Black Friday Special - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Questions 4

Which 2 individuals would be suitable for the role of Workshop Facilitator?

Options:

A.

Team Leader

B.

IT Operations Manager

C.

Marketing Director

D.

Software Developer

E.

Project Manager

Buy Now
Questions 5

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels' Senior Management Team.

Buy Now
Questions 6

Which 2 actions should the Workshop Facilitator take when preparing for the workshop?

Options:

A.

Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.

B.

Invite the Marketing Director to create a summary of the content they believe the system should hold and why.

C.

Assign ownership of the workshop to the Software Developer.

D.

Ask the IT Operations Manager to prepare the agenda for the workshop.

E.

Research other hotel reservation systems to form an opinion on what the content should be.

Buy Now
Questions 7

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.

2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.

3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.

4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.

5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.

Column 2:

A) Thought

B) Action

C) Conversation

AgilePM-Practitioner Question 7

Options:

Buy Now
Questions 8

What action should the Project Manager take during the Close-Out of Timebox C?

Options:

A.

Remove 'Aspects' from the supplier list for all future projects.

B.

Carry out final checks to ensure the deliverables of Timebox C meet the expected standards.

C.

Ensure that lessons are learned so that similar issues do not occur in future Timeboxes.

D.

Initiate the work required to complete the windows to the required standard.

Buy Now
Questions 9

During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what

needed to be done before these would be acceptable.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because this will enable the Solution Development Team to ensure they are on track to deliver a viable solution.

B.

Yes, because this allows each team member working in the Timebox to provide a short progress report and raise any issues that hinder their progress.

C.

No, because early and frequent visibility of the product features will maintain engagement with the stakeholders.

D.

No, because only members of the Solution Development Team are permitted to attend Review Sessions.

Buy Now
Questions 10

Find out who is responsible for challenging the priority of requirements and deal with them accordingly.

Options:

A.

Ask the Team Leader to resolve the situation.

B.

Ask the Marketing Director to explain to the Solution Development Team why the windows are a Must Have priority.

C.

Remove empowerment from the Solution Development Team.

D.

What action should the Project Manager take when dealing with the Solution Development Team's argument that the windows should not be a Must Have priority?

Buy Now
Questions 11

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?

Options:

A.

Paper-based drawings are to be used for each option being considered for the building and gardens.

B.

The SAD must include a physically-built miniature model of the Hoy Hall building.

C.

The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.

D.

The views of the 'Hoy for Hoy Hall' Action Group members are NOT relevant to the business decision made by Architecture Angels' Finance Director when approving the final option.

E.

The SAD should contain high-level costs for all elements of each solution option.

Buy Now
Questions 12

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Questions 13

Which 2 statements represent appropriate entries for the Prioritised

Requirements List?

Options:

A.

Creation of a new coffee shop insurance product on the existing website

is expected to increase the insurance company's revenues by up to 10%

per week.

B.

All correspondence sent to coffee shop owners by the new system should

contain the XAN logo in the top left hand corner of the page.

C.

Further website developments to allow existing customers to access

services online are NOT to be included within the scope of this project.

D.

The Business Visionary will provide a formal acceptance of the coffee

shop insurance product.

E.

An assessment will be made of the effectiveness of the techniques used

on the project, in line with the principles of Agile Project Management.

Buy Now
Questions 14

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

AgilePM-Practitioner Question 14

Options:

Buy Now
Questions 15

Which 2 statements represent appropriate entries for the Development

Approach Definition?

Options:

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called 'WebMatrix' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Buy Now
Questions 16

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?

Options:

A.

Change the end date of the Timebox.

B.

Ensure that this issue is escalated to the project level roles.

C.

Amend the end date in the Delivery Plan.

D.

Accept that the Must Have requirements will not be delivered on time.

Buy Now
Questions 17

A difference of opinion on the outcome of an earlier project has created a

'them and us' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

Options:

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.

Buy Now
Questions 18

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?

Options:

A.

Refuse to discuss any detailed requirements in the early phases.

B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.

C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.

D.

Capture the Marketing Director's requirements in detail but leave the

input of others until later in the project.

Buy Now
Questions 19

Answer the following questions about the contents of the DSDM

products.

Each of the following questions includes true statements about the project

but only two statements are appropriate entries for the DSDM product

identified.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 statements represent appropriate entries for the Business Case?

Options:

A.

A list of high-level functional and non-functional requirements that the

project should meet written as User Stories.

B.

Coffee shops that sell Fairtrade products and alcohol from local breweries

out perform other coffee shops in the market.

C.

The Sales Manager has been asked to produce a report within the next

two days showing the number of generic insurance policies sold to coffee

shops over the past three years.

D.

The Sales Manager has calculated that the new coffee shop insurance

product will increase revenues by 10% each week.

E.

Market research shows that the number of coffee shop patrons taking

legal action against retailers has increased by 200% over the past two

years.

Buy Now
Questions 20

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Questions 21

The Web Content Manager has provided the Web Developer with a mock up

of the 'Contact Us' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads 'Delete' instead of 'Cancel'.

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Buy Now
Questions 22

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

Options:

A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Buy Now
Questions 23

Which 2 actions should the Technical Coordinator take to implement the new

Must Have requirement?

Options:

A.

Ensure that the latest version of the website design in the Solution

Architecture Definition is provided to all members of the Solution

Development Team.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

D.

Consolidate and circulate an agenda for the workshop.

E.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Nov 22, 2024
Questions: 78

PDF + Testing Engine

$49.5  $164.99

Testing Engine

$37.5  $124.99
buy now AgilePM-Practitioner testing engine

PDF (Q&A)

$31.5  $104.99
buy now AgilePM-Practitioner pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 23 Nov 2024