Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
![AgilePM-Practitioner Question 18](/img/media/APMG-International/AgilePM-Practitioner/3.1/d950e8e7-1fa6-4311-87ed-a53f7bebaa3b.png)
Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
BECAUSE
The aim of the Investigation step within each Timebox is to complete as much of
the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the
imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the
work of each Timebox.
![AgilePM-Practitioner Question 18](/img/media/APMG-International/AgilePM-Practitioner/3.1/794e8e59-75fe-43f1-b977-b3ea93a98885.png)
![AgilePM-Practitioner Question 18](/img/media/APMG-International/AgilePM-Practitioner/3.1/f00351d2-75dc-44f0-872c-e77b84a0d96c.png)