Winter Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpm65

PMI-PBA PMI Professional in Business Analysis Questions and Answers

Questions 4

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

Options:

A.

Perform solution evaluation.

B.

Formulate a weighted-ranking matrix.

C.

Review the stakeholder analysis.

D.

Recommend the SVP's choice, as it is most likely to be adopted.

Buy Now
Questions 5

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.

The business analyst tells the stakeholder that the requirement status was changed to "deferred ”

What could have prevented the stakeholder from being surprised about the status change?

Options:

A.

The status should have been communicated to the requirement’s source.

B.

The status should have been reviewed prior to project launch.

C.

The status should have been communicated to all project stakeholders.

D.

The status should have been updated in the traceability matrix.

Buy Now
Questions 6

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

Options:

A.

Data modeling

B.

B. Interface modeling

C.

Rules modeling

D.

Enterprise modeling

Buy Now
Questions 7

After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:

Options:

A.

some requirements having not yet been discussed in a work group session.

B.

the requirements’ reference codes not tracing to the attribute numbers in the work breakdown structure.

C.

the requirements documents having not yet received sign-off from the sponsor.

D.

the requirements not providing all of the information needed to define the work.

Buy Now
Questions 8

How should a business analyst determine whether a solution satisfies business requirements?

Options:

A.

By reviewing the results of user acceptance testing

B.

By evaluating the solution against the project charter

C.

By conducting a brainstorming session with end users

D.

By reviewing the traceability matrix

Buy Now
Questions 9

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

Options:

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Buy Now
Questions 10

A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper," "Customer," and "Agent." These user groups

categorize stakeholders with similar needs and create a detailed narrative.

Which technique did the business analyst use for evaluating the solution's acceptance criteria?

Options:

A.

Stakeholder analysis

B.

Job analysis

C.

Persona analysis

D.

Risk analysis

Buy Now
Questions 11

A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.

What should the business analyst do to ensure that the business need can be validated?

Options:

A.

Document an assumption.

B.

Document a constraint.

C.

Document a defect.

D.

Document a business rule.

Buy Now
Questions 12

When managing a product backlog, which statement best describes how to determine the value of backlog items?

Options:

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Buy Now
Questions 13

Requirements elicitation for a project is occurring. The marketing, acquisition, and production departments want to include specific requirements. The CEO has a requirement to deploy in three months.

Which of the following actions will have a greater influence on the project success?

Options:

A.

Prioritize and develop the requirements of the marketing department since the project will impact a greater number of people.

B.

Estimate the effort required for each requirement and develop as many functionalities as possible.

C.

Conduct a stakeholder analysis and balance requirements by understanding the relative power associated with each stakeholder group.

D.

Explain the situation to the CEO and try to obtain an extension of the contract for the actual time necessary to develop the system.

Buy Now
Questions 14

A business analyst has been asked to investigate a problem. This investigation will provide input towards developing a business case. The business analyst wants to first understand the company's current business processes.

Which technique should the business analyst use?

Options:

A.

Observation

B.

RAC! matrix

C.

MoSCoW

D.

User stories

Buy Now
Questions 15

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

Options:

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Buy Now
Questions 16

What is one benefit of documenting the change control process?

Options:

A.

Stakeholders are shielded from how changes are assessed.

B.

Stakeholders know how to request changes.

C.

Stakeholders have a schedule of changes to be deployed.

D.

Stakeholders understand the difficulty of managing requirements.

Buy Now
Questions 17

A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.

Which technique should be followed?

Options:

A.

Interface analysis

B.

Requirements traceability

C.

MoSCoW

D.

Feasibility analysis

Buy Now
Questions 18

A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?

Options:

A.

Storyboard

B.

Project charter

C.

Business case

D.

Survey

Buy Now
Questions 19

A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.

Which model should the team employ to ensure the most effective representation of analysis boundary?

Options:

A.

Data flow diagram

B.

Context diagram

C.

State diagram

D.

Entity relationship diagram

Buy Now
Questions 20

The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

Options:

A.

Perform inspections through the lifecycle of the project to detect any gaps and adjust the requirements baseline.

B.

Plan regular meetings with stakeholders to review the requirements baseline update and to discuss changes.

C.

Establish a risk traceability matrix and designate someone to manage each risk with the appropriate response.

D.

Record all the requirements in a matrix, review it regularly, and get approval from stakeholders.

Buy Now
Questions 21

After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased. Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?

Options:

A.

Questionnaires and surveys

B.

Document analysis

C.

Observation

D.

Traceability matrix

Buy Now
Questions 22

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

Options:

A.

Time-boxing

B.

SWOT analysis

C.

Weighted ranking

D.

Multivoting

Buy Now
Questions 23

Which document best provides the boundaries for product development?

Options:

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

Buy Now
Questions 24

Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identify the requestor.

What should the business analyst have documented?

Options:

A.

Sponsor approval in the requirements traceability matrix

B.

The source in the RACI matrix

C.

Roles and responsibilities in the RACI matrix

D.

The source in the requirements traceability matrix

Buy Now
Questions 25

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

Options:

A.

Request that the project manager identify all affected project stakeholders.

B.

Provide all signed-off project documentation to the stakeholders for information purposes only.

C.

Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.

D.

Solicit feedback and add requirements to the project backlog.

Buy Now
Questions 26

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?

Options:

A.

Develop a change control process.

B.

Obtain approval from the project sponsor.

C.

Document changes as they occur.

D.

Hold firm on scope and reject changes.

Buy Now
Questions 27

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Buy Now
Questions 28

A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:

Options:

A.

requirements gathering workshops with the stakeholders.

B.

requirements acceptance with the customer.

C.

requirements validation with the testers.

D.

requirements sign-off with the customer.

Buy Now
Questions 29

A company is developing a new product for a customer and is required to verify and validate the product against the customer's acceptance test plan and requirements. The product was successfully verified against the acceptance test criteria, but the customer

does not believe that the product meets the requirements.

This occurred because the customer's acceptance test plan:

Options:

A.

was not included in the work breakdown structure.

B.

did not have measurable and testable requirements.

C.

was not formally accepted by the company.

D.

was incomplete and missing requirements.

Buy Now
Questions 30

Which of the following is a method for requirements change control?

Options:

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Buy Now
Questions 31

A financial company deployed a new online product to their customers to invest in the stock market. The company notices a problem regarding financial calculations and starts the problem analysis. The company discovers that the new rules for taxes and fees were not implemented.

This problem could have been avoided by:

Options:

A.

using a table that shows each applicable business rule with the implemented functional requirement.

B.

implementing an automated issue tracking system to facilitate the tracing of defects to the requirements.

C.

involving a business analyst during all phases of system development.

D.

rolling back the operations using a contingency process in order to avoid loss and client dissatisfaction.

Buy Now
Questions 32

When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?

Options:

A.

Stakeholder register

B.

RACI matrix

C.

SWOT analysis

D.

Stakeholder management plan

Buy Now
Questions 33

A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.

How could the business analyst address the end user's concerns about the new interface?

Options:

A.

Consult the stakeholder register to evaluate if the user has authority to influence the project.

B.

Develop a prototype to gather functional requirements.

C.

Develop a use case package to support the user interface.

D.

Document the business data objects using an entity relationship diagram.

Buy Now
Questions 34

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

Options:

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Buy Now
Questions 35

Which of the following techniques contrasts the current and desired business views to analyze possible business changes?

Options:

A.

Impact analysis SWOT analysis

B.

SWOT analysis

C.

Gap analysis

D.

Trend analysis

Buy Now
Questions 36

A key component of the business analyst's role during acceptance testing is to:

Options:

A.

execute all acceptance tests on behalf of the user community.

B.

delegate execution of acceptance testing and defect identification to users.

C.

act as a resource only when users encounter difficulties while performing tests.

D.

assist the quality assurance department by defining acceptance criteria.

Buy Now
Questions 37

During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

Options:

A.

Ask the developer to correct the logo as stated in the requirement.

B.

Confront the stakeholder that requested the change.

C.

Follow the change control process as defined in the business analysis plan.

D.

Discuss the change in the next stakeholder meeting.

Buy Now
Questions 38

The document that defines the process for managing requirements revisions is the:

Options:

A.

project management plan.

B.

change management plan.

C.

communications management plan.

D.

scope management plan.

Buy Now
Questions 39

When determining the value of a business case, which tool or technique should be used?

Options:

A.

Variance analysis

B.

Cost-benefit analysis

C.

SWOT analysis

D.

Feasibility analysis

Buy Now
Questions 40

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.

How should the business analyst obtain approval?

Options:

A.

Conduct a formal or informal review of the requirements.

B.

Create and maintain an audit history log of changes to requirements.

C.

Provide a defect tracking log for review.

D.

Send an email requesting approval of requirements.

Buy Now
Questions 41

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

Options:

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Buy Now
Questions 42

A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.

Which technique or tool should be used?

Options:

A.

Competitive analysis

B.

Benchmarking

C.

Trend analysis

D.

Focus group

Buy Now
Questions 43

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?

Options:

A.

Multivoting

B.

MoSCoW

C.

Time-boxing

D.

Budget analysis

Buy Now
Questions 44

Which function involves auditing both the quality requirements to resolve discrepancies and the results of quality control measurements to ensure that appropriate quality standards and operational definitions are being used?

Options:

A.

Quality control

B.

Quality assessment

C.

Quality management

D.

Quality assurance

Buy Now
Questions 45

Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?

Options:

A.

Decision tree

B.

Functional decomposition

C.

Expected monetary value

D.

Weighted criteria

Buy Now
Questions 46

A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.

What would be the most viable technique to use in this scenario?

Options:

A.

A review of the solution prototype

B.

A brainstorming session

C.

A use-case development session

D.

A review of the previous version

Buy Now
Questions 47

A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.

From the business analysis perspective, the main reason for this business failure was a failure to:

Options:

A.

set the product positioning.

B.

review and evaluate market expectations.

C.

gather the appropriate usability requirements.

D.

establish measurable success criteria in the business case.

Buy Now
Questions 48

Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.

What should the business analyst recommend to the project manager?

Options:

A.

Ask the developer's team manager for more resources.

B.

Review the business case to reconsider the project.

C.

Hire external subject matter experts for the core project team.

D.

Ask the sponsor for more resources.

Buy Now
Questions 49

A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?

Options:

A.

The industry is unregulated.

B.

The project impact is contained within a small department of the company.

C.

Errors in the product could result in financial solvency.

D.

The organization follows an iterative project life cycle.

Buy Now
Questions 50

A new project's goal is to replace an existing system. What is an input into solution evaluation and decision making in this context?

Options:

A.

A Cost-benefit analysis of the existing system

B.

Technical readiness of the development team

C.

New solution design specification

D.

Customer metrics on the existing system

Buy Now
Questions 51

Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?

Options:

A.

Brainstorming

B.

Interviewing

C.

Prototyping

D.

Surveying

Buy Now
Questions 52

In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be

reported.

What should the business analyst use?

Options:

A.

Configuration management system

B Work breakdown structure

B.

Traceability matrix

C.

Context models

Buy Now
Questions 53

A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?

Options:

A.

Risks identified in the risk management plan were not addressed properly.

B.

There is no issue since the product exceeded the customer expectations.

C.

The sponsor approved the release of the product without reviewing the budget.

D.

Requirements were not properly traced and monitored.

Buy Now
Questions 54

Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system. Which of the following has the business analyst defined?

Options:

A.

Solution design

B.

Business requirements

C.

Solution scope

D.

Business case

Buy Now
Questions 55

A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.

How can the business analyst determine the impact on existing requirements?

Options:

A.

Perform a stakeholder analysis.

B.

Review the requirements traceability matrix.

C.

Use time-boxing to defer the new requirement.

D.

Update the use case documentation.

Buy Now
Questions 56

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?

Options:

A.

The product was not adequately tested in accordance with the test plan.

B.

The requirements matrix did not adequately track back to client requirements.

C.

Requirement changes were not properly identified in the project charter.

D.

The product design was not properly reviewed by the quality department.

Buy Now
Questions 57

A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

Options:

A.

Perform a work breakdown structure.

B.

Perform a feasibility study.

C.

Perform process modelling.

D.

Perform a structured walkthrough.

Buy Now
Questions 58

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

Options:

A.

Requirements cards

B.

Requirements baseline

C.

Requirements management tool

D.

Requirements traceability matrix

Buy Now
Questions 59

A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.

Which course of action should the business analyst take?

Options:

A.

Evaluate if the new set of regulations is aligned with the business case.

B.

Evaluate the impact of the change on the project schedule.

C.

Obtain management sign-off on the new set of regulations.

D.

Check the traceability matrix to identify affected use cases.

Buy Now
Questions 60

The requirements traceability matrix should primarily be used to:

Options:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Buy Now
Exam Code: PMI-PBA
Exam Name: PMI Professional in Business Analysis
Last Update: Jan 12, 2025
Questions: 200

PDF + Testing Engine

$87.15  $249

Testing Engine

$78.75  $225
buy now PMI-PBA testing engine

PDF (Q&A)

$69.65  $199
buy now PMI-PBA pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 18 Jan 2025