Black Friday Special - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

Hot Vendors

PK0-005 CompTIA Project+ Certification (2024) Questions and Answers

Questions 4

How does data discovery assist with data classification'?

Options:

A.

It shows where specific data is stored

B.

It automatically classifies data by keywords

C.

It helps to identify the data owner

D.

It provides assurance of data integrity

Buy Now
Questions 5

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

Options:

A.

Apply the SDLC process.

B.

Establish a program.

C.

Consult the CCB.

D.

Use different frameworks

Buy Now
Questions 6

Which of the following requires the MOST availability from the business team?

Options:

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Buy Now
Questions 7

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

Options:

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Buy Now
Questions 8

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options:

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Buy Now
Questions 9

Which of the following best describes a benefit of the CI/CD process?

Options:

A.

Software delivery is sped up without compromising quality.

B.

Incremental changes are done at the end of the project.

C.

The software is integrated with other projects easily.

D.

Updates are released every sprint.

Buy Now
Questions 10

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

Options:

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Buy Now
Questions 11

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

Options:

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Buy Now
Questions 12

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Buy Now
Questions 13

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Buy Now
Questions 14

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

Options:

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

Buy Now
Questions 15

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

Options:

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Buy Now
Questions 16

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Options:

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

Buy Now
Questions 17

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

Options:

A.

Assemble a new project with existing resources.

B.

Obtain the final report from release management.

C.

Notify the functional manager that resources are released.

D.

Allocate resources in a different project

Buy Now
Questions 18

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

Options:

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Buy Now
Questions 19

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

Options:

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Buy Now
Questions 20

During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

Options:

A.

Awareness of the local environment

B.

Awareness of the brand value

C.

Awareness of the resource constraints

D.

Awareness of the company's mission

Buy Now
Questions 21

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

Options:

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Buy Now
Questions 22

Which of the following activities are important parts of the closing phase? (Select two).

Options:

A.

Releasing resources

B.

Locking risks

C.

Updating stakeholder register

D.

Closing contracts

E.

Completing the work breakdown structure

F.

Negotiating the next project

Buy Now
Questions 23

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?

Options:

A.

Buy a replacement for the faulty equipment.

B.

Get the maintenance team to resolve the issue.

C.

Escalate the issue to the project sponsor.

D.

Rate the severity of the impact the issue has on the project.

Buy Now
Questions 24

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

Options:

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Buy Now
Questions 25

Which of the following statements best describes zero-based budgeting?

Options:

A.

Start with the budget from the last project and add any new expenses.

B.

Start with allocating expenses based on the importance of the project.

C.

Start the project with a fixed amount decided by the management team.

D.

Start with no financial plan and justify each new expense.

Buy Now
Questions 26

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

Options:

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Buy Now
Questions 27

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

Options:

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

Buy Now
Questions 28

Which of the following is a quantitative key performance indicator?

Options:

A.

The project sponsor ranked the graphics of an application as four out of five.

B.

The project implements the application in ten different geographical regions.

C.

The workers complete tasks on average 25% faster using a new application.

D.

The use of a multimedia interface appeals more to users under the age of 21.

Buy Now
Questions 29

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

Options:

A.

Regression testing

B.

Smoke testing

C.

Stress testing

D.

Automation testing

Buy Now
Questions 30

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

Options:

A.

Rollback plan

B.

Downtime stage

C.

Maintenance window

D.

Validation checks

Buy Now
Questions 31

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

Options:

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Buy Now
Questions 32

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Options:

A.

Creating a backlog

B.

Managing the quality of deliverables

C.

Updating the issue log

D.

Performing a risk assessment

E.

Validating the deliverables

F.

Reconciling the project budget

Buy Now
Questions 33

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

Options:

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Buy Now
Questions 34

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

Options:

A.

Company vision

B.

Global environment

C.

Brand value

D.

Mission statement

E.

Portfolio budget

F.

Local legislation

Buy Now
Questions 35

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Buy Now
Questions 36

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options:

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Buy Now
Questions 37

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

Options:

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Buy Now
Questions 38

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

Options:

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Buy Now
Questions 39

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

Options:

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Buy Now
Questions 40

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

Options:

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Buy Now
Questions 41

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

Options:

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Buy Now
Questions 42

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Buy Now
Questions 43

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Options:

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Buy Now
Questions 44

Which of the following is the best example of a breach of physical security?

Options:

A.

System user IDs being used by multiple individuals

B.

Printers that do not request user authentication

C.

Developers having full access to both development and production environments

D.

Project documentation that is only kept on a removable device

Buy Now
Questions 45

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options:

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Buy Now
Questions 46

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

Options:

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Buy Now
Questions 47

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

Options:

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Buy Now
Questions 48

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Buy Now
Questions 49

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Options:

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

Buy Now
Questions 50

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

Options:

A.

Telephone

B.

Videoconference

C.

Face-to-face

D.

Email

Buy Now
Questions 51

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

Options:

A.

Project status report

B.

Project evaluation review

C.

Project management software

D.

Requirements traceability matrix

Buy Now
Questions 52

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Buy Now
Questions 53

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

Options:

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Buy Now
Questions 54

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Buy Now
Questions 55

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

Options:

A.

Milestone chart

B.

Work breakdown structure

C.

Project charter

D.

Detailed scope statement

Buy Now
Questions 56

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Options:

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Buy Now
Questions 57

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

Options:

A.

Resource management system

B.

Issue log

C.

Ticketing system

D.

Backlog

Buy Now
Questions 58

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

Options:

A.

Multiauthoring software

B.

Word processor

C.

Real-time polling

D.

Conferencing platforms

Buy Now
Questions 59

A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?

Options:

A.

Resolution time

B.

Issue list

C.

Work breakdown structure

D.

Cost optimization

Buy Now
Questions 60

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options:

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Buy Now
Questions 61

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

Options:

A.

Encryption

B.

Multifactor authentication

C.

Quality assurance

D.

Password protection

Buy Now
Questions 62

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:

A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

Buy Now
Questions 63

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

Options:

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Buy Now
Questions 64

Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

Options:

A.

Assign action items to attendees.

B.

Distribute an agenda.

C.

Email the minutes from the previous meeting.

D.

Schedule a convenient time.

Buy Now
Questions 65

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Buy Now
Questions 66

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options:

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Buy Now
Questions 67

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

Options:

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Buy Now
Questions 68

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Options:

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Buy Now
Questions 69

Which of the following software programs would be best to use to store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Buy Now
Questions 70

PK0-005 Question 70

Given the following network diagram:

Which of the following is the critical path?

Options:

A.

A-C-G-K-M

B.

A-B-D-l-L-M

C.

A-B-E-J-L-M

D.

A-B-F-L-M

Buy Now
Questions 71

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

Options:

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Buy Now
Questions 72

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

Options:

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

Buy Now
Questions 73

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

Options:

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

Buy Now
Questions 74

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Options:

A.

Agile works through larger integrated teams.

B.

Agile promotes project manager ownership over deliverables.

C.

Agile reinforces the importance of comprehensive documentation.

D.

Agile has more customer involvement throughout development.

E.

Agile is more flexible to allow for changes in scope.

F.

Agile is comprised of well-defined phases.

Buy Now
Questions 75

Given the following velocity chart:

PK0-005 Question 75

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Options:

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

Buy Now
Questions 76

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Buy Now
Questions 77

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

Options:

A.

Time to be fixed

B.

Impact to project

C.

Issue category

D.

Resource availability

Buy Now
Questions 78

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Buy Now
Questions 79

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

Options:

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Buy Now
Questions 80

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Options:

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Buy Now
Questions 81

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

Options:

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Buy Now
Questions 82

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

Options:

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start

Buy Now
Questions 83

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

PK0-005 Question 83

PK0-005 Question 83

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Buy Now
Questions 84

Which of the following is a typical characteristic of Scrum?

Options:

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Buy Now
Questions 85

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Questions 86

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Options:

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Buy Now
Questions 87

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

Options:

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2024)
Last Update: Nov 19, 2024
Questions: 291

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now PK0-005 testing engine

PDF (Q&A)

$31.5  $104.99
buy now PK0-005 pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 23 Nov 2024