Black Friday Special - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dm70dm

Note! The 1z0-244 Exam is no longer available.

1z0-244 Oracle EBS R12: Advanced Supply Chain Planning Questions and Answers

Questions 4

Identify the five Resource types that can be defined In Oracle.

Options:

A.

Amount

B.

Item

C.

Currency

D.

Machine

E.

Person

F.

Lead Time

G.

Miscellaneous

Buy Now
Questions 5

Which exception message appears when the planning engine schedules a Supply Order within a window whose size Is less than the minimum duration of the Supply Order?

Options:

A.

Demand quantity not satisfied

B.

Order lead time constraint

C.

Order with insufficient lead time

D.

Requirement with insufficient lead time

E.

Requirement lead time constraint

Buy Now
Questions 6

Identify three correct statements about phantom Items?

Options:

A.

One Bill of Material can represent a phantom subassembly for one parent Item, but It cannot be a stocked subassembly for another parent Item.

B.

The full cost rollup process sets the pending phantom assembly burden to 1.

C.

A phantom subassembly is a nonstocked subassembly that enables you to group the material needed to produce an assembly.

D.

Oracle Work In Process explodes through a phantom subassembly to the components as If the components were tied directly to the parent assembly.

E.

You cannot define routing for phantom assemblies the same way as other assemblies.

F.

You can compute manufacturing and cumulative lead times for phantom assemblies that have routings.

Buy Now
Questions 7

Identify five Material Constraints.

Options:

A.

Effectivity Dates of Components In Bills of Material

B.

Effectivity Dates of Operations in Routings

C.

Resource efficiency and utilization

D.

Order modifiers

E.

Change of Shift timings

F.

Tolerance fences

G.

Substitute components

Buy Now
Questions 8

Select the three correct repositories available In ASCP.

Options:

A.

Resource Data Store

B.

Operational Data Store

C.

Processing Data Store

D.

Oracle Application Data Store

E.

Item Data Store

F.

Planning Data Store

G.

Bills of Material (BOM) Data Store

Buy Now
Questions 9

The table In the Exhibit.

1z0-244 Question 9

shows Gross Requirements, Scheduled Receipts, and Project Available Balance for Item A across a five-day planning horizon. The Beginning On Hand, Lead Time, and Fixed Lot Multiplier for Item A are also provided.

What are the Planned Order Release recommendations?

Options:

A.

50 on Day 1 and 50 on Day 3.

B.

50 on Day 2 and 50 on Day 4.

C.

10 on Day 1 and 45 on Day 3

D.

10 on Day 2 and 45 on Day 4.

Buy Now
Questions 10

Select four correct Pegging methods available In ASCP.

Options:

A.

Soft Pegging

B.

Critical Resource Pegging

C.

Level of Pegging (Set the required level In BOM to which Pegging should be performed.)

D.

Hard Pegging

E.

Department Pegging (applicable to all Items that use this Department)

F.

Full Pegging

G.

End Assembly Pegging

Buy Now
Questions 11

Identify the three steps that a planner can perform during Net change Simul-ation On-line planning.

Options:

A.

Add Supplier capacity.

B.

Change BOM Supply Type for a component from Phantom to Supplier.

C.

Firm Discrete Jobs.

D.

Add new Resource availability by adding shifts.

E.

Change Item attribute order modifiers.

F.

Change Resource Basis from Item to Lot.

Buy Now
Questions 12

Your client received some plan-related constraint exception messages. Identify two such messages.

Options:

A.

Requirement is firmed late

B.

Order causes supplier capacity overload

C.

Transportation volume constraint

D.

Order lead time constraint

E.

Requirement causes resource overload

F.

Order Is firmed early

G.

Requirement with insufficient lead time

Buy Now
Questions 13

The MSO:Enable Decision Rules profile option is set to "No." Then a Constrained but not Optimized plan Is run.

Identify three statements that are true.

Options:

A.

Alternate BOMs will be considered.

B.

Alternate BOMs will not be considered.

C.

Default Demand priorities will be considered in the order of Sales Order, Forecast, and Safety Stock.

D.

Substitute items will be considered.

E.

Alternate Routings will not be considered.

Buy Now
Exam Code: 1z0-244
Exam Name: Oracle EBS R12: Advanced Supply Chain Planning
Last Update: Nov 28, 2023
Questions: 89
dumpsmate guaranteed to pass
24/7 Customer Support

DumpsMate's team of experts is always available to respond your queries on exam preparation. Get professional answers on any topic of the certification syllabus. Our experts will thoroughly satisfy you.

Site Secure

mcafee secure

TESTED 24 Nov 2024