

D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis.

 

Buy Now
Questions 23

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Options:

A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks.

 

Buy Now
Questions 24

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

Buy Now
Questions 25

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

Options:

A.

Applying modern risk management techniques.

B.

Aligning to project constraints and priorities.

C.

Ensuring risk response strategies mitigate all risks.

D.

Minimizing implementation costs.

E.

Obtaining stakeholder acceptance

Buy Now
Questions 26

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?

Options:

A.

Update the risk register accordingly and review it in regular project meetings.

B.

Accept the risk because residual risks are often low.

C.

Ask a subject matter expert (SME) to assess the residual risk and take action.

D.

Assign a risk owner and set it as high priority and high impact.

Buy Now
Questions 27

What should the risk owner use as an effective information-gathering technique during the planning session?

Options:

A.

Monte Carlo analysis

B.

Update risk register

C.

Brainstorming

D.

Cost and time estimating

Buy Now
Questions 28

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account.

 

Buy Now
Questions 29

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team

 

Buy Now
Questions 30

In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

Options:

A.

Exploit

B.

Accept

C.

Share

D.

Enhance

 

Buy Now
Questions 31

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.

Ensuring that the project sponsor is kept well-informed

B.

Arranging periodic risk: management process audits

C.

Communicating the status of risks regularly to stakeholders

D.

Monitoring costs with intervention when necessary

Buy Now
Questions 32

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk

Buy Now
Questions 33

A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.

What should the risk manager do?

Options:

A.

Assign a subset of stakeholders to work on the risk management process.

B.

Leverage the project manager's project stakeholder analysis.

C.

Agree with the project manager not to start risk activities.

D.

Send a communication inviting volunteers to join risk activities.

Buy Now
Questions 34

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project

B.

By helping to determine the overall project risks

C.

By helping the lessons learned from previous risks to be efficiently utilized

D.

By helping to update the project scope statement document

E.

By helping update the risk register and close out expired risks

 

Buy Now
Questions 35

A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

What process is this part of?

Options:

A.

Plan Risk Management

B.

Perform Qualitative Risk Analysis

C.

Perform Quantitative Risk Analysis

D.

Monitor and Control Risk

Buy Now
Questions 36

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

Options:

A.

Perform a sensitivity analysis to the higher-level aggregate activities

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Perform a base line Monte Carlo simulation to address overall threats to project objectives

Buy Now
Questions 37

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Buy Now
Questions 38

An organization faces immense competition in the market and decides 10 accelerate a keyproject. What is the first action for the project risk manager to take?

Options:

A.

Ensure sufficient resources are available

B.

Revise the risk management plan

C.

Update the risk register

D.

Meet with the project's stakeholders

Buy Now
Questions 39

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?

Options:

A.

Quantitative risk analysis

B.

Risk response planning

C.

Monitor and control risks

D.

Risk urgency assessment

Buy Now
Questions 40

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?

Options:

A.

Start a quantitative analysis to understand the impact.

B.

Crash the schedule to mitigate the risk consequences.

C.

Transfer the risk to the external team.

D.

Ask the risk owners to review the risk response plan.

Buy Now
Questions 41

After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?

Options:

A.

Risk trigger

B.

Risk escalation

C.

Risk urgency

D.

Risk time impact

Buy Now
Questions 42

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.

Review the agreed-upon risk tolerance

B.

Perform a sensitivity analysis of the risk

C.

Find out the stakeholders’ risk appetite

D.

Use industry standard risk thresholds

Buy Now
Questions 43

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Options:

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability

 

Buy Now
Questions 44

The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

How should this documentation be utilized in the future?

Options:

A.

To return the remaining amount of the contingency reserve

B.

To ensure information is recorded for lessons learned

C.

To comply with the rules and regulations

D.

To hold those who created the risk accountable

Buy Now
Questions 45

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Buy Now
Questions 46

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options:

A.

Schedule and resource assumptions

B.

Contingency reserves

C.

Work breakdown structure (WBS)

D.

Risk impact matrix

Buy Now
Questions 47

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

Options:

A.

Document the concern over the potential excessive additional cost.

B.

Manage the potential excessive additional cost as a new risk.

C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.

 

Buy Now
Questions 48

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.

 

 

Buy Now
Questions 49

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

Options:

A.

Perform time recovery actions.

B.

Execute the prevention plans.

C.

Execute the contingency plans.

D.

Perform change management.

Buy Now
Questions 50

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Options:

A.

Monte Carlo analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Quantitative risk analysis

Buy Now
Questions 51

An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

Buy Now
Questions 52

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

Options:

A.

Release this version and leave changes to be done at the end of the project phase.

B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

Buy Now
Questions 53

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

Options:

A.

To enable the team in identifying the specific causes of risks associated with project objectives.

B.

To ensure that project priorities are being appropriately factored into risk response plans.

C.

To determine there more attentive project leadership and organizational involvement is needed.

D.

To assign risks and risk severities to functional discipline and departments effectively.

Buy Now
Questions 54

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.

Process the freight invoices at higher shipping costs against the project's contingency allowance.

B.

Request a formal change order from the customer to increase the project's total budget.

C.

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.

D.

Ask the project sponsor to cover the additional shipping costs on the company's reserves account.

Buy Now
Questions 55

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan

 

Buy Now
Questions 56

A project manager wants to introduce a new technology to improve a project's performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.

What should the project manager do in this situation?

Options:

A.

Escalate this initiative to project decision makers and sponsors.

B.

Accept the fact that there is a risk associated with this new technology.

C.

Take advantage of this opportunity of Improving the project performance.

D.

Outsource the implementation of the new technology as soon as possible.

Buy Now
Questions 57

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Buy Now
Questions 58

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis

 

Buy Now
Questions 59

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Options:

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.

Motivate and influence the project team with risk engagement activities like workshops.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Buy Now
Questions 60

A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Options:

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Buy Now
Questions 61

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Buy Now
Questions 62

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.

Update the new risk in the risk register.

B.

Plan responses for the new risk.

C.

Passively accept the new risk.

D.

Add the new risk to the watch list.

Buy Now
Questions 63

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

Options:

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Decision tree analysis

D.

Cost-benefit analysis

Buy Now
Questions 64

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

Buy Now
Questions 65

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.

Request for a skilled facilitator to help resolve conflicts that have arise.

B.

Refer to the team’s ground rules on how to resolve conflicts.

C.

Run a sensitivity analysis to check which risks have the most impact.

D.

Use the assumption analysis techniques to validate the assumptions.

Buy Now
Questions 66

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

Options:

A.

Consult with the project manager to agree that these risks should be removed from the risk register

B.

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.

Identify workarounds that can be implemented whether or not the change takes place.

D.

Revisit the project the assumptions and constraints to potentially update the risk impact and response.

 

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Mar 31, 2025
Questions: 221

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now PMI-RMP testing engine

PDF (Q&A)

$31.5  $104.99
buy now PMI-RMP pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 02 Apr 2025