C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Questions and Answers

Questions 4

How do you reduce the scheduled duration of internally-processed activities if the time period within which the activities are to be scheduled is not long enough to process all activities?

Please choose the correct answer.

Response:

Options:

A.

Reduction

B.

Scheduling breech

C.

Milestones

D.

Capacity breech

Buy Now
Questions 5

In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.

How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?

Please choose the correct answer.

Response:

Options:

A.

The costs are distributed evenly over the earliest dates in the activity

B.

The system uses the key from the work center

C.

System uses valuation variant

D.

Costing key is considered

Buy Now
Questions 6

In which type of billing do you assign the posting to the down payment request when you post the incoming payment for a down payment?

Please choose the correct answer.

Response:

Options:

A.

Milestone billing

B.

Due date billing

C.

Sales order billing

D.

Locked billing

Buy Now
Questions 7

Which parameters determine if the network header or network activities are cost objects?

There are 2 correct answers to this question.

Response:

Options:

A.

Plant

B.

Activity

C.

Tasks

D.

Network type

Buy Now
Questions 8

How can material components be assigned to network activities?

There are 3 correct answers to this question.

Response:

Options:

A.

By assigning them manually

B.

Using the bill of materials transfer

C.

Using assigned sales orders

D.

Using ProMan

E.

Using the Internet-based catalog

Buy Now
Questions 9

Which of the following aids in calculating actual overheads based on the costing sheet and overhead key entered?

There are 3 correct answers to this question.

Response:

Options:

A.

WBS element

B.

Assignment

C.

Network header

D.

Network activity

Buy Now
Questions 10

What are the different views available for capacity planning and work center planning?

There are 2 correct answers to this question.

Response:

Options:

A.

Work center view

B.

Capacity planning view

C.

Periodic view

D.

Project view

Buy Now
Questions 11

In Structure Information System which transactions allow you to analyze and edit the entire hierarchical structure of a project including documents, PS texts, networks, other orders, investment programs, and SD documents?

There are 2 correct answers to this question.

Response:

Options:

A.

Network overview

B.

Order overview

C.

Structure overview

D.

Project structure overview

Buy Now
Questions 12

What are the three areas of the project screen?

There are 3 correct answers to this question.

Response:

Options:

A.

Structure tree

B.

Work area and template area

C.

Task list area

D.

Work area

Buy Now
Questions 13

Where can you define that a network is a "header-account assigned" or "activity-account assigned"?

Options:

A.

Network profile

B.

Parameters for the network type

C.

Project profile

D.

Network type

Buy Now
Questions 14

Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations?

Please choose the correct answer.

Response:

Options:

A.

Project reporting

B.

Progress analysis work bench

C.

Project analysis Team View

D.

Project progress analysis

Buy Now
Questions 15

Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?

There are 3 correct answers to this question.

Response:

Options:

A.

Scheduling of subnetworks and subordinate internal orders

B.

Introduction of a configurable level concept for the targeted selection of

C.

Scheduling that takes available capacities and material availability into

D.

Improve performance through the targeted selection of subnetworks to be

E.

Detailed subnetwork monitor

Buy Now
Questions 16

Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?

Please choose the correct answer.

Response:

Options:

A.

Control key

B.

Confirmation key

C.

Scheduling key

D.

Customizing key

Buy Now
Questions 17

In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as?

Please choose the correct answer.

Response:

Options:

A.

Deviations

B.

Time gaps

C.

Floats

D.

High priority

Buy Now
Questions 18

How do you create a detailed payment schedule if the expense for an external activity or purchased component is not paid with a single invoice?

Please choose the correct answer.

Response:

Options:

A.

Invoicing plan

B.

Billing plan

C.

Credit memos

D.

Detailed billing plan

Buy Now
Questions 19

Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.

What is the status that must be set before you can enter actual start and actual end dates?

There are 2 correct answers to this question.

Response:

Options:

A.

Partially released

B.

Released

C.

Partially set

D.

Partially finished

Buy Now
Questions 20

What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?

Please choose the correct answer.

Response:

Options:

A.

Workflow indicator

B.

Workflow purchase order change indicator

C.

Workflow change indicator

D.

Purchase order change indicator

Buy Now
Questions 21

When you assign material components using the BOM transfer function, the system uses the Reference Point field in the BOM items and activities to establish a logical connection between which items?

There are 2 correct answers to this question.

Response:

Options:

A.

Individual BOM items

B.

Multiple BOM items

C.

Multi level BOM

D.

Network activities

Buy Now
Questions 22

In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?

There are 3 correct answers to this question.

Response:

Options:

A.

This assignment can then be used to display the planned costs of the orders of the project

B.

This assignment can then be used to display the unit costs of the orders of the project

C.

It can be copied to a new project

D.

Cost planning can be moved automatically along with the activities

Buy Now
Questions 23

Most of the reports in the SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data?

Please choose the correct the answer.

Response:

Options:

A.

Hierarchical Reports

B.

Individual Overviews

C.

Reports by Cost Element

D.

Structure Overview

Buy Now
Questions 24

Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned?

There are 3 correct answers to this question.

Response:

Options:

A.

Persons

B.

Organizational units

C.

Jobs

D.

Positions

Buy Now
Exam Code: C_TPLM22_67
Exam Name: SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
Last Update: Nov 26, 2024
Questions: 165

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now C_TPLM22_67 testing engine

PDF (Q&A)

$36.75  $104.99
buy now C_TPLM22_67 pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 03 Dec 2024