AD0-E903 Adobe Workfront Project Manager Professional Questions and Answers

Questions 4

Which date type should an assignee update to change the completion date of a task?

Options:

A.

Actual Completion Date

B.

Commit Date

C.

Planned Completion Date

D.

Projected Start Date

Buy Now
Questions 5

A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a new report. In the filter, update the project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date and set the default view to “Calendar View.”

B.

Visit the Calendars page and create a new calendar. In the filter, update the date field to Planned Dates and update the Project Owner ID field with the project manager’s name. Set the color to purple.

C.

Visit the Reports page and create a new calendar. In the filter, update the Project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date.

Buy Now
Questions 6

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

Options:

A.

Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A's access level.

B.

Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.

C.

Share the program with Program Manager A with Manage access and remove Program Manager A's Manage access on the portfolio.

Buy Now
Questions 7

When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?

Options:

A.

Add a custom form

B.

Attach a template to the project

C.

Add tasks

Buy Now
Questions 8

A team lead wants to see all hours that have been logged this month by members of the team lead’s home team, organized by project. How should the team lead create this view?

Options:

A.

Navigate to a specific project and open the Hours tab. Filter the view by Owner > Home Team ID > Equal > [Name of Home Team] and Hour > Entry Date > This Month. Repeat on all projects in which team members are assigned.

B.

Visit the Reports area and create a new Hour report. Add the filters for Owner > Home Team ID > Equal > [Name of Home Team] and Hour > Entry Date > This Month. Group the results by Project > Name.

C.

Visit the Reports area and create a new Hour report. Add the filters for Hour > Entry Date > This Month and Project Status > Equal > Complete. Group the results by Project > Name.

D.

Visit the Teams landing page and on the Workload Balancer select the users' home team. Add the user filters for Task > Actual Start Date > This Month, click Apply. Update view settings and toggle on the Show remaining time setting.

Buy Now
Questions 9

How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

Options:

A.

Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.

B.

Visit the Reports page, create a new Project report, update the Project Owner ID filter with their name, and add a column for issues.

C.

Visit the Reports page, create a new Issue report, update the Project Owner ID filter with their name, and group by project name.

Buy Now
Questions 10

How is the primary assignee of a task determined?

Options:

A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

Buy Now
Questions 11

The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.

Which report grants the executive team this visibility?

Options:

A.

A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.

B.

A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.

C.

A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.

Buy Now
Questions 12

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Options:

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.

B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.

C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.

Buy Now
Questions 13

A project manager wants to see all of the assignees for each task in a project.

Which field should the manager reference to view all task assignees?

Options:

A.

Assigned To

B.

Assignments

C.

Assigned

Buy Now
Questions 14

Which date type on tasks can a project manager manually modify?

Options:

A.

Planned

B.

Estimated

C.

Projected

Buy Now
Questions 15

Which group of project elements can be used to monitor an active project’s progress?

Options:

A.

Gantt chart, project Condition, and Metrics

B.

Risks, planned hours, and resource utilization

C.

Project status, Updates, and Sharing

Buy Now
Questions 16

The art director is reviewing and approving a proof and has requested that they only get email notifications for a new proof or version. What Email alert option should be assigned to them on the workflow?

Options:

A.

Decisions and Notify recipients about this proof is selected

B.

Disabled and Notify recipients about this proof is selected

C.

Decisions and Notify recipients about this proof is not selected

D.

Disabled and Notify recipients about this proof is not selected

Buy Now
Questions 17

AD0-E903 Question 17

What do the connector lines between tasks in a Gantt chart represent?

Options:

A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Buy Now
Questions 18

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

Options:

A.

Change the Task Duration Type to Effort Driven

B.

Change the Task Duration Type to Calculated Work

C.

Change the Task Constraint to Fixed Dates

D.

Change the Task Constraint to As Soon As Possible

Buy Now
Questions 19

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

Options:

A.

Late

B.

At Risk

C.

In Trouble

Buy Now
Questions 20

Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?

Options:

A.

USER.NAME

B.

USER.ID

C.

USER.roleID

Buy Now
Questions 21

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?

Options:

A.

Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.

B.

Add a new billing rate to all tasks that involve video editing.

C.

Add a new billing rate within the project.

Buy Now
Exam Code: AD0-E903
Exam Name: Adobe Workfront Project Manager Professional
Last Update: Nov 28, 2024
Questions: 70

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now AD0-E903 testing engine

PDF (Q&A)

$36.75  $104.99
buy now AD0-E903 pdf
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 04 Dec 2024