Summer Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

CAPM Certified Associate in Project Management (CAPM) Questions and Answers

Questions 4

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.

What is this an example of?

Options:

A.

Monitoring the traceability matrix

B.

Managing the scope

C.

Maintaining the product backlog

D.

Managing the cost benefit

Buy Now
Questions 5

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

Options:

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

Buy Now
Questions 6

Which tool should a project manager consider to deal with multiple sources of risk?

Options:

A.

An updated risk register

B.

Risk breakdown structure

C.

Issue log

D.

Stakeholder register

Buy Now
Questions 7

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Buy Now
Questions 8

When should Project Risk Management be conducted?

Options:

A.

Project Planning

B.

Monitoring and Controlling

C.

Quality Planning

D.

Throughout the project lifecycle

Buy Now
Questions 9

The features and functions that characterize a result, product, or service can refer to:

Options:

A.

project scope

B.

product scope

C.

service scope

D.

product breakdown structure

Buy Now
Questions 10

When does Monitor and Control Risks occur?

Options:

A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Buy Now
Questions 11

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Buy Now
Questions 12

Which set of activities should a project manager use as part of the Develop Team process?

Options:

A.

Training and establishing ground rules

B.

Networking activities and estimating team resources

C.

Conflict management activities and tracking team performance

D.

Recruit new team members and training

Buy Now
Questions 13

What is the term assigned to products or services having the same functional use but different technical characteristics?

Options:

A.

Scope

B.

Quality

C.

Specification

D.

Grade

Buy Now
Questions 14

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Buy Now
Questions 15

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

Options:

A.

Project charter, business documents, and project management plan

B.

Agreements, scope baseline, and project management plan

C.

Project charter, business case, and project management plan

D.

Work performance data, enterprise environmental factors, and project management plan

Buy Now
Questions 16

A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.

What communication step is missing from the daily meetings?

Options:

A.

Interpersonal communication

B.

Feedback response communication

C.

Push communication

D.

Pull communication

Buy Now
Questions 17

How can working in iterations increase the quality of the product being built?

Options:

A.

Teams have to do less planning and focus more on quality.

B.

The project manager has more time to document goals in advance.

C.

Less testing is required since it is done at the end of the project.

D.

Requirements are frequently clarified by users of the product.

Buy Now
Questions 18

What should be the frequency for meetings when transitioning from Scrum to Kanban?

Options:

A.

Weekly

B.

Daily

C.

When required

D.

Monthly

Buy Now
Questions 19

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

Options:

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

Buy Now
Questions 20

A project team has missed a milestone.

Which response strategy should be implemented?

Options:

A.

Communications

B.

Stakeholder

C.

Contingent

D.

Risk

Buy Now
Questions 21

What important leadership quality/qualities should project managers possess?

Options:

A.

Skills and behaviors related to specific domains of project management

B.

Skills and behaviors needed to guide a team and help an organization reach its goals

C.

Industry expertise that helps to better deliver business outcomes

D.

Industry and organizational expertise that enhances performance

Buy Now
Questions 22

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?

Options:

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

Buy Now
Questions 23

A project team member identifies a possibility......the team member ' s idea?

A project team member identifies a possibility of increasing project performance by adopting an innovative approach to a proposed solution. This also will save resources for the company and increase stakeholder satisfaction.

How should the project manager evaluate the team member ' s idea?

Options:

A.

Treat the idea using risk management processes, to handle it in a controlled and managed way.

B.

Perform an experiment simulation to confirm idea results, to make sure the cost to implement is worthwhile.

C.

Do a feasibility analysis study to confirm if an investment to explore a solution will add value.

D.

Submit the idea as a change request to the change control board to ensure that all interests are met.

Buy Now
Questions 24

The process of prioritizing risks for further analysis or action is known as:

Options:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

Buy Now
Questions 25

What is the process of ensuring that project resources are assigned and available?

Options:

A.

Control Procurements

B.

Acquire Resources

C.

Control Resources

D.

Plan Procurement Management

Buy Now
Questions 26

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

Options:

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

Buy Now
Questions 27

A project manager needs to request outside support......manager need to create

A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?

Options:

A.

Time and material (TandM)

B.

Cost plus fixed fee (CPFF)

C.

Fixed price

D.

Cost plus award fee (CPAF)

Buy Now
Questions 28

When planning communications management what input identifies key stakeholders?

Options:

A.

Work performance information

B.

Project schedule

C.

Project charter

D.

Work performance reports

Buy Now
Questions 29

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Buy Now
Questions 30

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Buy Now
Questions 31

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

Options:

A.

Initiating Process Group

B.

Planning Process Group

C.

Executing Process Group

D.

Monitoring and Controlling Process Group

Buy Now
Questions 32

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

Options:

A.

Early requirements gathering

B.

Feedback analysis

C.

Progressive elaboration

D.

Requirements documentation

Buy Now
Questions 33

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

Options:

A.

8

B.

18

C.

36

D.

40

Buy Now
Questions 34

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

Options:

A.

$800

B.

$1000

C.

$1250

D.

$1800

Buy Now
Questions 35

What can a project manager review to understand the status of a project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Buy Now
Questions 36

Variance and trend analysis is a tool and technique used in which process?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

Buy Now
Questions 37

In an organization with a projectized organizational structure, who controls the project budget?

Options:

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Buy Now
Questions 38

Which is the correct hierarchy in a project environment, from most to least Inclusive?

Options:

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

Buy Now
Questions 39

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

Options:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Buy Now
Questions 40

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Buy Now
Questions 41

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Options:

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Buy Now
Questions 42

Which tool or technique is used in the Estimate Costs process?

Options:

A.

Acquisition

B.

Earned value management

C.

Vendor bid analysis

D.

Forecasting

Buy Now
Questions 43

A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?

Options:

A.

Prepare a WBS with task sequencing and detail the duration and cost estimates.

B.

Prepare a WBS to work package level to effectively manage duration and cost estimates.

C.

Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.

D.

Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.

Buy Now
Questions 44

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Buy Now
Questions 45

How does a requirements traceability matrix help to determine whether a product is ready for delivery?

Options:

A.

It captures assigned tasks and their estimated durations.

B.

It confirms the completion of all stories in the backlog.

C.

It assesses the quality of test cases and expected results.

D.

It tracks links between the approved requirements and each work product.

Buy Now
Questions 46

A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.

Which evaluation technique should be used here?

Options:

A.

Exploratory testing

B.

Integration testing

C.

User acceptance testing

D.

Day-in-the-life testing

Buy Now
Questions 47

What is the first step in the Stakeholder Management process?

Options:

A.

Plan Stakeholder Engagement

B.

Identify Stakeholders

C.

Manage Stakeholder Responsibility

D.

Monitor Stakeholder Activity

Buy Now
Questions 48

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Buy Now
Questions 49

An organizational structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques is referred to as:

Options:

A.

Project Management Information System

B.

Project Management System

C.

Project Management Office

D.

Project Management Knowledge Area

Buy Now
Questions 50

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Buy Now
Questions 51

Which of the in an adaptive project environment, which action helps the project manager?

Options:

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Buy Now
Questions 52

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Options:

A.

Organizational process updates

B.

Quality metrics

C.

Change requests

D.

Quality control measurements

Buy Now
Questions 53

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Buy Now
Questions 54

Which of the following processes are part of the Project Integration Management Knowledge Area?

Options:

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

Buy Now
Questions 55

Which tasks should a project manager perform in order to manage the project schedule effectively?

Options:

A.

Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities. Develop Schedule

B.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule. Control Schedule

C.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities. Develop Schedule

D.

Define Activities. Sequence Activities, Estimate Activity Durations. Define Quality of Activities. Estimate Cost of Activities, Develop Schedule

Buy Now
Questions 56

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Cost-benefit analysis

B.

Updated project charter

C.

Approved change request

D.

Multicriteria decision analysis

Buy Now
Questions 57

Which input to the Plan Risk Management process provides information on high-level risks?

Options:

A.

Project charter

B.

Enterprise environmental factors

C.

Stakeholder register

D.

Organizational process assets

Buy Now
Questions 58

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

Options:

A.

Power/influence grid

B.

Power/interest grid

C.

Influence/impact grid

D.

Salience model

Buy Now
Questions 59

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.

Options:

A.

Develop Schedule

B.

Define Activities

C.

Define Scope

D.

Collect Requirements

Buy Now
Questions 60

Match the project life cycle type with its corresponding definition.

CAPM Question 60

Options:

Buy Now
Questions 61

Match the process with its corresponding Process Group:

CAPM Question 61

Options:

Buy Now
Questions 62

Agile release planning provides a high-level summary timeline of the release schedule based on.

Options:

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Buy Now
Questions 63

Which of the following is an output from Control Scope?

Options:

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Buy Now
Questions 64

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

Options:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Buy Now
Questions 65

Which process is included in the Project Integration Management Knowledge Area?

Options:

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Buy Now
Questions 66

An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?

Options:

A.

Informal conversation

B.

Face-to-face meeting

C.

Short email update

D.

Written report

Buy Now
Questions 67

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Buy Now
Questions 68

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Buy Now
Questions 69

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Buy Now
Questions 70

Which of the following projects is a quality candidate for adaptive approaches?

Options:

A.

Installing new computers across offices

B.

Retrofitting an old building

C.

Upgrading an information system

D.

Designing a new suspension bridge

Buy Now
Questions 71

A key benefit of the Manage Communications process is that it enables:

Options:

A.

The best use of communication methods.

B.

An efficient and effective communication flow.

C.

Project costs to be reduced.

D.

The best use of communication technology.

Buy Now
Questions 72

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Buy Now
Questions 73

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Buy Now
Questions 74

Which sentence summarizes the salience model?

Options:

A.

Classifies stakeholders based on assessment of their power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Buy Now
Questions 75

Managing procurement relationships and monitoring contract performance are part of which process?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements

Buy Now
Questions 76

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?

Options:

A.

Review the project management plan.

B.

Share the requirements traceability matrix the same way it was shared previously.

C.

Consult the business analysis communications management plan.

D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.

Buy Now
Questions 77

A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear. What should the project manager do next?

Options:

A.

Add the risk to the project risk register, as the lack of solutions could impact how the product is built.

B.

Add the issue to the project issue log, as it will impact the project performance.

C.

Facilitate a brainstorming session for the team to discuss ideas to solve the problem.

D.

Meet with the project sponsor to understand their vision on how to address the problem.

Buy Now
Questions 78

A weighting system is a tool for which area of Conduct Procurements?

Options:

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller ' s

D.

Planning purchase and acquisition

Buy Now
Questions 79

An input to the Identify Stakeholders process is:

Options:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Buy Now
Questions 80

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

Options:

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

Buy Now
Questions 81

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Buy Now
Questions 82

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

Options:

A.

Plan Resource Management

B.

Estimate Activity Resources Communications

C.

Estimate Costs

D.

Acquire Resources

Buy Now
Questions 83

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Buy Now
Questions 84

Which of the following is TRUE about most project life cycles?

Options:

A.

Staffing level is highest at the start.

B.

The stakeholders ' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Buy Now
Questions 85

Which Process Group typically consumes the bulk of a project ' s budget?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

Buy Now
Questions 86

After defining activities in project schedule management, which processes should a project manager follow?

Options:

A.

Sequence Activities and Estimate Activity Durations

B.

Estimate Activity Durations and Control Schedule

C.

Develop Schedule and Control schedule

D.

Review Activities and Develop Schedule

Buy Now
Questions 87

Which is an input to the Verify Scope process?

Options:

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Buy Now
Questions 88

During which process would stakeholders provide formal acceptance of the completed project scope?

Options:

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Buy Now
Questions 89

Which of these is true of project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Buy Now
Questions 90

The process to ensure that appropriate quality standards and operational definitions are used is:

Options:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Buy Now
Questions 91

Which is a method of prototyping that creates a functioning representation of the final finished product to the user?

Options:

A.

Low-fidelity prototyping

B.

High-fidelity prototyping

C.

Data prototyping

D.

Report prototyping

Buy Now
Questions 92

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Buy Now
Questions 93

The Define Scope process is in which of the following Process Groups?

Options:

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Buy Now
Questions 94

Which tool uses an algorithm based on historical data to calculate cost?

Options:

A.

Three-point estimating

B.

Parametric estimating

C.

Analogous estimating

D.

Relative estimating

Buy Now
Questions 95

The zero duration of milestones in project planning occurs because milestones:

Options:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Buy Now
Questions 96

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

Options:

A.

The risk management plan and the assumption log

B.

Costs estimates and cost forecast

C.

The risk management plan and the basis of estimates

D.

The assumption log and the project charter

Buy Now
Questions 97

Which process numerically analyzes the effect of identified risks on overall project objectives?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 98

A project manager builds consensus and overcomes obstacles by employing which communication technique?

Options:

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Buy Now
Questions 99

Which project life cycle follows a plan reviewed and approved by the stakeholders?

Options:

A.

Predictive

B.

Adaptive

C.

Iterative

D.

Incremental

Buy Now
Questions 100

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Options:

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Buy Now
Questions 101

What can the cost management plan be established?

Options:

A.

Cost baseline

B.

Cost estimates

C.

Basis of estimates

D.

Control thresholds

Buy Now
Questions 102

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

Options:

A.

Schedule network analysis

B.

Reserve analysis

C.

Alternative analysis

D.

Variance analysis

Buy Now
Questions 103

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

Options:

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Buy Now
Questions 104

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Buy Now
Questions 105

An input to Develop Project Charter is a/an:

Options:

A.

Business case.

B.

Activity list.

C.

Project management plan.

D.

Cost forecast.

Buy Now
Questions 106

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 107

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Buy Now
Questions 108

In which domain of project management would a Pareto chart provide useful information?

Options:

A.

Project Scope Management

B.

Project Time Management

C.

Project Communications Management

D.

Project Quality Management

Buy Now
Questions 109

If a project manager effectively manages project knowledge, a key benefits is that:

Options:

A.

all stakeholders have access to the same information.

B.

the project team is able to understand the project status.

C.

project stakeholders have a clear picture of the project.

D.

new knowledge is added to organizational process assets.

Buy Now
Questions 110

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

Options:

A.

End user

B.

Product owner

C.

Subject matter experts (SMEs)

D.

Project sponsor

E.

Project team

Buy Now
Questions 111

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

Options:

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Buy Now
Questions 112

An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

Options:

A.

Task switching

B.

Multitasking

C.

Prediction

D.

Full allocation

Buy Now
Questions 113

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

Buy Now
Questions 114

Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)

Options:

A.

Current state analysis

B.

Facilitated workshops

C.

Scheduled interviews

D.

Shop floor observation

E.

Brainstorming sessions

Buy Now
Questions 115

Which tool or technique is effective in a project in which the deliverable is not a service or result?

Options:

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Buy Now
Questions 116

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

3

B.

5

C.

7

D.

9

Buy Now
Questions 117

Which conflict resolution technique produces the most lasting results?

Options:

A.

Withdraw/avoid

B.

Smooth/accommodate

C.

Compromise/reconcile

D.

Collaborate/problem solve

Buy Now
Questions 118

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

Options:

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

Buy Now
Questions 119

A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?

Options:

A.

Create a product backlog with the information depicted in the WBS and prioritize the newly developed user stories into iterations.

B.

Accept this limitation and perform accordingly since the WBS can only be used in Scrum iterations.

C.

Consider reforming the structure of the company first as it is difficult for a company to transition from predictive to adaptive methods.

D.

Save the WBS in the historical data as the information can only be used for educational purposes and not as inputs for creating user stories.

Buy Now
Questions 120

The scope of a project cannot be defined without some basic understanding of how to create the specified:

Options:

A.

objectives

B.

schedule

C.

product

D.

approach

Buy Now
Questions 121

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Buy Now
Questions 122

Which is an example of an internal enterprise environmental factor?

Options:

A.

Market Share brand recognition

B.

Factory location

C.

Local government regulation

D.

Industry research

Buy Now
Questions 123

Plan Communications Management develops an approach and plan for project communications based on stakeholders ' needs and requirements and:

Options:

A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

Buy Now
Questions 124

Select three elements that apply to agile/ adaptive environments

Options:

A.

Frequent team checkpoints

B.

Colocation

C.

Access to information

D.

Virtual team members

E.

Geographically dispersed team

Buy Now
Questions 125

Which contract type is least desirable to a vendor?

Options:

A.

Fixed price with economic price adjustment (FPEPA)

B.

Firm fixed price (FFP)

C.

Cost plus fixed fee (CPFF >

D.

Cost plus award fee (CPAF >

Buy Now
Questions 126

During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?

Options:

A.

It is calculated incorrectly, as it cannot be zero for an in-flight project; otherwise the project is completed.

B.

Change it to a negative value to show that the project is falling behind.

C.

Zero is a perfectly valid value for an in-flight project; hence share the zero value with the stakeholder.

D.

Change it to a positive value to show that the project is ahead of its baseline schedule.

Buy Now
Questions 127

A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?

Options:

A.

Resource availability

B.

Infrastructure

C.

Academic research

D.

Corporate knowledge base

Buy Now
Questions 128

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Buy Now
Questions 129

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 130

In project management, which document is used to start the initial risk identification?

Options:

A.

Assumption log

B.

Risk management plan

C.

Risk register

D.

Issue log

Buy Now
Questions 131

In what type of organizational structure does a project manager develop their role and work with a team assigned by job function?

Options:

A.

Matrix - strong

B.

Matrix - balanced

C.

Virtual

D.

Functional

Buy Now
Questions 132

What tools or techniques are necessary to create the project management plan?

Options:

A.

Meetings and data analysis

B.

Expert judgment and data gathering

C.

Interpersonal skills and change control

D.

Data analysis and expert judgment

Buy Now
Questions 133

In a project using agile methodology, who may perform the quality control activities?

Options:

A.

A group of quality experts at specific times during the project

B.

The project manager only

C.

All team members throughout the project life cycle

D.

Selected stakeholders at specific times during the project

Buy Now
Questions 134

At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?

Options:

A.

Run a spike to ensure all information available is correct and then decide which stories to implement.

B.

Develop a user story analysis based on the work done, depicting the current status, S-curve, schedule variance (SV), and planned value (PV).

C.

Plan the backlog by estimating and reprioritizing the user stories as new information becomes available.

D.

Bring up all risks for implementing the user stories and discuss possible solutions.

Buy Now
Questions 135

Which tools and techniques should a project manager use to monitor risks?

Options:

A.

Expert judgment, data analysis, and interpersonal and real skills

B.

Data analysis, audits, and decision making

C.

Expert judgement, audits, and decision making

D.

Meetings, data gathering, and expert judgment

Buy Now
Questions 136

How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?

Options:

A.

It details product or service failures experienced by the customer

B.

It clarifies the costs associated with assessing the quality of the product or service

C.

It accounts for costs used to avoid poor quality in the product or service

D.

It communicates product or service failures discovered by the project team

Buy Now
Questions 137

A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

What type of procurement document is the RFP?

Options:

A.

Bid document

B.

Statement of work (SOW)

C.

Source selection criteria

D.

Independent cost estimate

Buy Now
Questions 138

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Buy Now
Questions 139

A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?

Options:

A.

Business analyst, project manager, and sponsor

B.

Business analyst, project manager, and stakeholders

C.

Business analyst and project manager

D.

Only the business analyst

Buy Now
Questions 140

A project manager is preparing to meet with three crucial project stakeholders on a new project Which tools and techniques can the project manager use to capture stakeholder interest?

Options:

A.

Review stakeholder register and meeting

B.

Data analysis and communication skills

C.

Data gathering and data analysis

D.

Communication skills and cultural awareness

Buy Now
Questions 141

The Identify Stakeholders process is found in which Process Group?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Buy Now
Questions 142

What communications management process enables an effective information flow among project stakeholders ' ?

Options:

A.

Monitor Stakeholder Engagement

B.

Manage Communications

C.

Monitor Communications

D.

Manage Stakeholder Engagement

Buy Now
Questions 143

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Buy Now
Questions 144

It you established a contingency reserve including time, money, and resources, how are you handling risk?

Options:

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Buy Now
Questions 145

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Buy Now
Questions 146

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Requested changes

B.

Approved change requests

C.

Work performance information

D.

Implemented defect repair

Buy Now
Questions 147

After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?

Options:

A.

Appraisal costs

B.

Management reserves

C.

Cost of nonconformance

D.

Cost of conformance

Buy Now
Questions 148

A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?

Options:

A.

Earned Schedule + Actual Time

B.

Actual Time - Earned Schedule

C.

Planned Value - Earned Value

D.

Earned Value - Planned Value

Buy Now
Questions 149

When would resource leveling be applied to a schedule model?

Options:

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Buy Now
Questions 150

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

Options:

A.

Scope and impact of change to stakeholders

B.

Project scope and stakeholders goals

C.

Engagement level of key stakeholders

D.

Stakeholders expectations for the project

Buy Now
Questions 151

Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

Options:

A.

Build vs. buy

B.

Expert judgment

C.

Alternatives identification

D.

Product analysis

Buy Now
Questions 152

An input to the Plan Stakeholder Management process is:

Options:

A.

The project charter.

B.

The stakeholder analysis.

C.

A communication management plan.

D.

A stakeholder register.

Buy Now
Questions 153

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Buy Now
Questions 154

The following is a network diagram for a project.

CAPM Question 154

The shortest non-critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

16

Buy Now
Questions 155

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

Options:

A.

Project plan

B.

Business case

C.

Budget requirement

D.

Project charter

Buy Now
Questions 156

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Options:

A.

-8

B.

425

C.

1.4

D.

8

Buy Now
Questions 157

Which type of analysis would be used for the Plan Quality process?

Options:

A.

Schedule

B.

Checklist

C.

Assumption

D.

Cost-Benefit

Buy Now
Questions 158

A method to manage stakeholder expectations in the scope statement is to clearly:

Options:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

Buy Now
Questions 159

Which tools and techniques should a project manager use when estimating costs?

Options:

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Buy Now
Questions 160

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

Options:

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Buy Now
Questions 161

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

Options:

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

Buy Now
Questions 162

How many Project Management Process Groups are there?

Options:

A.

3

B.

4

C.

5

D.

6

Buy Now
Questions 163

A regression line is used to estimate:

Options:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Buy Now
Questions 164

Project reporting is a tool that is most closely associated with which process?

Options:

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

Buy Now
Questions 165

What is the recommended approach for handling risk in a high-variability environment?

Options:

A.

Adaptive

B.

Predictive

C.

Iterative

D.

Incremental

Buy Now
Questions 166

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

Options:

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Buy Now
Questions 167

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 168

What is a tailoring consideration for Project Scope Management ' ?

Options:

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Buy Now
Questions 169

What do top project managers do to maximize their sphere of influence within a project team?

Options:

A.

Consider management standards, economic factors, and sustainability strategies

B.

Contribute knowledge and expertise to others within the profession

C.

C Address political and strategic issues that impact the project ' s viability or quality

D.

D Demonstrate superior relationship and communication skills while displaying a positive attitude

Buy Now
Questions 170

A project manager is newly assigned to a project. Which document can help the project manager understand the project scope?

Options:

A.

Process flow diagram

B.

Data flow diagram

C.

Context diagram

D.

User interface flow

Buy Now
Questions 171

What is the purpose of the project management process groups?

Options:

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

Buy Now
Questions 172

To ensure stakeholder satisfaction; identified stakeholder needs should all be

Options:

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Buy Now
Questions 173

A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the timeline for development.

What should the project manager do next?

Options:

A.

Update the project management plan.

B.

Add the discovery to the assumptions.

C.

Evaluate the risk with the project team.

D.

Conduct an opportunity analysis with the team.

Buy Now
Questions 174

An input to the Plan Procurement Management process is:

Options:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Buy Now
Questions 175

One of the objectives of a quality audit is to:

Options:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Buy Now
Questions 176

The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?

Options:

A.

Prompt lists and data analysis

B.

Reports and representations of uncertainty

C.

Data analysis and risk audits

D.

Interpersonal and team skills and project management Information system

Buy Now
Questions 177

What is the equation to calculate cost variance (CV)?

Options:

A.

CV = EV / BAC

B.

CV = EV - AC

C.

CV = EV - BAC

D.

CV = EV / AC

Buy Now
Questions 178

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

Options:

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Buy Now
Questions 179

A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager ' s key responsibility during this phase?

Options:

A.

Defining the scope of the project

B.

Building a collaborative environment

C.

Creating a detailed project management plan

D.

Directing the delivery of the project

Buy Now
Questions 180

Technical capability, past performance, and intellectual property rights are examples of:

Options:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Buy Now
Questions 181

Which kind of communication should the project manager use when creating reports for government bodies?

Options:

A.

Hierarchical

B.

External

C.

Formal

D.

Official

Buy Now
Questions 182

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Buy Now
Questions 183

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?

Options:

A.

3 days

B.

5 days

C.

7 daysD .10 days

Buy Now
Questions 184

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

Options:

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Buy Now
Questions 185

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

Options:

A.

Organizational standard processes

B.

Marketplace conditions

C.

Historical information

D.

Templates

Buy Now
Questions 186

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Buy Now
Questions 187

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Buy Now
Questions 188

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Buy Now
Questions 189

According to the PMI Talent Triangle. leadership skills relate to the ability to:

Options:

A.

understand the high-level overview of the organization

B.

tailor traditional and agile tools for the project

C.

work with stakeholders to develop an appropriate project delivery

D.

guide, motivate, and direct a team to reach project goals

Buy Now
Questions 190

Select three processes that are associated with Project Schedule Management.

Options:

A.

Define Activities

B.

Plan Resource Management

C.

Estimate Activity Durations

D.

Develop Schedule

E.

Acquire Resources

Buy Now
Questions 191

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Buy Now
Questions 192

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

Options:

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

Buy Now
Questions 193

Which process involves determining, documenting, and managing stakeholders ' needs and requirements to meet project objectives?

Options:

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Buy Now
Questions 194

A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?

Options:

A.

Project Resource Management

B.

Project Quality Management

C.

Project Schedule Management

D.

Project integration Management

Buy Now
Questions 195

When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?

Options:

A.

Requirements matrix

B.

Presentation slides

C.

Story map

D.

Project management plan

Buy Now
Questions 196

What conflict resolution technique involves delaying the issue or letting others resolve it?

Options:

A.

Smooth/accommodate

B.

Collaborate/problem solve

C.

Withdraw/avoid

D.

Force/direct

Buy Now
Questions 197

When does the project team determine which dependencies are discretionary?

Options:

A.

Before the Define Activities process

B.

During the Define Activities process

C.

Before the Sequence Activities process

D.

During the Sequence Activities process

Buy Now
Questions 198

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Buy Now
Questions 199

Which factors should be considered for cross-cultural communication?

Options:

A.

Background, personality, and communications management plan

B.

Personality, background, and escalation process

C.

Sponsor relationship, personality and background

D.

Current emotional state, personality, and background

Buy Now
Questions 200

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

Options:

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Buy Now
Questions 201

The project management processes presented in the PMBOK Guide® should:

Options:

A.

always be applied uniformly.

B.

be selected as appropriate by the sponsor.

C.

be selected as appropriate by the project team.

D.

be applied based on ISO guidelines.

Buy Now
Questions 202

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

Options:

A.

Daily scrum

B.

Increments

C.

Sprint retrospective

D.

Sprint backlog

E.

Product backlog

Buy Now
Questions 203

What is the project manager ' s responsibility in Project Integration Management?

Options:

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

Buy Now
Questions 204

Which of the following lists represents the outputs of the Monitor Communications process?

Options:

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Buy Now
Questions 205

What process group includes processes performed to complete work to satisfy the project requirements defined in the project management plan?

Options:

A.

InitiatingB Executing

B.

Monitoring and Controlling

C.

Planning

Buy Now
Questions 206

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Buy Now
Questions 207

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Buy Now
Questions 208

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

Options:

A.

stakeholder management strategy.

B.

communications management plan,

C.

stakeholder register,

D.

performance report.

Buy Now
Questions 209

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Buy Now
Questions 210

Which of the following activities are included as part of a project manager ' s responsibilities?

Options:

A.

Direct, control, and focus on structure.

B.

Problem solve , achieve the bottom line, and focus on success.

C.

Control, maintain project status, and develop.

D.

Inspire, engage, and build relationships with people.

Buy Now
Questions 211

Who defines the scope of the product

Options:

A.

The client

B.

The project manager

C.

The team

D.

The program manager

Buy Now
Questions 212

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

Options:

A.

Implement Appropriate Response

B.

Plan Project Risk Management

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 213

What are the Project Procurement Management processes?

Options:

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Buy Now
Questions 214

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Buy Now
Questions 215

What is the best tool to calculate the critical path on a project?

Options:

A.

Critical chain method

B.

Graphical evaluation and review technique (GERT) diagram

C.

Gantt chart

D.

Project network diagram

Buy Now
Questions 216

In which Project Management Process Group is the project charter developed?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Buy Now
Questions 217

In the Control Quality process, which tools and techniques can be applied to verify deliverable?

Options:

A.

Statistical sampling, inspection, and meetings

B.

Lessons learned register, control charts, and product evaluation

C.

Checklists, retrospective documents, and approved change requests

D.

Black box tests, questionnaires and surveys, and lessons learned register

Buy Now
Questions 218

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Buy Now
Questions 219

During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?

Options:

A.

Submit a change request for additional budget to secure a project resource.

B.

Consult with the functional manager for a replacement resource.

C.

Distribute work to other team members to reduce impact to the project schedule.

D.

Consult the risk register for an appropriate risk response.

Buy Now
Questions 220

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

Options:

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Buy Now
Questions 221

In agile projects while performing scope management. What is the definition of requirements

Options:

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

Buy Now
Questions 222

Which of the following is a tool and technique for Estimate Activity Durations?

Options:

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Buy Now
Questions 223

What tool or technique is used in the Collect Requirements process?

Options:

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

Buy Now
Questions 224

The product scope description is used to:

Options:

A.

Gain stakeholders ' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Buy Now
Questions 225

In which organizational structure would the project manager have most authority?

Options:

A.

Matrix-weak

B.

Matrix-balanced

C.

Matrix-strong

D.

Organic or simple

Buy Now
Questions 226

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

Options:

A.

Utilize the change control process.

B.

Crash the schedule to fix the defect.

C.

Leave the defect in and work around it.

D.

Fast-track the remaining development.

Buy Now
Questions 227

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

Options:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Buy Now
Questions 228

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

Options:

A.

Analogous

B.

Parametric

C.

Bottom-up

D.

Top-down

Buy Now
Questions 229

A project team identifies defects that will require a modification to a tool ' s functionality. What process should the project manager follow to obtain stakeholder buy-in?

Options:

A.

Control Schedule

B.

Perform Qualitative Risk Analysis

C.

Perform Integrated Change Control

D.

Control Scope

Buy Now
Questions 230

What is the primary purpose of Project Scope Management?

Options:

A.

Determining and managing stakeholder needs

B.

Contorting the status of the product scope and managing changes to its be seine

C.

Defining and controlling what is and is not included in the project

D.

Differentiating between the product scope and project scope

Buy Now
Questions 231

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

Options:

A.

risk management plan

B.

human resource management plan

C.

scope management plan

D.

procurement management plan

Buy Now
Questions 232

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Buy Now
Questions 233

An input of the Plan Procurement Management process is:

Options:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Buy Now
Questions 234

In which type of organization does the project manager have the maximum influence

Options:

A.

Centralized

B.

Composite

C.

Simple Organic

D.

Multi-divisional

Buy Now
Questions 235

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (TandM)

Buy Now
Questions 236

Which three processes are generally included in risk management? (Choose three)

Options:

A.

Monitor Risk Costs

B.

Identify Risks

C.

Plan Risk Responses

D.

Perform Qualitative Risk Analysis

E.

Estimate Risk Activity Resources

Buy Now
Questions 237

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

Options:

A.

The development team ran out of time and did not pull the social media story from the backlog.

B.

The development team completed all of the stories identified by the product owner as having the highest customer value.

C.

The sprint demo went smoothly and the team did not find any open issues.

D.

The social media story is a marketing priority and less important than other priorities.

Buy Now
Questions 238

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Buy Now
Questions 239

Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Buy Now
Questions 240

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?

Options:

A.

Strategic and business management skills

B.

Leadership skills

C.

Technical project management

D.

Organizational management

Buy Now
Questions 241

Which is a tool or technique used in Define Scope?

Options:

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Buy Now
Questions 242

Which of the following technology platforms is most effective for sharing information when managing virtual project teams?

Options:

A.

Video conferencing

B.

Audio conferencing

C.

Shared portal

D.

Email/chat

Buy Now
Questions 243

Which behavior is a management trait?

Options:

A.

Asking what and why

B.

Challenging the status quo

C.

Innovating

D.

Relying on control

Buy Now
Questions 244

Which item is a formal proposal to modify any document, deliverable, or baseline?

Options:

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Buy Now
Questions 245

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Options:

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Buy Now
Questions 246

In a typical project, project managers spend most of their time:

Options:

A.

Estimating

B.

Scheduling

C.

Controlling

D.

Communicating

Buy Now
Questions 247

During what project management process does the project team begin identifying risks?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 248

In the Develop Project Team process, which of the following is identified as a critical factor for a project ' s success?

Options:

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

Buy Now
Questions 249

Projects are separated into phases or subprojects; these phases include:

Options:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Buy Now
Questions 250

During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.

What should the project manager do?

Options:

A.

Inform the stakeholders that the stakeholder register needs to be recreated, as the team does not understand the requirements.

B.

Share the project management plan with the team members again to bring them up to speed on the requirements.

C.

Schedule additional meetings with the customer to explain the requirements for each deliverable at length.

D.

Revisit the work breakdown structure (WBS) again during execution, as the WBS can be defined at different points in the project.

Buy Now
Questions 251

Which tool or technique is used to manage change requests and the resulting decisions?

Options:

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

Buy Now
Questions 252

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Questions 253

A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.

Which of the following project delivery approaches should be recommended?

Options:

A.

Adaptive

B.

Hybrid

C.

Extreme

D.

Traditional

Buy Now
Questions 254

The organization ' s perceived balance between risk taking and risk avoidance is reflected in the risk:

Options:

A.

Responses

B.

Appetite

C.

Tolerance

D.

Attitude

Buy Now
Questions 255

The process of formalizing acceptance of the completed project deliverables is known as:

Options:

A.

Validate Scope.

B.

Close Project or Phase.

C.

Control Quality.

D.

Verify Scope.

Buy Now
Questions 256

In the Plan Stakeholder Management process, expert judgment is used to:

Options:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Buy Now
Questions 257

An element of the project scope statement is:

Options:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Buy Now
Questions 258

Which is a key skill set in PMI’s Talent Triangle?

Options:

A.

Project excellence and scope management

B.

Strategic and business management

C.

Scope management and business management

D.

Financial management and people management

Buy Now
Questions 259

The process for performing variance analysis may vary, depending on:

Options:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Buy Now
Questions 260

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

Options:

A.

0.88

B.

1.12

C.

0.58

D.

1.58

Buy Now
Questions 261

Which of these is a hybrid contract?

Options:

A.

Cost plus award fee (CPAF)

B.

Firm fixed price (FFP)

C.

Fixed price incentive fee (FPIF)

D.

Time and material (TandM)

Buy Now
Questions 262

Which of the following is a tool or technique used in the Determine Budget process?

Options:

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Buy Now
Questions 263

A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?

Options:

A.

-9

B.

37

C.

9

D.

322

Buy Now
Questions 264

Which process occurs within the Monitoring and Controlling Process Group?

Options:

A.

Control Costs

B.

Plan Quality

C.

Perform Quantitative Risk Analysis

D.

Determine Budget

Buy Now
Questions 265

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Buy Now
Questions 266

A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?

Options:

A.

Resource management plan and lessons learned register

B.

Resource management plan and cost baseline

C.

Resource management plan and procurement management plan

D.

Resource management plan and preassignment

Buy Now
Questions 267

The integrative nature of project management requires which Process Group to interact with the other Process Groups?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Project Management

Buy Now
Questions 268

A required input for Create WBS is a project:

Options:

A.

quality plan.

B.

schedule network.

C.

management document update.

D.

scope statement.

Buy Now
Questions 269

To which process is work performance information an input?

Options:

A.

Administer Procurements

B.

Direct and Manage Project Execution

C.

Create WBS

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 270

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Buy Now
Questions 271

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Buy Now
Questions 272

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

Options:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Buy Now
Questions 273

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Buy Now
Questions 274

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Questions 275

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Buy Now
Questions 276

A project charter is an output of which Process Group?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Closing

Buy Now
Questions 277

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Buy Now
Questions 278

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

Options:

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Buy Now
Questions 279

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?

Options:

A.

Policy compliance and auditing

B.

Standards and compliance

C.

Review of lessons learned

D.

Test and inspection planning

Buy Now
Questions 280

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

Options:

A.

Analysis

B.

Appetite

C.

Tolerance

D.

Response

Buy Now
Questions 281

What are the two most common contract types used in a project?

Options:

A.

Cost plus award fee (CPAF) contract and fixed price contract

B.

Fixed price contract and cost-reimbursable contract

C.

Cost-reimbursable contract and time and material (TandM) contract

D.

Time and material (TandM) contract and cost plus award fee (CPAF) contract

Buy Now
Questions 282

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Options:

A.

Define Activities

B.

Direct and Manage Project Work

C.

Develop Project Management Plan

D.

Develop Project Charter

Buy Now
Questions 283

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Buy Now
Questions 284

Which quality control technique illustrates the 80/20 principle?

Options:

A.

Ishikawa diagram

B.

Control chart

C.

Run chart

D.

Pareto chart

Buy Now
Questions 285

Perform Quality Control is accomplished by:

Options:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Buy Now
Questions 286

An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?

Options:

A.

Project charter

B.

Product roadmap

C.

Project management plan

D.

Product requirements

Buy Now
Questions 287

Which is an output from Distribute Information?

Options:

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

Buy Now
Questions 288

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Buy Now
Questions 289

A project manager needs to develop a product roadmap. Which artifact category is a product roadmap?

Options:

A.

Report artifact

B.

Strategic artifact

C.

Baseline artifact

D.

Plan artifact

Buy Now
Questions 290

Development of the benefits management plan occurs in which stage of the project life cycle?

Options:

A.

Starting the project

B.

Organizing the project

C.

Completing pre-project work

D.

Executing the product

Buy Now
Questions 291

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Buy Now
Questions 292

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

Options:

A.

The frequency of the quality and review steps

B.

The number of deliverables

C.

The duration of each of the quality and review steps

D.

The tools used in the quality and review steps

Buy Now
Questions 293

The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?

Options:

A.

Accepted deliverables

B.

planning packages

C.

Verified deliverables

D.

Work packages

Buy Now
Questions 294

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

Options:

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Buy Now
Questions 295

A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built. What activity is the team involved in?

Options:

A.

Creating a work breakdown structure (WBS)

B.

Identifying risks and issues in the project

C.

Developing a stakeholder engagement plan

D.

Developing a communications management plan

Buy Now
Questions 296

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Buy Now
Questions 297

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

Options:

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Project management processes

D.

Project scope management plan

Buy Now
Questions 298

Which of the following types of a dependency determination is used to define the sequence of activities?

Options:

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Buy Now
Questions 299

The probability and impact matrix is primarily used to:

Options:

A.

Quantify risk issues for trends during a quality audit.

B.

Develop a risk register for risk planning.

C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.

Buy Now
Questions 300

What is the responsibility of the project manager and the functional manager respectively?

Options:

A.

Oversight for an administrative area; a facet of the core business

B.

Achieving the project objectives; providing management oversight for an administrative area

C.

A facet of the core business; achieving the project objectives

D.

Both are responsible for achieving the project objectives.

Buy Now
Questions 301

During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project ' s components. What should be included in the WBS?

Options:

A.

Activity dependencies

B.

Work package risks

C.

Description of work

D.

Resource estimates

Buy Now
Questions 302

Plan Risk Management is the process of defining how to:

Options:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Buy Now
Questions 303

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Buy Now
Questions 304

What does the creation of a project management plan accomplish?

Options:

A.

Defines the basis of all project work and how it will be performed

B.

Acknowledges the existence of a project and defines its high-level information

C.

Authorizes the project manager to apply organizational resources to project activities

D.

Provides the project manager with organizational standards, policies, processes, and procedures

Buy Now
Questions 305

Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?

Options:

A.

Learn methods

B.

collaborative teams

C.

Generalizing specialists

D.

Knowledge sharing

Buy Now
Questions 306

Project management processes ensure the:

Options:

A.

alignment with organizational strategy

B.

efficient means to achieve the project objectives

C.

performance of the project team

D.

effective flow of the project throughout its life cycle

Buy Now
Questions 307

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

Options:

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Buy Now
Questions 308

Which is the correct formula for calculating expected activity cost for three-point estimating?

Options:

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Buy Now
Questions 309

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

Options:

A.

Power interest grid

B.

Stakeholder cube

C.

Salience model

D.

Directions of influence

Buy Now
Questions 310

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options:

A.

Discuss the processes and deliverables needed to meet the project objectives with the team.

B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.

C.

Identify the processes and deliverables for only the current phase first.

D.

Follow organizational methodology and produce all required deliverables.

Buy Now
Questions 311

Project governance refers to framework.......which of the following is a portfolio?

Pioject governance refers lo framework, functions, and processes that guide project management activates with a defined hierarchy between projects, programs and poctfotos. According to this hierarchy, which ot Die following is a portfolio?

Options:

A.

A portfolio is a group of projects, programs, subsidiary portfolios and operations managed together to achieve strategic objectives.

B.

A portfolio is the mam project of the company, supervised directly by the CEO.

C.

A portfolio is a group of projects managed by the same project manager.

D.

A portfolio is a group of related proiecls, programs, subsidary portfolios, and operation*, thai provides similar products or services.

Buy Now
Questions 312

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

Options:

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Buy Now
Questions 313

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

Options:

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Buy Now
Questions 314

What process is included in Project Integration Management?

Options:

A.

Monitor and Control Project Work

B.

Control Scope

C.

Control Schedule

D.

Develop Team

Buy Now
Questions 315

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Buy Now
Questions 316

A few project team members are having issues understanding the requirements as described. Which action should be taken to resolve this issue?

Options:

A.

Review the requirements traceability matrix and set up a meeting with the business analyst and key stakeholders.

B.

Review the requirements traceability matrix, the business analysis communications management plan, and set up a meeting with the business analyst and key stakeholders.

C.

Review the business analysis communications management plan and set up a meeting with the business analyst and key stakeholders.

D.

Review the project management plan and set up a meeting with the project manager and key stakeholders.

Buy Now
Questions 317

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Buy Now
Questions 318

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Buy Now
Questions 319

An input to the Perform Quantitative Risk Analysis process is the:

Options:

A.

quality management plan.

B.

project management plan.

C.

communications management plan.

D.

schedule management plan.

Buy Now
Questions 320

Change requests are processed for review and disposition according to which process?

Options:

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Questions 321

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Buy Now
Questions 322

Which is the appropriate tool to identify the possible correlation two elements in aprocess?

Options:

A.

Scatter diagram

B.

Cause and effect diagram

C.

Histogram

D.

Control charts

Buy Now
Questions 323

In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

Options:

A.

Ensures a thorough unit test case coverage

B.

Ensures an accurate reflection of the stakeholders ' intentions

C.

Ensures that the business problem is solved

D.

Ensures the successful delivery of business value

Buy Now
Questions 324

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

Options:

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Buy Now
Questions 325

Which of the following includes how requirements activities will be planned, tracked, and reported?

Options:

A.

Configuration management plan

B.

Scope baseline

C.

Requirements management plan

D.

Schedule baseline

Buy Now
Questions 326

Which project risk listed in the table below is most likely to occur?

CAPM Question 326

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 327

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Buy Now
Questions 328

What is the difference between verified and accepted deliverables?

Options:

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.

B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.

C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.

D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.

Buy Now
Questions 329

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

Options:

A.

cultural differences of team members

B.

possibility of communication misunderstandings

C.

costs associated with travel

D.

costs associated with technology

Buy Now
Questions 330

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

Options:

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Buy Now
Questions 331

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Buy Now
Questions 332

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Buy Now
Questions 333

In which of the Risk Management processes is the project charter used as an input?

Options:

A.

Plan Risk Responses

B.

Implement Risk Responses

C.

Plan Risk Management

D.

Perform Quantitative Risk Responses

Buy Now
Questions 334

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Buy Now
Questions 335

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Buy Now
Questions 336

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Buy Now
Questions 337

In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process ' ?

Options:

A.

Assumption log

B.

Milestone list

C.

Business case

D.

Risk register

Buy Now
Questions 338

Which of the following does a portfolio combine?

Options:

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Buy Now
Questions 339

Which process requires implementation of approved changes?

Options:

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Buy Now
Questions 340

What is one of the main purposes of the project chatter?

Options:

A.

Formal authorization of the existence of the project

B.

Formal acceptance of the project management plan

C.

Formal approval of the detailed project budget

D.

Formal definition of stakeholder roles and responsibilities

Buy Now
Questions 341

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

Options:

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Buy Now
Questions 342

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Buy Now
Questions 343

A project manager has just consolidated the project risk management plan and sent it to the sponsor. The sponsor wants to reduce the likelihood of a specific risk.

Which approach should the project manager take?

Options:

A.

Escalate

B.

Mitigate

C.

Avoid

D.

Transfer

Buy Now
Questions 344

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

Options:

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Buy Now
Questions 345

What tool or technique will establish expected behaviors for project team members?

Options:

A.

Ground rules

B.

Decision mating

C.

Power/influence grid

D.

Stakeholder engagement assessment matrix

Buy Now
Questions 346

A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team ' s workflow at any moment, the project manager will need to restrict the maximum amount of activities to be performed.

Which element will the project manager handle?

Options:

A.

Capacity limit

B.

Pull system

C.

Work in progress

D.

Virtual board

Buy Now
Questions 347

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

Options:

A.

Defining, sequencing, estimating activity duration, and developing a schedule model are so tightly inked that they are viewed as a single process.

B.

The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge

C.

An iteractive scheduling and on-demand, pull-based scheduling will be required.

D.

To address the full delivery schedule, a range of techniques may be needed and then need to be adapted

Buy Now
Questions 348

A construction project is underway, and during... tasks impacted the painting work

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?

Options:

A.

Finish-to-Finish (FF)

B.

Start-to-Finish (SF)

C.

Finish-to-Start(FS)

D.

Start-to-Slart(SS)

Buy Now
Questions 349

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

Buy Now
Questions 350

How can emotional intelligence (EI) be effective in project management?

Options:

A.

By preparing a project plan and managing the team members

B.

By planning for user acceptance testing

C.

By establishing project resource allocation

D.

By reducing tension and increasing cooperation among team members

Buy Now
Questions 351

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

Options:

A.

Direct

B.

Interactive

C.

Pull

D.

Push

Buy Now
Questions 352

When closing a project or phase, part of the process may require the use of which type of analysis?

Options:

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Buy Now
Questions 353

An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

Which two of the following items should be included in the planning? (Choose two)

Options:

A.

Daily scrum

B.

Sprint backlog

C.

Sprint review

D.

Increments

E.

Sprint retrospective

Buy Now
Questions 354

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Buy Now
Questions 355

Which of the following is an example of schedule compression?

Options:

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Buy Now
Questions 356

Which of the following tasks focuses on decomposing work packages?

Options:

A.

Adjust duration estimates

B.

Define activities

C.

Complete rolling wave planning

D.

Develop milestone list

Buy Now
Questions 357

When developing a schedule which tools and techniques should a project manager use?

Options:

A.

Schedule Networfc Analysis and Critical Path Method

B.

Activity list and expert Judgement

C.

Milestone Iist and Risk Register

D.

Basis ot estimates and Rolling Wave Planning

Buy Now
Questions 358

Under which circumstances should multiple projects be grouped in a program?

Options:

A.

When they are needed to accomplish a set of goals and objectives for an organization

B.

When they have the same project manager and the same organizational unit

C.

When they have the same scope, budget, and schedule

D.

When they are from the same unit of the organization

Buy Now
Questions 359

Company A’s accountant sends notification about a change in the company’s tax classification.

What would a project have to be initiated?

Options:

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Buy Now
Questions 360

The following is a network diagram for a project.

CAPM Question 360

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Buy Now
Questions 361

What is an objective of the Develop Project Team process?

Options:

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Buy Now
Questions 362

Which risk response strategy is common for both positive and negative risks?

Options:

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Buy Now
Questions 363

A project manager is working on the communications management plan. Which of these documents are inputs to consider?

Options:

A.

Stakeholder engagement plan and organizational process assets

B.

Project schedule and stakeholder register

C.

Quality management plan and risk register

D.

Basis of estimates and scope baseline

Buy Now
Questions 364

Which of the following is provided by the critical path method?

Options:

A.

Schedule float

B.

Earned value (EV)

C.

Total float

D.

Schedule value

Buy Now
Questions 365

Which of the following is an output of the Distribute Information process?

Options:

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Buy Now
Questions 366

Which process uses expert judgment to manage project resources?

Options:

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Manage Team

D.

Both A and B

Buy Now
Questions 367

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Buy Now
Questions 368

Project contracts generally fall into which of the following three broad categories?

Options:

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Buy Now
Questions 369

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Buy Now
Questions 370

An example of a group decision-making technique is:

Options:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Buy Now
Questions 371

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Buy Now
Questions 372

What communication methods would a project manager use for overall effective project communication?

Options:

A.

Interactive communication, push communication, interpersonal communication

B.

Interactive communication, push communication, pull communication

C.

Push communication, pull communication, interpersonal communication

D.

Pull communication, interactive communication, interpersonal communication

Buy Now
Questions 373

High-level project risks are included in which document?

Options:

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

Buy Now
Questions 374

Success is measured by benefits realization for a:

Options:

A.

strategic plan

B.

project

C.

portfolio

D.

program

Buy Now
Questions 375

A newly developed project team is working together, building trust and adjusting its work habits to support the team What stage of the Tuckman ladder does this describe?

Options:

A.

Forming

B.

Norming

C.

Storming

D.

Performing

Buy Now
Questions 376

During project selection, which factor is most important?

Options:

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Buy Now
Questions 377

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

Options:

A.

Communication models.

B.

Stakeholder participation.

C.

Expert judgment

D.

Enterprise environmental factors.

Buy Now
Questions 378

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Buy Now
Questions 379

Which method should be used to elicit a cross-functional requirement?

Options:

A.

Focus groups

B.

Prototyping

C.

Facilitated workshops

D.

Interviews

Buy Now
Questions 380

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Buy Now
Questions 381

A project ' s business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology?

Options:

A.

Must have, should have, could have, won ' t have (MoSCoW)

B.

Strengths, weaknesses, opportunities, threats (SWOT)

C.

Work breakdown structure (WBS)

D.

Responsible, accountable, consulted, informed (RACI)

Buy Now
Questions 382

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Closes Project or Phase

D.

Perform itegrated Change Control

Buy Now
Questions 383

Which of the following strategic considerations often results in project authorization?

Options:

A.

Customer requests and/or issue resolution

B.

Stakeholder expectations and/or strategic opportunity (business need)

C.

Technological advancement and/or senior executive request

D.

Market demand and/or legal requirements

Buy Now
Questions 384

A project manager needs information to finish their work on the project charter for a clinical trial.

Which procedure is used to obtain the requirements information?

Options:

A.

Forecasting

B.

Simulations

C.

Elicitation

D.

Quantitative analysis

Buy Now
Questions 385

What should a project manager use to determine how much money is needed to complete a project?

Options:

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Buy Now
Questions 386

Which statement describes the various purposes of project scheduling?

Options:

A.

Define the policies, rules, and techniques to run a schedule; serve as a tool to manage stakeholder expectations; and serve as a base for backlog management

B.

Define how and when deliverables will be completed, serve as communication tool, and serve as a base for performance reporting

C.

Define the life cycle, traditional or agile approach, and tools to control schedule; serve as a reference for scope management; and serve as a base for risk management

D.

Define activities, sequences, duration, and dependencies, serve as a reference for resource allocation, serve as a base for earned value analysis.

Buy Now
Questions 387

In a project, the cost performance indicator (CPI) is less than 1 and the schedule performance indicator (SPI) is more than 1. What is the status of the project?

Options:

A.

The project is over budget and behind schedule.

B.

The project is over budget and ahead of schedule.

C.

The project is under budget and behind schedule.

D.

The project is under budget and ahead of schedule.

Buy Now
Questions 388

The project manager has following information about duration for an activity:

* Most likely [tM] - 15 days

* Pessimistic [tP] - 20 days

* Optimistic [tO] - 10 days

What is the estimated duration of this activity, according to the triangular distribution technique?

Options:

A.

10 days

B.

15 days

C.

12.5 days

D.

5 days

Buy Now
Questions 389

Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three)

Options:

A.

Focus groups

B.

Facilitation

C.

Meeting management

D.

Conflict management

E.

Interviews

Buy Now
Questions 390

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Options:

A.

Feedback analysis

B.

Stakeholder analysis

C.

Communication management plan

D.

Stakeholder management plan

Buy Now
Questions 391

What tool or technique is primarily used to plan risk responses ' ?

Options:

A.

Risk categorization

B.

Project risk document updates

C.

Strategies for overall project risk

D.

Risk management plan

Buy Now
Questions 392

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

Options:

A.

Get expert judgment.

B.

Count on personal experience.

C.

Ask project sponsors.

D.

Delay the project until technical uncertainty is clarified

Buy Now
Questions 393

Which of the following is an information gathering technique in Identify Risks?

Options:

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

Buy Now
Questions 394

The purpose of the Project Communications Management Knowledge Area is to:

Options:

A.

Monitor and control communications throughout the entire project life cycle.

B.

Maintain an optimal flow of information among all project participants.

C.

Develop an appropriate approach for project communications.

D.

Ensure timely and appropriate collection of project information.

Buy Now
Questions 395

During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?

Options:

A.

Burndown chart

B.

Velocity chart

C.

Definition of ready (DoR)

D.

Definition of done (DoD)

Buy Now
Questions 396

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Buy Now
Questions 397

A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.

Which modeling tool best describes this process?

Options:

A.

Traceability

B.

User interface design

C.

Use case

D.

Wireframe

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jun 29, 2026
Questions: 1326

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now CAPM testing engine

PDF (Q&A)

$31.5  $104.99
buy now CAPM pdf
dumpsmate guaranteed to pass

24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 29 Jun 2026