For heavy equipment, such as anetwork storage device weighing approximately 600 kg/1,300 lbs, newfloor loading calculationsare indeed required, particularly since the rack is non-standard. Astructural engineer, approved by the building owner, should conduct these calculations to ensure the floor can safely support the new load without risking structural integrity.
Detailed Explanation:
Data centers are designed with specific floor load ratings, which are determined during the design phase based on anticipated equipment. When adding or replacing equipment that is significantly heavy or non-standard, reassessing the floor's capacity is essential to avoid overloading. A structural engineer has the expertise to verify if the existing floor can accommodate the weight and, if not, can recommend reinforcement measures.
This step ensures compliance with safety standards and helps prevent damage to the infrastructure,which could lead to costly repairs or even catastrophic failure in extreme cases.
EPI Data Center Specialist References:
EPI Data Center Specialist training advises that any changes in the data center load, particularly involving non-standard and heavy equipment, warrant a structural assessment. Ensuring compliance with floor load capacity is a critical safety and operational concern, as underscoring data center infrastructure reliability and safety is a priority in EPI's best practices.