Which is the correct formula for calculating expected activity cost for three-point estimating?

Options:

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Buy Now
Questions 5

Monte Carlo is which type of risk analysis technique?

Options:

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Buy Now
Questions 6

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Buy Now
Questions 7

Which activity involves ensuring that the composition of a projects configuration items is correct?

Options:

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Buy Now
Questions 8

Which of the following is an input to the Direct and Manage Project Execution process?

Options:

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Buy Now
Questions 9

Which of the following is an output from Control Scope?

Options:

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Buy Now
Questions 10

Which of the following is an output of the Distribute Information process?

Options:

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Buy Now
Questions 11

Which of the following characteristics are found in a functional organizational structure?

Options:

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager's role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Buy Now
Questions 12

An input to the Perform Quantitative Risk Analysis process is the:

Options:

A.

quality management plan.

B.

project management plan.

C.

communications management plan.

D.

schedule management plan.

Buy Now
Questions 13

Labor, materials, equipment, and supplies are examples of:

Options:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Buy Now
Questions 14

What causes replanning of the project scope?

Options:

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Buy Now
Questions 15

In which Process Group are lessons learned documented?

Options:

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Buy Now
Questions 16

When sequencing activities, what does the common acronym FF stand for?

Options:

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

Buy Now
Questions 17

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Options:

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

Buy Now
Questions 18

The process of identifying the stakeholders' information needs is completed during:

Options:

A.

Plan Communications.

B.

Manage Stakeholder Expectations.

C.

Stakeholder Analysis.

D.

Identify Stakeholders.

Buy Now
Questions 19

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

Options:

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

Buy Now
Questions 20

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Options:

A.

Exploit

B.

Share

C.

Enhance

D.

Transfer

Buy Now
Questions 21

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

Options:

A.

The influence of the stakeholders increases, the cost of changes increases.

B.

The influence of the stakeholders decreases, the cost of changes increases.

C.

The influence of the stakeholders increases, the cost of changes decreases.

D.

The influence of the stakeholders decreases, the cost of changes decreases.

Buy Now
Questions 22

Which is an example of Administer Procurements?

Options:

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Buy Now
Questions 23

The process of formalizing acceptance of the completed project deliverables is known as:

Options:

A.

Validate Scope.

B.

Close Project or Phase.

C.

Control Quality.

D.

Verify Scope.

Buy Now
Questions 24

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Buy Now
Questions 25

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Buy Now
Questions 26

Perform Quality Control is accomplished by:

Options:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Buy Now
Questions 27

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 28

Which is one of the major outputs of Sequence Activities?

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list

Buy Now
Questions 29

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Buy Now
Questions 30

The Human Resource Management processes are:

Options:

A.

Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.

B.

Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.

C.

Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.

D.

Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

Buy Now
Questions 31

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Buy Now
Questions 32

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Buy Now
Questions 33

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Buy Now
Questions 34

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Buy Now
Questions 35

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

Options:

A.

0.45

B.

0.56

C.

0.70

D.

1.36

Buy Now
Questions 36

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

Buy Now
Questions 37

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Buy Now
Questions 38

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

Options:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

Buy Now
Questions 39

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Buy Now
Questions 40

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Buy Now
Questions 41

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Buy Now
Questions 42

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Questions 43

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Buy Now
Questions 44

An input to the Manage Project Team process is:

Options:

A.

Work performance reports.

B.

Change requests.

C.

Activity resource requirements.

D.

Enterprise environmental factors.

Buy Now
Questions 45

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

Options:

A.

Enhance

B.

Share

C.

Exploit

D.

Accept

Buy Now
Questions 46

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Buy Now
Questions 47

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Buy Now
Questions 48

Which tool or technique is used in the Plan Scope Management process?

Options:

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Buy Now
Questions 49

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Questions 50

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Buy Now
Questions 51

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Buy Now
Questions 52

An output of the Validate Scope process is:

Options:

A.

A requirements traceability matrix.

B.

The scope management plan.

C.

Work performance reports.

D.

Change requests.

Buy Now
Questions 53

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

Options:

A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning

Buy Now
Questions 54

An output of the Direct and Manage Project Work process is:

Options:

A.

Deliverables.

B.

Activity lists.

C.

A work breakdown structure.

D.

A scope statement.

Buy Now
Questions 55

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Buy Now
Questions 56

Sensitivity analysis is typically displayed as a/an:

Options:

A.

Decision tree diagram.

B.

Tornado diagram.

C.

Pareto diagram.

D.

Ishikawa diagram.

Buy Now
Questions 57

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Buy Now
Questions 58

Which tool or technique is used in the Develop Project Management Plan process?

Options:

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Buy Now
Questions 59

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Options:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Buy Now
Questions 60

An input to the Plan Stakeholder Management process is:

Options:

A.

The project charter.

B.

The stakeholder analysis.

C.

A communication management plan.

D.

A stakeholder register.

Buy Now
Questions 61

In which Knowledge Area is the project charter developed?

Options:

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Buy Now
Questions 62

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

Options:

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Buy Now
Questions 63

Which items are components of a project management plan?

Options:

A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Buy Now
Questions 64

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Options:

A.

Verified deliverables.

B.

Validated deliverables.

C.

Acceptance criteria.

D.

Activity resource requirements.

Buy Now
Questions 65

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Buy Now
Questions 66

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Questions 67

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Buy Now
Questions 68

The scope management plan and scope baseline are contained in:

Options:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

Buy Now
Questions 69

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

Options:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Buy Now
Questions 70

The scope management plan and scope baseline are contained in:

Options:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

Buy Now
Questions 71

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

Options:

A.

Result

B.

Product

C.

Service

D.

Improvement

Buy Now
Questions 72

A disadvantage associated with virtual teams is that they:

Options:

A.

Require communication technology that is not readily available.

B.

Create difficulties when including people with disabilities.

C.

Often cannot accommodate teams that work different hours or shifts.

D.

Create the possibility for misunderstandings to arise.

Buy Now
Questions 73

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

Options:

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Buy Now
Questions 74

The following is a network diagram for a project.

PMI-100 Question 74

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Buy Now
Questions 75

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Buy Now
Questions 76

Specification of both the deliverables and the processes is the focus of:

Options:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Buy Now
Questions 77

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Buy Now
Questions 78

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Buy Now
Questions 79

The following is a network diagram for a project.

PMI-100 Question 79

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Buy Now
Questions 80

An input to the Perform Integrated Change Control process is:

Options:

A.

expert judgment

B.

seller proposals

C.

the project charter

D.

the project management plan

Buy Now
Questions 81

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Options:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Buy Now
Questions 82

The following is a network diagram for a project.

PMI-100 Question 82

The critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

17

Buy Now
Questions 83

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Options:

A.

Define Activities

B.

Direct and Manage Project Work

C.

Develop Project Management Plan

D.

Develop Project Charter

Buy Now
Questions 84

Which risk response strategy is common for both positive and negative risks?

Options:

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Buy Now
Questions 85

The three processes of Project Cost Management are:

Options:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Buy Now
Questions 86

Which of the following is an input to the Develop Project Charter process?

Options:

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Buy Now
Questions 87

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

Options:

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (T&M)

D.

Cost Plus Incentive Fee Contract (CPIF)

Buy Now
Questions 88

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Buy Now
Questions 89

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Buy Now
Questions 90

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Buy Now
Questions 91

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two

B.

Four

C.

Five

D.

Twelve

Buy Now
Questions 92

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Buy Now
Questions 93

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Buy Now
Questions 94

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Buy Now
Questions 95

The process to ensure that appropriate quality standards and operational definitions are used is:

Options:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Buy Now
Questions 96

What is project management?

Options:

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Buy Now
Questions 97

The completion of the project scope is measured against the:

Options:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Buy Now
Questions 98

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Buy Now
Questions 99

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

Options:

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Buy Now
Questions 100

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Buy Now
Questions 101

An input of the Create WBS process is:

Options:

A.

requirements documentation.

B.

scope baseline.

C.

project charter.

D.

validated deliverables.

Buy Now
Questions 102

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Buy Now
Questions 103

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Buy Now
Questions 104

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Buy Now
Questions 105

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

Options:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

Buy Now
Exam Code: PMI-100
Exam Name: Certified Associate in Project Management (CAPM)®
Last Update: Nov 16, 2024
Questions: 704

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now PMI-100 testing engine

PDF (Q&A)

$31.5  $104.99
buy now PMI-100 pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 23 Nov 2024