Winter Sale - Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dpm65

APM-PMQ APM Project Management Qualification (PMQ) Exam Questions and Answers

Questions 4

You have been appointed as project manager on a transformation project which is looking to improve the recruitment process for a large engineering company. The project has a clearly defined scope, as well as clear milestones and timescales. A hybrid life cycle is being used for this project.

State a total of five features from both linear and iterative life cycles and describe why you recommend incorporating each one in this scenario.

Options:

Buy Now
Questions 5

You are a project manager taking over a project that’s in the definition phase. The project sponsor asks you to prepare for an upcoming budget review as they have concerns regarding the lack of cost control shown by the project to date.

Which of the following actions would best improve the project sponsor's confidence in how you will control costs?

Options:

A.

Create a work breakdown structure.

B.

Create a cost breakdown structure.

C.

Create an earned value report.

D.

Create a financial appraisal.

Buy Now
Questions 6

Structure is the most common temporary structure used to manage projects. This allows the balance of authority between the functional line manager and the project manager. In a permanent structure, allocated tasks will match an individual’s capability so may be more repetitive and less varied.

Options:

A.

Matrix Structure

B.

Functional Structure

C.

Projectized Structure

D.

Hybrid Structure

Buy Now
Questions 7

Which of the following are not typical responses to risks?

    Complete root cause analysis to understand why the situation has occurred.

    Reduce the probability of the threat occurring or the impact on the project.

    Change objectives or practices to change the cause of the threat so it can no longer occur.

    There are no acceptable or viable approaches to take to avoid or reduce, so the threat and any residual risk must be managed.

    Prepare a risk management plan to document the risk and give it to your sponsor.

    Pass the responsibility for bearing the impact of the threat from one party to another.

Options:

A.

2 and 6.

B.

4 and 5.

C.

3 and 4.

D.

1 and 5.

Buy Now
Questions 8

You are managing a large UK-based team to design and build a multi-billion dollar railway in the Middle East. You have completed a stakeholder analysis and identified a diverse range of stakeholders, each with differing levels of power and interest in the project.

Describe the engagement approach you would take with both of these stakeholder groups and why you would take that approach.

Options:

Buy Now
Questions 9

Identify one of the five steps of a benefits management plan and state one action you would take to apply it to ensure the successful realization of project benefits.

Options:

Buy Now
Questions 10

You are managing a construction project aimed at developing a new eco-friendly office building. You are tasked with ensuring that sustainability measures are effectively monitored and reported.

At which point in the project life cycle should you implement sustainability measures?

Options:

A.

Sustainability measures should be captured at the building's completion and reported in the final project report.

B.

Sustainability measures should only be reviewed during major project milestones and construction stopped if targets are not being met.

C.

Sustainability measures should be monitored continuously and integrated into project planning, before construction begins.

D.

Sustainability measures should be implemented once construction has begun and reported if significant issues arise.

Buy Now
Questions 11

You are in the design phase of a project to deliver offices on a newly acquired plot of land. You have now completed extra surveys and discovered that the ground conditions are a lot softer than expected, meaning the design and delivery will be far more complex and costly. You did not account for this in your risk register.

Which of the following statements about the project business case is true?

Options:

A.

The business case contained assumptions which should be reviewed against the cost-benefit analysis.

B.

There is a strong strategic case for the project to continue, even if it is late or over budget.

C.

The business case has already been signed off, so the project should continue as planned.

D.

The project sponsor did not properly evaluate all available options in the business case.

Buy Now
Questions 12

Which of the following statements best describes the purpose of an integrated project management plan?

Options:

A.

It is a document used exclusively within linear project life cycles to set the project’s baseline.

B.

It is managed by the project sponsor to track the project’s progress against the business case.

C.

It sets the baseline for the project and cannot be changed after the definition phase.

D.

It details the "why," "what," "when," "who," "how," "where," and "how much" of a project.

Buy Now
Exam Code: APM-PMQ
Exam Name: APM Project Management Qualification (PMQ) Exam
Last Update: Jan 16, 2025
Questions: 40

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now APM-PMQ testing engine

PDF (Q&A)

$36.75  $104.99
buy now APM-PMQ pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 18 Jan 2025